Street Improvement—Time fob Completion of Work—Effect of Appeal—Setting Aside Acceptance—Jurisdiction to Extend Time. An appeal taken to the city council before the expiration of the time allowed to complete a street improvement, and after the work has been accepted as complete, operates to suspend the running of the time originally allowed, and, upon the city council setting aside the acceptance, it has jurisdiction to extend the time for the final completion of the work.Action upon a street assessment. The common council of the city of Los Angeles passed an ordinance for the improvement of Main street in that city, between Hinth and Thirty-seventh streets. Plans and specifications, together with an estimate of the cost of the work, were furnished by the city engineer prior to the passage of the resolution of intention, and in that resolution the city council declared, that it found upon such estimate that the cost of the improvement would be greater than one dollar per front foot along each line of the street, including the cost of intersections, and that in accordance with the provisions of the act of February 27, 1893, serial bonds extending over a period of ten years would be issued to represent its cost. After the completion of the work and issuance of the assessment therefor, demand and return of nonpayment were made thereon. Thereafter the appellant, whose property had been assessed for its proportion of the cost of the work, notified the city treasurer, in accordance with the provisions of the aforesaid act, that he desired no bond to be issued for the assessment against his land, and accordingly no bond therefor was issued. The assessment not being paid, the present action was brought for its enforcement by a sale of the land. Judgment was rendered in favor of the plaintiff and a new trial denied, from which he has appealed.
The contract for doing the work was entered into May 6, 1896, and provided that the work should be completed within two hundred and fifty days from its date—i. e., on or before January 11, 1897. Before the expiration of this time the con
1. Upon these facts the appellant contends that as the work was not completed within the period of two hundred and fifty days from the date of the contract, and as the subsequent extension was not made until after the expiration of that period, the contract had expired before the acceptance of the work, and the assessment therefor was invalid and created no lien. We are of the opinion, however, that this objection cannot be sustained. The contract provided, in accordance with the express requirements of the statute, that the contractor would do and perform the work "under the direction and to the satisfaction of the street superintendent.” The provision therein •fi-sri-ng two hundred and fifty days as the time for the completion of the work must refer to the completion of the work
2. The contract was originally awarded to John T. Long, and before its completion was assigned to the Western Contracting and Construction Company. The warrant issued with the assessment was in favor of “The Western Contracting and Construction Company, assignee of John T. Long, agents or assigns.” The appellant contends that the warrant should have been issued in the name of the original contractor, and that its issuance in favor of his assignee was unauthorized. The form of warrant which is prescribed in the street improvement act in terms authorizes and empowers the contractor, his agents or assigns, to demand and receive the several assessments, and the act declares that the warrant to be issued shall be “substantially” in this form. The right of the contractor to assign the contract, prior to the completion of the work, is recognized in many portions of the act, and has been recognized by this court. (Anderson v. De Urioste, 96 Cal. 404 .) After he has ceased to have any interest in the contract, or in the assessment therefor, there would seem to be no reason for the issuance of the warrant in his name, especially since the statute does not specifically require it. Sections 9 and 10 of the act designate the
3. It is further objected that the reference in the warrant to the issuance of bonds, as provided by section 3 of the aforesaid act of February 27th is insufficient. The reference to the bonds in the warrant is as follows: “Serial bonds béaring interest at the rate of six per cent per annum and extending over a period of ten years from their date of issue, to represent the costs and expenses of the work described in the assessment, and in the manner and form prescribed by law, and notice is hereby given that a bond in such series will issue to represent each assessment of fifty dollars or more, remaining unpaid for thirty days after'date of this warrant, or five days after the decision of the city council upon an appeal.”
We deem this to be a sufficient compliance with the act of 1893. That act requires that there shall be “included in the warrant” “a notice that a bond will issue to represent each assessment of fifty dollars or more, remaining unpaid for thirty days after the date of the warrant, or five days after the decision of said council, upon an appeal, and describing the bonds.” The warrant in question contains both a description of the bonds and the notice thus specified.
4. Upon the assessment offered in evidence was the following indorsement:
“The foregoing work was performed under the supervision of and was accepted by the Los Angeles city council; said work was not under my control or supervision at any time, and was not accepted by me. I hereby disclaim all responsibility for said work, and I sign and deliver this assessment and warrant upon the order of and the authority of said city council.
“J. H. DRAIN",
“Street Supt.”
