Majority
Headnote
Injunction—Abatement of Private Nuisance—Dust Resulting from Cement Plant—Stay of Injunction Pending Appeal Refused— Irreparable Injury to Appellant.—Pending an appeal from a judgment enjoining the operation of a cement plant, because of thePetitioner has made an original application to this court to suspend the operation of a certain injunction until the decision of the appeals in two cases, in each of which the California Portland Cement Company, a corporation, is the defendant, on the ground that the property of the corporation would be so greatly damaged by the operation of the injunction pending the appeals, that a judgment in defendant’s favor would be almost fruitless, while, it is contended, the damage to plaintiffs is easily susceptible of satisfaction by a payment of money. Petitioner offers to furnish any bond this court may require if the order which is prayed for shall be granted. As this was (the first case in America, so far as this court knew, in which the operation of a cement plant had been enjoined because of the dust produced in the processes of manufacture, and as the showing which was made indicated that petitioner’s loss would be very great if the injunction were enforced at once, an order was entered temporarily staying its operation until both sides to the .controversy could be hearcQ The court was moved somewhat to such action also because the trial court had made an order staying the operation of the injunction for sixty days, so that this court might have the opportunity of passing upon this application. Two principal questions are presented: 1. Has the supreme court the authority in aid of its appellate jurisdiction under section 4 of article VI of the constitution to suspend the operation of an injunction pending appeal? 2. If it has such power is this a proper case for the exercise thereof ? Owing to the conclusion which we have reached it is unnecessary to answer the first question authoritatively because assuming a reply to it in the affirmative, we cannot say that the facts of this case
The salient facts shown by the petitioner are that the California Portland Cement Company is engaged in the manufacture of cement on property situated nearly two miles from the center of the city of Colton in the county of San Bernardino, but not within the limits of said city; that said manufactory is located at Slover Mountain, where the substances necessary to the production of Portland cement are quarried; that long before the surrounding country had been generally devoted to the production of citrus fruits, Slover Mountain had been known as a place where limestone was produced; that quarries of marble and limestone had been established there; that lime kilns had been operated upon said mountain for many years; that in 1891 the petitioner obtained title to said premises and commenced thereon the manufacture of Portland cement; that the said corporation has expended upon said property (more than eight hundred thousand dollar^; that (at the time when petitioner began the erection of the cement plant the land surrounding the plant was vacant and unimproved^ except some land lying to the north, which had been planted to young citrus trees; that these trees were first planted about a year before the erection of the cement plant was commenced (but long after the lime kilns and the marble quarries had been operated); that subsequently, other orange groves had been planted in the neighborhood; that petitioner’s plant on Slover Mountain has a capacity of three thousand barrels of cement per day; but that by the judgment of the superior court in two certain actions against petitioner entitled Lillie A. Hulbert, Administratrix etc. v. California Portland Cement Company, a Corporation, and Spencer E. Gilbert, plaintiff, v. the same defendant, the corporation aforesaid was enjoined from operating its plant in such manner as to produce an excess of 88,706 barrels of finished cement per annum; that the regular pay-roll of the company includes the names of about five hundred men who are paid 'about thirty-five thousand dollars a month; that the fixed, constant monthly expenses for supplies and materials amount to thirty-five thousand dollars; that the California Portland Cement Company employs the best, most modern methods in its processes of manufacture, but that nevertheless there is an unavoidable
The learned judge of the superior court in deciding the cases in which petitioner here was defendant, described the method of manufacturing cement and the injury to the trees. He said, in part: “The output from these two mills at the present time is about 2500 barrels of cement every twenty-four hours, and to produce this there is fed into the various kilns of the defendant, during the time mentioned, about one and one-half million pounds of raw mix, composed of limestone and clay, ground as fine as flour and thoroughly mixed. This raw mix is fed into the tops of kilns, wherein the temperature varies from 1800 to 3000 degrees Fahrenheit, and through which kilns the heated air and combustion gases pass at the rate of many thousands of feet per minute. The result of this almost inconceivable draft is to carry out, in addition to the usual products of combustion, particles of the raw mix, to the extent of probably twenty tons per day or more, the greater part of which, without question, is carried up into the
In view of such facts solemnly found by the court after trial, £we cannot say that there is reason for a suspension by this court of the injunction^ even conceding that we have power under proper circumstances thus to prevent a disturbance of existing conditions, pending an appeal. [We are not
