Majority
Headnote
Agency—Declarations of Unauthorized Person Acting as Agent— Evidence Inadmissible.—No person is bound by the declarations of another who is not his agent and expressly or by implication authorized by him to make the declarations. Unless at least prima facie evidence of such authority appears; such conversations are not admissible in evidence.The action is to recover damages arising from the alleged negligence of the defendant in failing to deliver two telegrams sent to the plaintiff's agents in San Francisco.
The plaintiff was constructing a power plant on the Stanislaus River in Tuolumne County. On October 10, 1906, it made an agreement with the Risdon Iron and Locomotive Works, of San Francisco, by which the plaintiff was given the option to close a contract with said Iron Works, within ninety days from said date, for the construction by said Iron Works of a part of the plant, consisting of an additional pressure line, known as the Mine Line, at a cost of one hundred and forty-three thousand dollars, to be paid by the plaintiff. The right to exercise this option expired at midnight of January 8, 1907. The determination whether or not plaintiff would accept said contract within that time was committed by plaintiff to its engineers, Sanderson & Porter, of New York. Plaintiff’s headquarters for said construction work was at Yallecito, Tuolumne County, where H. F. Jackson, its manager, conducted the work. It also maintained an office in the Kohl building in San Francisco, in charge of H. P. Yeeder. A day or two before January 8, 1907, Jackson went to San Francisco, expecting there to receive a telegram from Sander-son & Porter, accepting or rejecting the contract offered by
On that day, Sanderson & Porter, sent to plaintiff, at Vallecito, the following telegram regarding this option: “Wire Jackson that we will exercise option on Mine Line and header.” The plaintiff’s agent at Vallecito received this telegram and thereupon wrote and delivered to the agent of the Western Union Telegraph Company at Vallecito, for transmission to Jackson at San Francisco, the following telegram:
■ “Vallecito, Cal., Jany. 8, 1907. “H. F. Jackson, 909 Kohl Building, S. F., Cal.
“Hobart Porter wires he will exercise option on Mine Line and header.
“(signed) Union Construction Company.”
This telegram was received by the telegraph company at its San Francisco office at 8:35 p. m. of that day. It was not delivered to Jackson, or to plaintiff, until after 9 a. m. the next day. Porter had left New York for California and had arrived at Chicago, on January 8th. He there delivered to the defendant for transmission the following telegram:
Chicago, Jan. 8, 1907.
“H. P. Veeder, Kohl Building, San Francisco,
“Advise Jackson that we wired him Vallecito to close option oñ Mine Line and header.
“ (signed) Hobart Porter.”
The complaint alleges that, after the defendant had received the dispatches at its San Francisco office, and during the evening of January 8th, the plaintiff inquired of the defendant’s agent at that office to learn whether or not said telegrams had been received by defendant and was informed by said agent that they had not been received. Jackson testified, for the plaintiff, that he went out to dine Avith Field that evening and remained at the restaurant with him until nearly ten o’clock. As stated, he was not allowed to testify that he directed Veeder to stay at the office and bring or send him any telegrams that were received while he was at the restaurant. The court also refused, to permit him to testify that during his absence at dinner he had inquired of Veeder by telephone in regard to the telegrams. Veeder testified that he remained at the plaintiff’s office after Jackson went out to dine, that Jackson left at 6 o’clock, that he was himself absent at dinner from 6:30 to 7:15, that he then stayed in the office until 10:15 that evening, that no telegrams were received or delivered there during that time, and that when he reached the office after dining he looked about to see if a notice of a telegram had been left during his absence. Finding none, he then took down the telephone and called the central telephone office to connect him with the line running to the Western Union Telegraph Company’s office in the city. The connection was made and some one responded,- apparently at the Western Union office. He then inquired if that was the Western Union Telegraph office and received through the receiver the answer: “Yes.” He did not recognize the voice of the person ansivering and had no means of knowing that he was connected with the defendant’s office, except that he had made the call and received the response in the usual and customary manner of telephone
The Kohl building and the defendant’s office were half a mile apart. A street-ear line was in operation from a point near the defendant’s office to and beyond the Kohl building. The excuse offered by the defendant for failing to make delivery that evening was that it had no messengers at its office during the evening. The Kohl building was in the midst of the district destroyed by the great fire of April, 1906, and in January, 1907, there were few buildings near it that were occupied in the evenings after dark. The evidence offered, as will presently be more fully shown, would have a tendency to prove gross negligence of the defendant in relation to the delivery of the telegrams. For that purpose it was material and, in view of the fact that the court may be presumed to have granted the nonsuit because it believed no negligence was proven, it was very important to the plaintiff. Its exclusion is assigned as error.