5. The certificate of the engineer, offered in evidence, did not show that it had ever been recorded, but was indorsed: “Recorded -, 189—, -, Superintendent of Streets.” The act requires that the superintendent shall record the warrant, assessment, and diagram, together with the certificate of the engineer, in his office, and that after they are recorded they shall be delivered to the contractor, and it also declares that these documents, with the affidavit of demand and nonpayment, shall be prima facie evidence of the regularity and correctness of the assessment and of the prior proceedings and acts of the superintendent of streets and city council upon which said warrant, assessment, and diagram are based, and like evidence of the right of the plaintiff to recover in the action. It does not require that the evidence of the recording shall con- . stitute a portion of the prima facie evidence which is sufficient to entitle the plaintiff to recover. Ho evidence was offered
6. For the same reason, the objection to the finding by the city council in reference to the cost of the improvement must be disregarded. The objection to the sufficiency of this finding is that the language of the resolution wherein it is made is that such cost will be greater than one dollar per front foot along each line of said street, “including the cost of intersections,” whereas the statute prescribes, as a condition upon which bonds for the improvement may be issued, that the council shall find that the cost will be greater than one dollar per front foot along the line of the street, “including the cost of intersection work assessable upon said frontage.” The line of the proposed work herein included twenty-four intersections of cross-streets, and the city engineer had presented an estimate .that the probable cost of the work per front foot, on each side of the street would be four dollars and ninety cents. The act requires that only one-half of the cost of an intersection shall be assessed upon the frontage of the street along which the improvement is made, and it is therefore urged that it was not shown that the cost of the work “assessable upon the frontage” would be more than one dollar per front foot. The council must be deemed to have used the phrase “cost of intersection” with reference to the matter upon which it was acting, and, as so used, the expression must be regarded as equivalent to the “cost of the intersection work assessable upon said frontage.” The record does not show what was the width of any of the intervening streets, or the length of the several blocks of Main street, and we cannot say from any calculation whether the finding of the council was incorrect, but, as it must be assumed that these dimensions had been officially declared and were known to the council, it must be held that the prima facie character of the plaintiff’s evidence was not overcome. The council was not required to find the exact cost per front foot, but only to determine whether it would be greater- than one dollar per front foot.
7. It is next contended by the appellant that the assessment is invalid by reason of the unconstitutionality of the statute under which it was made, in that the statute makes an arbitrary apportionment of the expense according to the frontage of the lots, and does not require that the assessment upon each lot shall be made in proportion to the benefits received by that lot. The constitutionality of the statute has been upheld by this court so frequently that it is not an open question, but the appellants insist that the decision in Norwood v. Baker, 172 U. S. 269 , wherein it was held that the assessment therein considered was in contravention of the constitution of the United States, is at variance with these decisions and requires them to be disregarded. If the facts and statute under which the present assessment was made were of the same character as those involved in that case, we would without hesitation accept that decision as conclusive upon us, but we are of the opinion that there is a marked distinction between the two cases, and that that decision is not applicable to the facts herein. In Norwood v. Baker, supra, the question considered by the court was the validity of an assessment for the cost of opening a new street, consisting of the value of the land taken and the costs of its condemnation, and whether the same could be taxed upon the owners of the land abutting upon that taken, irrespective of any consideration -of the benefits received by that land. The assessment therein involved did not include any of the expense of improving an existing street, and whether such expense may ■be assessed upon lands fronting upon the street within certain limits designated by the legislature was not presented or dis-. cussed in the opinion; and, although the “improvement” of the street is frequently mentioned in the opinion, this expression is to be read in the light of the question to be determined by the court upon the facts before it.
The village of Uorwood desired to open and extend Ivenhoe
The principle invoked, that the assessment must be in proportion to benefits, was not disputed in the case, the only question being as to the application of that principle to the facts before the court, and its conclusion was reached by reason of the inhibition of the statute and constitution of Ohio, from considering whether the land assessed had received any benefit by reason of the opening of the street. In no portion of the opinion is it intimated that an assessment for the improvement of an 'existing street upon the lands abutting thereon, according to their frontage, within a district designated or prescribed by legislative authority, is invalid, nor did the court question the correctness of any of its previous decisions, many of which are cited in the opinion, in which assessments under such a rule had been sustained. In Mattingly v. District of Columbia, 97 U. S. 692 , that court had said: “Special assessments for special road or street improvements very often are oppressive, but that the legislative power may authorize them to be made in proportion to the frontage, area, or market value of the adjoining property, at its discretion, is under the decisions no longer an open question.” In Bauman v. Ross, 167 U. S. 548 , it had said: “The class of lands to be assessed for the purpose [of a public improvement] may be either determined by the legislature itself by defining a territorial district or by other designation; or it may be left by the legislature to the determination of commissioners, and may be made to consist of such lands, and such only, as the commissioners shall decide to be benefited. The rule of apportionment among the parcels of land benefited also rests with the discretion of the
8 55 Am. Dec. 266 .