¿Petitioner contends for the rule that the resulting injuries must be balanced by the court and that where the hardship inflicted upon one party by the granting of an injunction would be very much greater than that which would be suffered by the other party if the nuisance were .permitted to continue, injunctive relief should be denied]] ¿This doctrine of “the balance of hardship” and the associated rule that “an injunction is not of right but of grace” are the bases of petitioner’s argument, and many authorities in support of them have been called to our attentiog'3 In petitioner’s behalf are cited such eases as Richards’s Appeal, 57 Pa. St. 105 , [ 98 Am. Dec. 202 ], where an injunction which had been sought to restrain defendant from using large quantities of bituminous coal to plaintiff’s damage was refused, and the plaintiff was remitted to his action at law, the court saying, among other things: “Whatever of injury may have or shall result to his, the plaintiff’s property, from the defendant’s works, by reason of a nuisance complained of, is only such as is incident to a lawful business conducted in the ordinary way and by no unusual means. Still there may be injury to the plaintiff, but this of itself may not entitle him to the remedy he seeks. It may not, if ever so clearly established, be a cause in which
Petitioner lays great stress upon North Fork Water Co. v. Medland, 187 Fed. 169 , in which in the opinion by Judge Ross, formerly a member of this court, the following appears: “Now, in the first place, it is to be remembered that no one is entitled to an injunction as a matter of absolute right. When a contract is broken and any party thereto sustains an injury by reason of such breach, the injured party has an absolute right to maintain an action at law for the recovery of such damages as "can be shown to have been sustained by him. But a suit in equity either to enjoin the continuance of such a breach or to enforce the specific performance of the contract appeals to the sound discretion of the chancellor—to his conscience— and the relief so sought will be granted or withheld according to the real equity of the case, in view of all its facts and circumstances.” Petitioner also cites Mountain Copper Co. v. United States, 142 Fed. 625 , [ 73 C. C. A. 621 ], in which the opinion was also by Judge Ross. In that case the court refused to enjoin the operation of defendant’s smelter relying largely upon the early cases from Pennsylvania which declare the “balance of hardship” doctrine and that an injunction is ex gratia and not ex debito justitice, and citing other cases including the well known Madison v. Ducktown Sulphur, Copper & Iron Co., 113 Tenn. 331 , [ 83 S. W. 658 ]. While we have the utmost respect for the learned author of these opinions
The Mountain Copper Company case has also been criticised by the supreme court of Arizona, as well as the later case of McCarthy v. Bunker Hill & Sullivan Mining & Con. Co., 164 Fed. 927 , [ 92 C. C. A. 259 ]. In Arizona Copper Co. v. Gillespie, 12 Ariz. 203 , [ 100 Pac. 470 ], this language was used: “Counsel press upon us the proposition that we should consider the comparative damage that will be done by granting or withholding an injunction in this case, alleging that the effect of an injunction will be to stop the operation of extensive works, deprive thousands of persons of employment, and cause loss and distress to other thousands. It is undoubtedly true that a court should exercise great care and caution in acting where such results would follow. It should very clearly appear that the acts of the defendant are wrongful, and that the complainant is suffering substantial and irreparable injury, for which he cannot secure adequate compensation at law. A number of eminent courts support the contention of appellant that the comparative injury to the parties in granting or withholding relief must also be considered. Among the eases so holding is the case of McCarthy
Petitioner cites, among others, the following cases, which, although tending for the most part to support the rule for which he contends, are not we think in accord with the best modern ideas upon this subject and with the current of
In Georgia v. Tenn. Copper Co., 206 U. S. 230 , [ 27 Sup. Ct. 618 , 51 L. Ed. 1038 ], there is a dictum to the effect that if the plaintiff were a private individual the court might consider the balance of hardship, but from this Harlan, J., dissented. One of the most -instructive cases upon this subject is American Smelting & Rep. Co. v. Godfrey, 158 Fed. 225 , [ 89 C. C. A. 139 ]. In that case Judge Riner says: “The fact, urged by counsel, that these smelters are located at a place where by, reason of its relation to the railroads and mines is most convenient for smelting purposes does not, in our judgment, constitute any defense to a bill to abate a nuisance; neither can a court take into consideration the fact that the business is conducted in a proper and reasonable manner employing the latest and best devices and instrumentalities, where the evidence shows, as in this case, that when so operated and conducted, it still results in very great damage to, if not the total destruction of, complainant’s property, and is a menace to health. ‘The rights of
Our attention has been directed to certain Californian cases which, according to petitioner’s belief, support the rule with reference to the “balancing of injury.” These are Peterson v. City of Santa Rosa, 119 Cal. 387 , [ 51 Pac. 557 ], and Williams v. Los Angeles Railway Co., 150 Cal. 593 , [ 89 Pac. 330 ]. In the latter case the court was considering the refusal by the superior court of an injunction pendente lite. While it contains some language perhaps susceptible of the meaning for which petitioner contends, the court was really considering the principle announced in Hicks v. Michael, 15 Cal. 116 , that an injunction should not be issued before a hearing on the merits except in cases of urgent necessity. In Peterson v. Santa Rosa, 119 Cal. 387 , [ 51 Pac. 557 ], the following language is found: “In Attorney General v. Council of Birmingham, 4 Kay & J. 528, the court indicated that in such cases only the right of plaintiff to relief, rather than the question of inconvenience to defendants was to be considered, although the latter represented a large population. We regard the foregoing as an extreme statement and deem it more proper to adopt the language of Swayne, J. in Parker v. Winnipiseogee Etc. Co., 2 Black (U. S.) 545, [ 17 L. Ed. 333 ] :
Let the temporary order staying the operation of the injunction be dismissed and the petition be denied!)