The defendant claims that, under the circumstances we have stated, the telephone conversation was not admissible as evir
We are of the opinion, however, that there was sufficient circumstantial evidence to make a prima facie case of identity and authority. The courts take notice of discoveries and inventions that have become of common and general use. The telephone has been in common use for more than thirty years past. For many years its use, especially in such large cities as San Francisco, has been well nigh universal, more so than the telegraph and almost as much so as the mails. The system and method of communication by that means is universally known among business men. Practically every business house and office has one or more of such instruments and uses it daily and frequently. Large establishments maintain a local system with a special operator at their place of business, with ear to the receiver, to hear calls and answer them or connect the local wire with the person called for or some one authorized to act in the particular matter. The telephone companies keep a large force of operators in their central stations constantly engaged in connecting the wires of the different subscribers who wish to speak to each other. The process of making these connections is so rapid and frequent that it becomes almost mechanical. The telephone companies are engaged in public service of the same character as that of a telegraph company or a common carrier, and they are in like manner
They show that the telephone and its use have become so much a part of daily life and experience, that business carried on over it must be deemed to be subject to the operation of the disputable presumptions or inferences applicable to like affairs, as declared in section 1963 of the Code of Civil Procedure. We refer to the following subdivision of that section, “That private transactions have been fair and regular,” (subd. 19); “That the ordinary course of business has been followed”; (subd. 20); “That things have happened according to the ordinary course of nature and the ordinary habits of life” (subd. 28). These presumptions have been recognized by the courts and applied to the cognate operations of the telegraph and the post-office. If a letter or telegram is duly addressed, prepaid and delivered in the post-office receptacle or to the telegraph company, there is a disputable presumption of fact, arising from the almost invariable result, that it has been transmitted and delivered in regular course to the person addressed. (Eppinger v. Scott, 112 Cal. 371 , [ 53 Am. St. Rep. 220 , 42 Pac. 301 , 44 Pac. 723 ]; Code Civ. Proc., sec. 1963, subd. 24; 1 Greenleaf on Evidence, sec. 40; 1 Elliott on Evidence, sec. 107; 1 Wigmore on Evidence, sec. 95.) For like reasons, if nothing unusual occurs in the prom ess, there would be a disputable presumption that a request to the central telephone operator to connect the caller with a named number in the directory, and to call such subscriber by means of a bell or other signal, has been complied with by making the proper connection with the number and giving the necessary signal at the other end of the line.
For these reasons we conclude that when it appeared that plaintiff and defendant each maintained a business office in the same city, that each had a telephone in such office connecting with the same city telephone system, with their respective
The question has never heretofore been considered by this court. It has frequently arisen in other states and the decisions in the main support our conclusion. The following cases, in effect, declare the rule to be as we have stated it: Wolfe v. Railway Co. [1888], 97 Mo. 481 , [ 10 Am. St. Rep. 331 , 3 L. R. A. 539 , 11 S. W. 49 ] ; Globe P. Co. v. Stahl [1886], 23 Mo. App. 451 ; Guest v. Hannibal etc. Co. [1898], 77 Mo. App. 262 ; Kansas C. S. Co. v. Standard W. Co. [1907] , 123 Mo. App. 13 , [ 99 S. W. 765 ]; Star. B. Co. v. Cleveland F. Co. [1907], 128 Mo. App. 517 , [ 109 S. W. 802 ] ; Rock I. etc. Co. v. Potter [1889], 36 Ill. App. 592 ; Rogers Grain Co. v. Tantor [1907], 136 Ill. App. 533 ; Godair v. Hamilton N. B. [1907], 225 Ill. 572 , [ 116 Am. St. Rep. 172 , 8 Ann. Cas. 447, 80 N. E. 407 ]; General H. Soc. v. New Haven Co. [1907] , 79 Conn. 581 , [ 118 Am. St. Rep. 173 , 9 Ann. Cas. 168, 65 Atl. 1065 ] ; Knickerbocker Ice Co. v. Gardiner Co. [1908] , 107 Md. 571 , [ 16 L. R. A. (N. S.) 746 , 69 Atl. 405 ] ; Miller v. Lieb [1909], 109 Md. 425 , [ 72 Atl. 466 ]; Conkling v. Standard O. Co. [1908], 138 Iowa, 596 , [ 116 N. W. 822 ] ; Western U. T. Co. v. Rowell [1907], 153 Ala. 314 , [ 45 South. 73 ]; Barrett v. Magner [1908], 105 Minn. 120 , [ 127 Am. St. Rep. 531 , 117 N. W. 245 ] ; Holzhauer v. Sheeny [1907], 127 Ky. 35 , [ 104 S. W. 1034 ] ; Gillilland v. Southern R. Co. [1910], 85 S. C. 36 , [ 137 Am. St. Rep. 861 , 27 L. R. A. (N. S.) 1106 , 67 S. E. 20 ].
