Majority
Headnote
Contract—Construction of Writings Question of Law—Contract Price of Marble Set in Building—Assignment—Assignee Bound By Terms of Contract.—In an action by an assignee of a contractor to recover a balance alleged to be due on a contract for furnishing marble to. a building erected by the defendant, it is held, upon a review of the writings evidencing the original contract and a subsequent modification of it by the parties thereto, that the contract price was to be determined by the amount of the marble set and measured in the building, and not by the amount actuallyThis action was brought to enforce the payment of a sum of money alleged to be due on a contract for furnishing marble to the Monadnock building in San Francisco owned by the defendant. The cause was tried before a jury and plaintiff received a verdict in the sum of $6,170.61, the full amount sued for, with interest. Judgment was rendered in accordance with the verdict. Defendant appeals from that judgment and from the order denying his motion for a new trial.
So little dispute is there over the facts that it may be said that they are presented without conflict. The controversy arises over the legal conclusions to be drawn from the admitted facts. The latter are the following: In 1904 defendant ,Law contemplated the construction of an office building in San Francisco known as the Monadnock building. W. A. Perrin, a marble man, entered into a contract with Law to furnish the marble proposed to be used in the construction of this, building. The contract was in writing. It set forth the various pric'es for the marbles and the condition in which they were to be shipped f. o. b. cars, Colton, California. This contract was known as the “square foot” agreement and concluded as follows: “If my quotations are accepted, it is understood that this per square foot agreement will be substituted for a lump sum contract, this contract to be drawn
In the square foot agreement the provision for payment is the following: “On arrival and checking of marble in Sari Francisco in carload lots 90% of the amount due will be paid on presentation of architect’s certificate. The balance of 10% will be due twenty-five days after the marble is set in the building complete. ’ ’ Perrin entered upon the delivery of the marble. Because of his immediate need for money to pay his labor and because of the delay in procuring the architect’s certificates Perrin testifies, and it is without dispute, that the mode of payment was modified. The presentation of the architect’s certificate was waived and Law permitted Perrin to draw upon him for ninety per cent of the contract price of the marble as soon as it was placed on the cars at Col-ton. Meanwhile the drawings, plans and specifications had been completed and Law from time to time requested Perrin to enter into the “lump sum” agreement which was to take the place of the “square foot” agreement with the result that on February 23, 1906, Perrin executed the following writing:
“ San Francisco, California.
“Me. Herbert E. Law,
“Rialto Building, City.
“Dear Sir:—
“It is agreed that payments for marble on contract dated September 6, 1904, for marble in Monadnock Building are approximate only and that the actual marble to be paid for by you will be measured set in building; the owner taking no responsibility as to size or condition, etc., delivered.
“Tours very truly,
“ (Signed) W. A. Perrin.
“Dated this 23rd day of February, 1906.”
Perrin had fallen into financial difficulties and was unable to pay his laborers. On or about the date of the letter above quoted he entered into an agreement with T.
Following these writings and upon March 6, 1906, Fleming presented the following letter to the defendant:
“March 6, 1906.
“Herbert E. Law,
“San Francisco, California.
“Dear Sir:
“I beg to hand you herewith two copies of the assignment of the contract Mr. W. A. Perrin has with you for furnishing the marble to be used in the Bishop Building (Monadnock) in San Francisco. I understand that Perrin has been in San Francisco and advised you of this assignment, and that it is agreeable to you. If this is correct I would be pleased if you would designate your acceptance on one of the .copies and return it to me at your earliest convenience. I understand there will be a carload of marble ready to be shipped in a few days. Thanking you for your prompt attention to this matter, I am
“Very truly yours,
“(Signed) T. J. Fleming, Trustee.”
To this letter he received this response:
“San Francisco, Cal., March 8, 1906.
“Mr. T. J. Fleming,
“California Portland Cement Co.,
“401-3 Trust Building, Calif.
“Dear Mr. Fleming:
“I have your favor of the 6th inst. It will be quite apparent to you that I cannot consider the transfer of my contract to a number of persons of whom I know nothing, and
of whose responsibility and ability to carry out the contract I do not know. Mr. Perrin, I think, is a responsible man and that he will carry it out. These gentlemen are perhaps responsible, I do not lmow anything about them.
