AI-generated from this judgment's text. It can contain errors and is not the official version.
No AI brief yet. Click to generate.
Majority
Headnote
Building Contract—Action on Bond—Former Judgment—Bes Judicata.—In an action by the owner on the bond of a contractor for the construction of a building, the contract for which was void for want of record, to recover an amount paid by the owner to discharge liens, after the contractor had abandoned the contract, a judgment for costs in favor of the owner in a former action by the contractor to recover the reasonable value of his labor and materials, in which the owner set up such abandonment, and a payment made to the contractor and the amount paid in discharge of the liens, and prayed judgment' for the sum paid in excess, of the contract price, although the judgment rendered is erroneous, is res judicata as to the subject-matter, and is a defense to the action.The plaintiff entered into a contract with the defendant Wahlenmaier for the construction of a building in Los Angeles at the agreed price of $6,277, and at the same time Wahlenmaier and his co-defendant, the Fidelity and Deposit Company, of Maryland, as his surety, executed a bond to the plaintiff for the faithful performance by him of his contract. The bond provided that Wahlenmaier should also cancel and release the building from all claims or liens that might accrue against it from the performance of the contract, and should save the plaintiff herein harmless from all damage thereby. Wahlenmaier abandoned work upon the building before it was completed, and thereafter the plaintiff finished its construction. The plaintiff paid to Wahlenmaier $2,577 before he abandoned the work, and afterwards paid $4,360 in discharge of liens for materials and labor furnished and employed in its construction at the request of Wahlenmaier. The present action is brought upon the above-named bond to recover the amount paid by the plaintiff in discharge of liens in excess of the contract price for constructing the building.
The contract for the construction of the building was not filed in the recorder’s office. Prior to the commencement of this action, but after the building had been completed, Wahlenmaier brought an action against the plaintiff to recover from him the reasonable value of the labor performed and materials furnished by him in its construction, alleging the same to be $8,448. In his answer to the complaint in that action the plaintiff herein alleged that Wahlenmaier had contracted with him to construct the building for the sum of $6,277; that the labor and materials furnished by him in its construction were under and by virtue of said contract; and that the said sum was the reasonable value of the labor and materials furnished by him. He also set forth in his answer
The defendants herein have pleaded the judgment in that action in bar of the plaintiff’s right of recovery. The superior court held that it was a bar in favor of Wahlenmaier, but not in favor of the surety company, and rendered judgment against the latter and in favor of the plaintiff for $691. The surety company has appealed.
The rule formulated by Lord Chief Justice De Grey in the Duchess of Kingston’s ease, and frequently repeated in other cases, that “The judgment of a court of concurrent jurisdiction directly upon a point is, as a plea, a bar, or as evidence conclusive between the same parties upon the same matter directly in question in another court,” has been substantially reproduced in section 1908 (subd. 2) of the Code of Civil Procedure of this state. The estoppel thus created is not
The liens, for whose payment in excess of the contract price for constructing the building the plaintiff now seeks to recover from the defendants, are the same liens which were set forth by him in the former action in support of his claim against Wahlenmaier. In that action he presented to the court, as an issue to be tried and determined, his right to recover from Wahlenmaier the amount of money paid by him upon these liens in excess of the contract price for constructing the building, and asked for a judgment therefor against Wahlenmaier. His right to recover this excess was thus brought into judicial investigation, and at the trial evidence was presented by him to the court in support of his demand, and the court found that he had paid the liens to the extent claimed by him, but refused to give him judgment therefor upon the ground that, as the contract was invalid, Wahlenmaier was entitled to the entire value of the labor and materials used in the construction of the building, irrespective of the price named in the contract. The omission of the court to give him any relief for the payment of this excess was, in its legal effect, an adjudication that he was not entitled to
The judgment is none the less a bar for the reason that it was erroneous. “In passing upon the plea of res judicata, the question is not whether a court decided the point involved right or wrong, but the question is, Did the court decide the point and is the decision final?” (Chouteau, v. Gibson, 76 Mo. 38 .) By failing to appeal and seek a correction of the error through a reversal of the judgment, it is as conclusive upon the plaintiff as if at the trial he had omitted to present sufficient evidence to the court in support of his demand. (Collins v. Bennett, 46 N. Y. 490 ; Davis v. Tallcot, 12 N. Y. 184 ; Caldwells. White, 77 Mo. 471 ; Herman on Estoppel, sec. 268; Freeman on Judgments, sec. 249.)
It must be held, therefore, that by reason of the judgment in the former action of Wahlenmaier against the plaintiff, the latter is estopped from enforcing any obligation to him on the part of Wahlenmaier, arising out of the payment of the liens against the building in excess of the contract price.
The plaintiff’s right to recover from the appellant is solely by virtue of its having become the surety for Wahlenmaier for such payment, and it is a familiar principle of suretyship that any act of the creditor, by which the principal is discharged from liability, will also discharge the surety. The surety has an immediate right of action against the principal for reimbursement of any payment enforced against him by the creditor; but if, by the act of the creditor, he will be unable .to proceed against the principal, he is for that reason discharged from liability to the creditor. It is upon this principle that the surety is discharged, if, without his consent, the creditor gives to the principal an extension for the time of performance, or surrenders to him securities which he holds for the obligation, or releases him from his obligation. The reason which underlies this rule is the obligation of fidelity, the uberrima fdes which the creditor is under to the surety,
The judgment by virtue of which Wahlenmaier was exonerated from any obligation to the plaintiff was the direct result of the course of action taken by the plaintiff in that suit. The plaintiff therefore being, as the result of his own act,
We advise that the judgment and order denying a new trial be reversed.
Cooper, C., and Gray, C., concurred.
For the reasons given in the foregoing opinion the judgment and order denying a new trial are reversed.
Angellotti, J., Shaw, J., Van Dyke, J.
Footnotes
- 2 27 Am. Rep. 744 .
Cases cited
- Ehle v. Bingham 7 Barb. 494 p. 94
- Thompson v. McKay 41 Cal. 221 p. 95
- Laidlaw v. Marye 133 Cal. 170 p. 95
- Collins v. Bennett 46 N. Y. 490 p. 95
- Davis v. Tallcot 12 N. Y. 184 p. 95