Majority
Headnote
Action on Quantum Meruit—Work Performed in Opposition to Order.—An action on quantum meruit, to recover the reasonable value of services performed, is based upon a request to perform the services; and such action will not lie for services performed in violation of an express order of the defendant not to do the work sued for.Plaintiffs are architects, and were employed by defendant to prepare the plans, specifications, etc., and oversee the construction of a certain building, and in consideration of their services they were to receive four per cent of the cost of the building. The plans of this structure included the construction of a very elaborate café, and while in the negotiations leading up to the employment of the plaintiffs they insisted upon a compensation amounting to five per cent of the cost of the building, yet finally, actuated by the fact that their employment was to extend to the entire work, including the interior decorations of this café, they agreed to undertake the work upon the basis of four per cent. Considerable work was done by them under the contract, but very little of it upon the interior decorations of the café, when upon July 31st, defendant addressed to the plaintiffs a letter
An action in quantum meruit is based upon the theory that one party has performed services for another at his request; and here, if defendant ordered plaintiffs not to perform services upon the interior decorations of the café, they could not recover in quantum meruit if thereafter they proceeded in opposition to that order. Services performed under these circumstances would not be performed at the request of the defendant. This principle of law is approved by the trial court when it gave to the jury the following instruction: “The plaintiffs cannot recover in this action for any work they may have done for the interiors of the building known as the Pabst Café, except such work, if there was any, as was done at the request of the defendant.”
The court is thus brought to a consideration of the force and effect of the letter sent by defendant to plaintiffs. It is claimed upon their part that it is equivocal in character, and is not in effect a direction to cease and refrain from work upon the interior decorations. But the letter appears to be plain to the contrary, and such was the construction given it by the plaintiffs themselves. If they had come before the trial court claiming the letter to be equivocal, vague, and indefinite, and asserted that they continued their labors through a misunderstanding or misconstruction of its force and effect,—that is, if its effect was to order them to cease work upon this particular part of the building,—another question would be presented; but no such case was attempted to be
It is insisted that the contract for the service was an entire contract, covering the whole building, inside and outside, and that defendant could not repudiate the contract as to a part,— namely, the interior decorations of the café. This contention is unsound. As to defendant, it could repudiate a part of it or repudiate it all. In other words, a repudiation of a part of it was, as to plaintiffs, a repudiation of' it all,—that is, plaintiffs had the right to consider the breach of this covenant a breach of the entire contract. The acts of defendant were a breach of the entire contract, but the breach could be waived by plaintiffs as to all portions thereof not included in that part relating to the interior decorations. As to all other matters, plaintiffs could waive the breach and continue their work. That was a matter entirely optional with them at the moment they were ordered to cease work upon the interior decorations. At that moment they were justified in law in ceasing from work upon all parts of the building if they so felt disposed. It is said in Haskell v. McHenry, 4 Cal. 411 : “The contract declared on was an entirety. The first breach by the defendant was a breach of the whole, and discharged the plaintiff from the performance of any conditions on his part. It gave him a complete right of action. (See Cockley v. Brucker, 54 Ohio St. 214 .)”
Plaintiffs insist that subsequent to July 31st they performed
For the foregoing reasons the judgment and order are reversed and the cause remanded for a new trial.
Harrison, J., and Van Dyke, J., concurred.
Hearing in bank denied.
Cases cited
- Lord v. Thomas 64 N. Y. 107 at 109 p. 409
- Purdy v. Bullard 41 Cal. 444 p. 409
- Day v. New York Central Railroad 53 Barb. 250 p. 409
- San Francisco Bridge Co. v. Dumbarton Land & Improvement Co. 119 Cal. 272 p. 409
- Porter v. Arrowhead Reservoir Co. 100 Cal. 500 p. 409
- Cox v. McLaughlin 76 Cal. 60 p. 409
- Haskell v. McHenry 4 Cal. 411 p. 411