“It seems to me, Mr. Fleming, that a transfer on my part is not necessary anyhow. Mr. Perrin will give you an order on me for the money that falls due from time to time, and I will pay it to you. That is all there will be to it. Just as soon as you have served me with notice of assignment, I will acknowledge receipt and whatever money becomes due to Mr. Perrin, I will pay on his order. It seems that this would accomplish your desire without requiring any other assignment than the arrangement that may be made between the men, Mr. Perrin and yourself.
“Very truly yours,
“(Signed) Hebbebt E. Law.”
It appears that the suggestion in Mr. Law’s letter outlined the course which was actually pursued for Perrin did give a written order to Mr. Law to “pay to T. J. Fleming, trustee, all moneys now due or that may become due me on that certain contract for furnishing marble,” etc.
Much marble had been delivered under this contract at the time of the earthquake and fire of April, 1906. The Monadnock building was injured in this calamity. In May, 1906, inspection was had and measurements were made of the marble saved from the disaster. A detailed list of the kinds and quantity of marble thus saved was prepared by Perrin and his son who had the contract for setting the marble in the building. It was found that in value $7,404.35 had been saved. Work was taken up for the completion of the building and more marble was shipped and placed therein. It is shown that up to within a few days before the April disaster there had been shipped for use in the Monadnock building marble of the contract value of $32,558.29. Upon this Law had paid $29,819.51, leaving a balance unpaid of $2,738.78. After the disaster marble of the value of $34,747.23 was shipped. Upon this Law had paid $31,315.40, leaving the value of the marble unpaid $3,431.83. These two items of $2,738.78 and $3,431.83 represent the sums sued for by plaintiff for which he obtained judgment.
Appellant still further argues and shows that immediately after the disaster there was a balance unpaid upon the marble shipped of $2,738.78; that there was marble saved to the value of $7,404.35. Deducting from this the sum of $2,738.78, which was owing, $4,665.57 had been paid upon the marble saved from the disaster and placed in the building. Upon the shipment of marble made after the disaster there has admittedly been paid $31,315.40, making a total payment for the marble actually set in the building of $35,980.97. But (so runs appellant’s argument), the value of all marble set in the building, measured by its contract price, was only $33,908.45; from which results the inevitable conclusion that appellant, instead of being indebted to plaintiff, has made payments in excess of the full contract price and for the excess marble wherever it is or whatever it may be, appellant disclaims all liability and responsibility.
Respondent, in effect, concedes this to be true if his rights are to be measured by the contract between Perrin and Law embodied in the written communications above set forth, and
Thus, it will be seen that the legal controversy between these parties revolves around two propositions: 1. Did Law assent to Perrin’s assignment of his contract to Fleming to the extent that Fleming became substituted for Perrin therein; and, 2, Was this assent to the assignment, if given, given under such circumstances as to relieve Fleming from the operation of the modification contained in Perrin’s letter to Law of February 23d. Without hesitation both of these questions must be answered in the negative. As to the first, Law’s response to Fleming’s letter is a distinct refusal to recognize the assignment and to relieve Perrin from his responsibility thereunder. He was willing to go no further, and did go no further, than to declare that he would recognize in favor of Fleming such orders for the payment of moneys due to Perrin arising under the contract as Perrin might give. Such an order was actually given and was honored by Law. Upon the second proposition it is, of course, beyond argument that if Fleming had not been substituted for Perrin as assignee under the contract with the acceptance of Law, Law and Perrin were at perfect liberty to make such modifications and changes in their contract as they saw fit. The modification evidenced by the letter of February 23 d, however respondent may argue against the unreasonableness of it, was precisely such a modification as was contemplated in the original “square foot” contract where it is said: “It is understood that this per square foot agreement will be sub
We do not perceive in Perrin’s testimony anything at variance with the modification of the contract and the explanation of it just quoted. Nor, if there were, in the absence of fraud, coercion or mutual mistake, nothing of which is here asserted, could a witness be permitted, by a mere declaration of his concept of 'a written contract, to overthrow its plain, unmistakable, and unambiguous language.
It necessarily follows herefrom that under his contract with Perrin, Law was responsible only for the contract price of the marble set and measured in the building and it was the duty of the trial court so to have instructed the jury as matter of law. It was error for the court to leave to the jury, under the circumstances here shown, the determination of the question whether or not plaintiff could recover under the original square foot contract unmodified by the letter of February 23d.
Under the conclusion thus reached no other propositions advanced by appellant require consideration.
For the foregoing reasons the judgment and order are reversed and the cause remanded.
Melvin, J., and Lorigan, J., concurred.
Hearing in Bank denied.