There are a few decisions to the contrary: Young v. Seattle T. Co. (1903), 33 Wash. 225 , [ 99 Am. St. Rep. 942 , 63 L. R.
In the application of the rule many of the conditions we have mentioned are usually deemed matters of judicial knowledge, or as implied from other facts, and are not expressly shown. The general rule, as gathered from the foregoing decisions, is that where it is shown that the witness-called up the other party at his place of business, through the central station with which both were connected, and received a response as in the usual course of business over the telephone, this is sufficient prima facie identification of the speaker at the other end of the line as the party called, or his authorized agent, and that, upon such proof, the ensuing conversation, if otherwise admissible, may be testified to by the witness. It is proper to add that the weight of such evidence depends largely upon the circumstances of each case and is always a question for the trial court or jury. The court below erred
Each of the messages in question were written upon a blank provided by the defendant containing a contract purporting to exempt it from liability for damages in excess of the charges for transmission. It is claimed that this relieves the defendant from the damages here claimed. The contract is as follows :—
“To guard against mistakes or delays, the sender of a message should order it repeated; that is, telegraphed back to the originating office for comparison. For this, one-half the regular rate is charged in addition.
“It is agreed between the sender of the following message and this company, that said company shall not be liable for mistakes or delays in transmission or delivery, or for nondelivery of any unrepeated message, beyond the amount received for sending the same; nor for any mistakes or delays in the delivery of any repeated message, beyond fifty times the sum received for sending the same, unless specially insured, nor in any case for delays arising from unavoidable interruption in the working of its lines, or for errors in cipher or obscure messages. . . .
“Correctness in the transmission of a message to any point on the lines of this company can be insured by contract in writing, stating agreed amount of risk, and payment of premium thereon, at the following rates, in addition to the usual charges for repeated messages, viz.: one per cent, for any distance not exceeding 1,000 miles, and two per cent for any greater distance.”
This contract is identical with those considered by this court in Hart v. Western U. T. Co., 66 Cal. 581 , [ 56 Am. Rep. 119 , 6 Pac. 637 ]; Redington v. Pacific P. T. C. Co., 107 Cal. 321 , [ 48 Am. St. Rep. 132 , 40 Pac. 432 ], and Coit v. Western U. T. Co., 130 Cal. 661 , [ 80 Am. St. Rep. 153 , 53 L. R. A. 678 , 63 Pac. 84 ], except that the words, “whether happening by negligence of its servants or otherwise,” occurred in those messages in the second paragraph immediately after the words, “unrepeated message,” and before the word, “beyond.” It was decided in those cases that the taking of such contract was a reasonable precaution by the company, that it was lawful and binding upon all senders of messages who assented to
It is admitted that the usual tolls for such messages were in each instance paid to the defendant, and that each was an unrepeated message. Upon the trial, however, the plaintiff expressly waived any claim for the amount of the tolls paid as damages. For this reason, if no further damage appeared, the court below was justified in granting the nonsuit.