The provision in the street improvement act of this state, that in cases where, in the opinion of the city council, the work of the improvement is not “of more than local or ordinary public benefit” the cost of any street improvement shall be assessed as an entirety upon the lots and lands fronting upon the improvements, and shall be apportioned between the several lots therein according to their frontage, is a declaration by the legislature that, in the judgment of that body, the property within that district will receive a benefit from the improvement in proportion to its frontage upon the work. Unless, therefore, it is made to appear upon the face of the proceedings, or by some competent showing, that there is a gross or substantial variation from this principle, it is the duty of courts, under the rules and authorities above cited, to uphold the assessment. Before the judiciary would be justified in holding an assessment to be invalid, it should be made to appear that it is, as was said in Norwood v. Baker, supra, “in substantial excess of the benefits,” or, as was said in Cleveland v. Tripp, supra, that it “palpably transgresses” the principle upon which it is authorized. In Fallbrook Irr. Dist. v. Bradley, supra, the court said: “The way of arriving at the amount may be, in some instances, inequitable and unequal, but that is far from arising to the level of a constitutional problem, and far from the ease of taking property without due process of law.” In Lent v. Tillson, supra, the court said: “The benefits need not be immediate. I see no just limitation in this respect, except that a tax will not
The judgment and order are affirmed.
Garoutte, J., and Temple, J., concurred.
Hearing in Bank denied.
Cases cited
- Beveridge v. Livingstone 54 Cal. 54 p. 209
- Raisch v. City & County of San Francisco 80 Cal. 1 p. 209
- Klauber v. San Diego St.-Car Co. 95 Cal. 353 p. 209
- Remy v. Olds 88 Cal. 537 p. 209
- Palmer v. Burnham 120 Cal. 364 p. 209
- Taylor v. Palmer 31 Cal. 240 p. 209
- Mills v. La Verne Land Co. 97 Cal. 254 p. 209
- McCrea v. Johnson 104 Cal. 224 p. 209
- Rauer v. Fay 110 Cal. 361 at 367 p. 209
- Williams v. Bergin 108 Cal. 166 at 169 p. 209
- Witter v. Bachman 117 Cal. 318 p. 209
- Gray v. Lucas 115 Cal. 430 p. 209
- Warren v. Chandos 115 Cal. 382 p. 210
- In re Grove Street 61 Cal. 438 at 448-50 p. 210
- Lake County v. Sulphur Bank Quicksilver Mining Co. 66 Cal. 17 p. 210
- Emeric v. Alvarado 90 Cal. 444 at 465, 466 p. 210
- Brock v. Luning 89 Cal. 316 p. 210
- People v. Sierra Buttes Quartz Mining Co. 39 Cal. 511 at 515, 516 p. 210
- People v. Hollister 47 Cal. 408 p. 210
- Shepard v. Colton 44 Cal. 628 p. 210
- Donnelly v. Tillman 47 Cal. 40 p. 210
- Donnelly v. Marks 47 Cal. 187 p. 210
- Reis v. Graff 51 Cal. 86 p. 210
- Haskell v. Bartlett 34 Cal. 281 p. 210
- Norwood v. Baker 172 U. S. 269 p. 210, p. 217
- Holley v. County of Orange 106 Cal. 420 p. 210
- Himmelmann v. Reay 38 Cal. 163 p. 211
- Anderson v. De Urioste 96 Cal. 404 p. 213
- California Improvement Co. v. Reynolds 123 Cal. 88 p. 216
- Bauman v. Ross 167 U. S. 548 p. 219
- People ex rel. Griffin v. Mayor of Brooklyn 4 N. Y. 419 p. 220
- Ramish v. Hartwell 126 Cal. 443 p. 222