Lorigan, J., concurred.
Concurrence
I concur in the order, fit seems to me, however, that the discussion concerning the right of a court of equity to refuse an injunction where the injury resulting to the plaintiff from a denial of the relief would be far less than that sustained by the defendant if the injunction were granted, is applicable to a consideration of appeals on their merits, rather than to the question here involved.! If the court may balance the extent of the losses to be suffered by the respective parties, it exercises its discretion in this behalf when it grants or refuses the injunction. In this case the lower court has determined that it was essential, or at least proper, for the protection of the plaintiffs’ rights that the defendant should be restrained. We are not now reviewing the correctness of that determination. The petitioner cannot, of course, ask us in this proceeding to stay the force of the injunction on the ground that the trial court abused its discretion or that it erred otherwise in granting the injunction. What is claimed is that a suspension of the judgment “is necessary or proper to the complete exercise” of our appellate jurisdiction (Const., art. VI., sec. 4); it is claimed that a refusal to stay the injunction will so affect the subject of the controversy that, if the judgment should ultimately be reversed, the appellant will in large measure be deprived of the fruits of its successful appeal.
But we must consider the rights of the respondents, as well as those of the appellants. If the judgment of the court below is right, the plaintiffs are absolutely entitled to have the wrongful acts stopped, not only after the determination of the appeal, but pending the appeal. Under the findings the acts complained of are inflicting a continuing injury upon the plaintiffs and their lands, an injury of a kind which has always been regarded by courts of chancery as irremediable and not capable of adequate redress by damages. If the appellant may ask that it shall not lose the fruits of an appeal which may turn out to be meritorious, the respondents are in at least as good a position to demand that the appellate court shall not irrevocably take away from them the benefit'which they have already won and which will be confirmed to them if the judg
It may be suggested, further, that the effect of an order by this court suspending the operation of a prohibitory injunction is to reverse, pro tanto, the judgment granting the injunction, and that in advance of a hearing on the merits. That this is so will appear more clearly if we suppose the case of an appeal from an order of the superior court granting an injunction pendente lite. In such case, an application for a suspension of the injunction pending the appeal could be urged upon precisely the same grounds as those here presented by petitioner. The thing decided by the trial court, in the case supposed, was that defendant should be restrained until a trial on the merits, or until that court should order otherwise. That conclusion is reviewable on appeal, but to suspend the order before a hearing of the appeal would clearly be to set aside the very thing decided below, viz., that the defendant should be enjoined until a trial or a further order. The situation does not differ where the injunction is embraced in a final judgment. There, too, it is a part of the .adjudication that the defendant should be enjoined at once, and this adjudication should not be set aside on appeal before a hearing on the merits of the appeal.
Angellotti, J., and Shaw, J., concurred.
Cases cited
- Fisher v. Zumwalt 128 Cal. 493 p. 245, p. 250
- Sullivan v. Royer 72 Cal. 248 p. 246
- Natoma Water & Mining Co. v. Clarkin 14 Cal. 544 at 551 p. 250
- Atchison v. Peterson 20 Wall. 507 p. 252
- New York City v. Pine 185 U. S. 93 p. 252
- Georgia v. Tennessee Copper Co. 206 U. S. 230 p. 252
- Peterson v. City of Santa Rosa 119 Cal. 387 p. 253
- Swift v. Shepard 64 Cal. 423 p. 256
- City of Pasadena v. Superior Court of L.A. Cty. 157 Cal. 781 p. 256