The message from Porter at Chicago to Veeder at the Kohl building in San Francisco was received at the main office of the defendant in the Ferry building in San Francisco at 6:57 p. m. of January 8th. The defendant claims that this was not proven. The evidence shows, however, that a note of that time was made by the defendant upon the copy of the message delivered by it to Veeder, and from what was said' at the trial concerning this fact, by the court and counsel, it is a fair inference that these figures were intended by the defendant as a note of the hour and minute of the arrival of the message at its office in the Ferry building. It, therefore, constitutes evidence of that effect. Street-ears were then running frequently from a point near the Ferry building, along California Street, and directly in front of the Kohl building, to which the message was directed. According to the evidence offered and improperly excluded we must assume that the plaintiff would have been able to prove thereby that within half an hour after defendant had received this message, and while the copy for delivery was lying among the messages in its possession at the Ferry building office, and then awaiting delivery, •Veeder inquired of defendant’s agent at said office to learn if such message had been received by the defendant, and that he was informed by defendant’s agent that none such had been received. After receiving this information that the telegram was important and that Veeder could be communicated with by telephone the defendant failed to deliver either this telegram or the one received later to Jackson, apparently on the same subject, on that evening, and so far as appears, made no effort to do so or to inform Veeder thereof. If these facts had been proven they would have tended to prove gross neglect on the part of the defendant in failing to deliver the Veeder message on that day, or to inform Veeder of its arrival.
The respondent contends that the evidence does not show that the plaintiff has sustained any damage except to the amount of the charges which, as above stated, the plaintiff waived. Taking the evidence as a whole, it is plain that if either message had been received by the plaintiff’s agents during the evening of January 8th, the option would have been exercised by them on behalf of the plaintiff. In that event, the Iron Works would have been bound to furnish the pipe and construct the Mine Line for one hundred and forty-three thousand dollars. After waiting until late that evening for the expected telegram Jackson and Field agreed that the option should be extended for an additional period of fifteen days but that the Iron Works should be entitled to change the price mentioned in said contract. Within the fifteen days thus allowed the plaintiff and the Risdon Iron Works agreed to and executed a modification of the contract. The evidence shows that this was the best contract the plaintiff could obtain for the Mine Line. By its provisions the price for the Mine Line, instead of being fixed at one hundred and forty-three thousand dollars, was to be at the rate of eight cents per pound for the weight of metal furnished for the Mine Line. Jackson testified that this change added to the price of the Mine Line the sum of $21,252 in excess of the sum of one hundred and forty-three thousand dollars fixed by the first contract. He further testified that the price of steel had raised in the interval between the making of the first contract and the eighth day of January about one-quarter to one-half a cent. There was a provision in the first contract that if the price of steel rose before the option was exercised, the price fixed should be increased accordingly. Jackson stated that he was not sure that the increase was no more than half a cent per pound. From this respondent argues that the actual advance may have been enough to cover the difference in price between the two contracts and hence that no loss was shown. It is apparent, however, from all of
The California decisions above cited are all cases of mistakes made in the' words of the message in transmitting it through the wires or in receiving it at the office of its destination. The negligence complained of in the present case is a delay in the delivery of the message after it had been correctly transmitted. The plaintiff contends that there is an obvious distinction between errors or delays in transmission and a delay in the delivery of a message after its arrival. It is argued that since the repeating of a message would have no tendency to prevent a delay in delivery, but merely secures accuracy in transmission, it has no logical relation to any other object; that as the provision for insurance applies only to accuracy of transmission, and the contract as a whole affords the sender no means of protection against a delay in the subsequent delivery, the question of the reasonableness of such a contract, and its accordance with public policy, is not settled by said decisions. Able and exhaustive arguments are presented on each side of this question.
