Majority
Headnote
The plaintiffs agreed to ship to the defendants 5500 tons of railroad iron, 500 in June, 1851',. 2500 in July, and 2500 in August, as nearly as practicable. In consideration of which the defendants agreed to pay $35 per ton for said iron, together with the freight and duties; and they were to give then- notes for éach parcél of iron that should be shipped, at six, eight and ten months, on receiving each bill of lading. Ro iron was shipped in June, and only part of the specifiéd quantity was shipped in July, and only a part of what was required in August was shipped in that month; and only 2900 tons were shipped previous to the 25th of October, 1851. The 2900 tons were received by the defendants. Ro excuse was shown for not delivering the iron in due time; nor was there any proof that the defendants made any objection on account of its not being delivered in due time; nor that they made any protest against this delay; nor that they ashed for the prompt delivery of the remainder. But, having received the iron without objection, they neglected to give their notes, from that time until April, 1852, when suit was brought. Held, that the defendants, by accepting a part of the iron out of time and without objection, waived that portion of the contract which requireihthatpartto be delivered in due time, or admitted that it was delivered as soon after that time as practicable. That in either case they were bound to give their notes; and that, having neglected' to do so, this discharged the plaintiffs from their obligation to deliver the rest of the iron until the defendants should tender their notes for the portion delivered ; and entitled the plaintiffs to commence a suit, without tendering a delivery of the rest of the iron, although the time for the delivery of the whole was past before the suit was brought.The plaintiffs agreed to ship to the defendants 5500 tons of iron, 500 in June, 1851, 2500 in July, and 2500 in August, if it were practicable within that time. The defendants agreed to give their notes for each parcel of iron that should be shipped, on receiving each bill of
The contract may not be rescinded by the omission of the defendants to give their notes; but the obligation of the plaintiffs to deliver the iron is suspended by that omission. Take a familiar case, and similar to this, as an illustration. A builder agrees to erect a house for a certain sum, to be paid by installments ; a certain part of the sum when the first tier of beams is on, another certain part when the second tier of beams is on, and so on, throughout the work. He finishes the house so far as to have the first and second tier of beams on, and the owner refuses to pay him ; he waits patiently for his money until the time elapses when the whole house should have been completed, and then sues for the sums to he paid under the contract when the first and second tiers of beams should be on. The owner denies his liability, because the whole house was not finished in
This case differs from that only because in this the iron was not delivered in due time. But it is conceded that the acceptance of the iron by the defendants waived the objection as to time. That being so, the first fault, and the continuous fault, is in the defendants, in ■ not giving their notes, and makes this case precisely like the one proposed.
If a servant is employed for a year at $120 per annum, to be paid in equal monthly installments, and leaves his employer before the year is out, because he is not paid the installments due, can he not recover at the end of the year for those installments ? If a tenant hire a house for a year at a certain sum, payable in equal quarterly payments, and he is evicted, after the end of the third quarter, by h.is landlord, is the eviction any defense for the installments of rent previously due ? A contract to pay for land by installments, and for a delivery of the deed when the last installment shall be due, is different, because there the consideration on one side cannot be and is not intended to be divided into parcels ; and there it is properly decided, that if the vendor do not sue until the last installment fall due, he must aver a tender of the deed. But a different principle would apply, if the contract were to buy 100 different lots of land and to pay for each lot whenever a deed for that lot should be tendered. If the title were to fail as to one lot, the vendor could, even after the time for the delivery -of all was expired, recover for the ninety-nine lots conveyed, and justice would be done in allowing him damages for the non-delivery of the deed as to the one lot
It was said that the law opposes the splitting up of actions, and that accordingly, if a bond be payable by installments and the plaintiff sues after the last installment is due, and claims for only the prior installments, he cannot recover afterwards for the last. In the case of a bond the judgment is for the penalty, which covers the whole cause of action, and prevents a new re-'
Even if there were a protest that the defendants should not be bound to pay for the part delivered, if the rest should not be delivered in a reasonable time thereafter, that protest would not exonerate the defendants from liability to give their notes, pursuant to the contract, for the part actually delivered. They should have given their notes, and protested that they would not hold themselves liable on them, nor excuse the past delay, nor accept or pay for the rest of the iron, but would claim' damages
[New-York General Term,
June 1, 1854.
Judgment should be entered for the plaintiffs.
Judgment accordingly.
Mitchell, Roosevelt and Clerke, Justices.]