Headnote
Contract — Installation of Fire-extinguishing Apparatus — Time of Performance—Verbal Agreement Varying Terms of Written Contract.—A written contract for the installation of an automatic fire-extinguishing apparatus in a factory, which specifies no-time for the completion of the work, is to be performed within a réasonable time; -and where the contract, by distinct and unequivocal language, prohibits any change or modification of its terms unless the same is indorsed in writing upon it by the president of the contractor, an agent of the contractor is without power by verbal agreement to vary the terms of the contract so as to provide for a shorter time for performance.We will treat this as an appeal from the judgment and from an order denying plaintiff’s motion for a new trial, although respondents contend that no efficient appeal was made from the order, owing to the failure of plaintiff to serve them with proper notice.
Plaintiff entered into a written contract on July 7, 1910, with the Manufacturers’ Automatic Sprinkler Company, whereby the latter agreed for a certain consideration to install in the former’s box factory an improved “wet-pipe” system of automatic sprinklers and fire-extinguishing apparatus. On September 22, 1910, and while the sprinkler company was putting in the pipes for the installation of said system, a fire broke out in the box factory and destroyed it. The plaintiff corporation sued for fifteen thousand dollars damages alleging that when the fire occurred the work was being done in a dilatory manner; that the manufacturers’ company had agreed to install the system within three weeks following July 10, 1910; and that if this promise had been kept, or if within a reasonable time the work had been completed, the fire would have been extinguished and plaintiff’s loss prevented. The Automatic Sprinkler Company of America is sued as the successor to the obligations of the other corporation defendant. By a second count the latter company is sued for five hundred dollars money had and received from plaintiff on the twenty-ninth day of September, 1910.
After trial the court made findings substantially support
All of these findings are substantially supported by the testimony, and we discover no material error in the record to plaintiff’s prejudice.
Plaintiff’s counsel lay great stress upon the verbal promise made by Barney, the agent for the other, contracting corporation, that the installation of the sprinkler should be within three weeks, but it is evident that no dependence was placed on this promise by plaintiff’s officer, Mr. Brookings, who conducted the negotiations. It is true that he testified that this agreement as to the time of installation was the controlling feature of the contract, yet he did not cause it to be put into
It is not necessary to analyze in detail the testimony upon the subject of the reasonable amount of time necessary to complete the work. There was testimony to the effect that the contract, under the rules of the manufacturing corporation, had to be sent to New York state for approval before the representatives of the contractor in this state could act upon it. So, also, there was testimony that the materials were only obtainable in Syracuse, New York, and that their shipment to Highland in this state, where the work of installation was to be done, consumed thirty-five days or more. The peculiar appliances necessary to complete the work were received by that defendant then busy installing the apparatus only on September 22d. Whether these delays were reasonable or not was a matter peculiarly for the superior court to determine and we will not disturb the findings of that tribunal based, as they were, upon conflicting testimony.
Appellant’s contention that the failure to complete the construction of the fire-extinguishing machinery was the proximate cause of the destruction of the building by fire has no force. In this state the law is definitely settled adversely to the views expressed in the briefs filed by appellant’s counsel. In Hunt Brothers do. v. San Lorenzo Water Co., 150 Cal. 51 , [ 7 L. R. A. (N. S.) 913 , 87 Pac. 1093 ], the suit was for damages because of loss by fire against a corporation that had promised to furnish certain appliances for protection against fire but had failed to keep its agreement. It was held in that case that where the contract had been executed to the extent of installing and commencing the contemplated service, and where both parties were acting thereunder, the one being bound for a consideration to furnish water and the other depending upon such service for the extinguishment of fires, only then could the breach of the agreement to supply water be the basis for damages because of loss by fire. The proximate cause of the loss to plaintiff was the fire, not the incomplete condition of the fire-extinguishing plant. In Schaeffer Piano Mfg. Co. v. National Fire Extinguisher Co., 148 Fed. 159 , [ 78 C. C. A. 293 ], the fire-extinguisher company had entered into an agreement very similar to the one here' under review. In that contract, as in this, was a stipulation that in case of destruction of the building by fire before completion of the equipment, the piano company would be liable
At the trial plaintiff endeavored to prove that the check for five hundred dollars was sent by mistake, and there was some showing of an attempt to stop payment on it after the fire. But by its own statement of account the plaintiff had later fixed this item as a payment on the contract. This was a ratification of the payment on account in any view of the case, and the court’s finding that the money was not sent by mistake therefore finds ample support. It was alleged in the answer that this sum was applied as a credit against plaintiff’s obligation to pay for materials destroyed by the fire and for work performed up to that time. While there was no definite proof that the materials and labor furnished by the sprinkler companies amounted to more than five hundred dollars, there was testimony that they amounted to approximately that sum. We think the court was justified in holding that plaintiff by not demanding an accounting had waived any recovery of the five hundred dollars paid under the contract.
There are several alleged errors in admitting and excluding testimony which appellant specifies. We have examined them and find no substantial merit in any of the contentions regarding them.
The judgment and order are affirmed.
Henshaw, J., and Lorigan, J., concurred.
Cases cited
- Peterson v. Chaix 5 Cal. App. 525 p. 682
- Standard Box Co. v. Mutual Biscuit Co. 10 Cal. App. 746 p. 682
- Belden v. Union Central Life Insurance 167 Cal. 740 p. 682
- Hunt Bros. v. San Lorenzo Water Co. 150 Cal. 51 p. 683