Majority
Headnote
Vendor and Vendee—Construction of Contract for Sale of Minino Property—Covenant for Development Work and Installation of Improvements.—The contract for the sale of certain mining property, to avoid which this action was brought, after providing that deferred payments of the purchase price should be made out of the gross output of the mine, contained covenant's on the part of the vendee to fit up the mill with described machinery, and to continue development work on the property at such rate as to keep the mill in operation, provided said vendee with due diligence should find ores sufficiently valuable, and should not be prevented from such work by unavoidable accident. This was immediately followed by a covenant reciting that “abandonment of work for a period of six months at any one time except as above,” should operate to forfeit the vendee’s rights. It was also agreed that the property should be kept free from debts and liens on account of the development or other work done by the vendee, and that the vendee should make a report of its gross earnings to the vendors four times a year. Eeld, that' the contract, read as a whole, justified the construction that development work was to be commenced by the vendee from the time it took possession, or at least very promptly following that event, and that the evidence supported a finding that such work had not been done by the vendee as agreed, and that it had also failed to place upon the property the promised improvements.Plaintiffs brought suit to quiet their title to certain real property and to have a certain contract between plaintiffs and defendant declared void. Judgment was given in favor of plaintiffs. Defendant appeals therefrom, and also from 'an order denying its motion for a new trial.
There is no denial by defendant that the record title to the land is in plaintiffs. The contract between the parties to this suit was one with reference to the property, and it recited that a deed of conveyance had been executed by plaintiffs and placed in escrow, there to remain until the sum of thirty thousand dollars should be paid as set out in-the agreement. This deed by its terms conveyed oné hundred and sixty-five acres of land in Siskiyou County to defendant. Upon the property was the “Little Maggie Quartz Mine.” The purchase price was to be paid as follows: One thousand two hundred dollars on the execution of the contract, eight hundred dollars in sixty days, and the balance out of twenty per cent of the gross output of the mine. Payment was to be made in five years, unless the veins and values of ore should not continue in depth, in which event defendant was to be allowed two years longer to complete the payment of the pur
The court found, among other things, that defendant failed to perform work and labor on the property as agreed under the contract; that it neglected to place upon the land the improvements provided by the covenants of the agreement; that contrary to the contract the corporation permitted debts to accumulate against the property and attachments to be levied thereon; and that for more than a year defendant did not do any work or labor of any sort upon the land or any portion of it.
The appellant attacks the finding that it covenanted to begin development work immediately after the execution of the contract. It is the contention of defendant that the agreement was merely to do sufficient development work to keep the mill in operation. Reading the contract as a whole, however, the court was justified in the conclusion that the parties to it contemplated development work from the time defendant took possession of the property, or at least very promptly following that event, because there were to be reports regarding the gross earnings every three months.
Defendant also says that the evidence does not support the finding that no work or labor was performed in the development of the mine, and that the mining company neglected to place upon the property the promised improvements specified
Certain evidence was introduced for the purpose of showing that defendant had violated the covenant to keep the property free from debt. Counsel for appellant say that this matter was not put in issue by the pleadings, and that therefore the evidence was improperly admitted. In the answer defendant set out the contract and alleged compliance with it in all particulars. The evidence to which objection is now made was clearly responsive to the issue of full performance tendered by defendant and presumed to be denied by plaintiffs.
Appellant objected to the admission in evidence of certain letters written by Bossman to one of the plaintiffs. These letters had reference to the machinery invented by Mr. Bossman and intended for the mine. Appellant’s principal contention was that at all times it was diligently preparing to install this machinery, and that Mr. Bossman had accepted its orders
Appellant’s whole defense was based upon the assertion that due .diligence had been practiced by it, and that it had not been granted a reasonable time for the installation of the new machinery. The things done and omitted by the parties to the agreement were such that we cannot say that the trial court was not justified in deciding that appellant was in default when the suit was instituted.
The judgment and order are affirmed.
Henshaw, J., and Lorigan, J., concurred.