The question whether the restriction of liability for errors in transmission is void because contrary to public policy has produced an unusual conflict in the authorities. In a comparatively few jurisdictions, outside of California, the contract is declared to be valid unless there is gross negligence or willful misconduct. These are as follows: Maryland, in United States Tel. Co. v. Gildersleeve, 29 Md. 232 , [ 96 Am. Dec. 519 ]; Massachusetts, in Wheelock v. Postal etc. Co., 197
For the opposite side, the following states declare such' contracts to be against public policy and void as a protection to the company against its own ordinary negligence. We cite but one case from each state: Alabama, in American etc. Co. v. Daugherty, 89 Ala. 196 , [ 7 South. 660 ] ; Arkansas, in Western Union Tel. Co. v. Short, 53 Ark. 440 , [ 9 L. R. A. 744 , 14 S. W. 649 ]; Florida, in Western Union Tel. Co. v. Milton, 53 Fla. 496 , [ 125 Am. St. Rep. 1077 , 11 L. R. A. (N. S.) 560 , 43 South. 495 ] ; Georgia, in Western Union Tel. Co. v. Blanchard, 68 Ga. 299 , [ 45 Am. Rep. 480 ] ; Illinois, in Western Union Tel. Co. v. Tyler, 74 Ill. 168 , [ 24 Am. Rep. 279 ] ; Indiana, in Western Union Tel. Co. v. Meredith, 95 Ind. 94 ; Idaho, in Strong v. Western Union Tel. Co., 18 Idaho, 389 , [Ann. Cas. 1912A, 55, 30 L. R. A. (N. S.) 409 , 109 Pac. 910 ; Iowa, in Harkness v. Western Union Tel. Co., 73 Iowa, 193 , [ 5
In this connection it may be observed that it is somewhat difficult to reconcile the California decisions with our Civil Code. Section 2162 provides that “A carrier of messages for reward must use great care'and diligence in the transmission and delivery of messages. ’ ’ Section 1667 declares that a contract which is contrary to an express provision of law or to the policy of express law is unlawful. Section 1668 declares that “all contracts which have for their object, directly or indirectly, to exempt any one from responsibility for his own . . . violation of law, whether willful or negligent, are against the policy of the law.” It is essential to the legal existence, of a contract, that is, to its recognition by the law as a contract, that it shall have a lawful object. (Sec. 1550.) Where the object of a contract is unlawful the contract is void. (Sec. 1598.) It seems clear that if the law requires the telegraph company to use great care and diligence in the transmission and delivery of messages, and the object of this contract, directly or indirectly, is to relieve it from responsibility for the damages caused by its failure to use great care and diligence in so doing, or, in other words, by its negligent violation of section 2162, then by the express provision of section 1668 the
Under these circumstances, we may consider whether or not the contract in question should be construed to apply to delays in delivery of a message which has been correctly transmitted. These contracts are prepared by the telegraph company and printed upon all of its blanks provided for the use of the public. They are not often the result of negotiation between the parties. The sender has no choice, nor any reasonable opportunity to make terms not specified in the printed contract. Although he does'not sign it he is presumed to have seen it, and from his failure to object, he is taken to have assented to it. Hence, if it is uncertain in any particular, its language on that point is to be interpreted most strongly against the company. (Civ. Code, sec. 1654.) The subject to which it was intended to relate and the delays and mistakes against which it was intended to provide are shown by the opening words, to wit: “To guard against mistakes or delays, the sender of a message should order it repeated.” Where a guard is offered against mistakes and delays which are not more particularly described, a reasonable construction of the language is that the mistakes and delays intended are those which the proposed guard would prevent; in this case, mistakes and delays which a repetition of the message would disclose, so that they could be immediately corrected or avoided. That this was the object and meaning of the con
There are some cases in the states which hold the contract valid as to errors in transmission which extend the rule tó delays in subsequent delivery. But the better reason and the greater number of cases uphold the views we have stated. In Texas the contract is held valid as to mistakes in transmission but invalid with respect to delays in delivery. (Gulf etc. Co. v. Wilson, 69 Tex. 741 , [ 7 S. W. 653 ]; Western Union Tel. Co. v. Bennett (Tex. Civ. App.), 124 S. W. 154 .) In Barnes v. Western Union Tel. Co., 24 Nev. 140 , [ 77 Am. St. Rep. 791 , 50 Pac. 438 ], and Western Union Tel. Co. v. Graham, 1 Colo. 234 , [ 9 Am. Rep. 136 ], it is conceded that it is valid against errors in transmission but held to be void as to delays in delivery. In all of these cases the distinction we have pointed out is held to be good. In Box v. Postal Tel. Co., 165 Fed. 138 , [ 28 L. R. A. (N. S.) 566 , 91 C. C. A. 172 ], the court says: “Although the regulation purports to be made to guard against mistakes or delays, it should be construed to refer to such mistakes and delays as could be corrected or avoided by repetition or comparison.” In Beatty v. Western Union Tel. Co., 52 W. Va. 412 , [ 44 S.
The judgment is reversed.
Sloss, J., and Angellotti, J., concurred.
Hearing in Bank denied.