Majority
Headnote
[1] Contracts—Performance of Services—Satisfaction of Party— Cases of Operative Fitness or Mechanical Utility.—In contracts involving matters of fancy, taste, or judgment, when one party agrees to perform to the satisfaction of the other, he renders the other party the sole judge of Ms satisfaction without regard to the justice or reasonableness of his decision, and a court or jury cannot say that such party should have been satisfied where he asserts that he is not. The rule is also applied to cases of operative fitness or mechanical utility when the contract clearly provides that performance shall be satisfactory t'o the promisor.Plaintiff sued for damages caused fry an alleged wrongful discharge of plaintiff from the defendant’s service. The court below made findings and entered judgment in favor of the plaintiff for $3,617.17, being the full amount prayed for in the complaint. Defendant appeals.
The defendant was engaged in the business of manufacturing glazed brick. Plaintiff was employed by the defendant as an “expert glazeman” for the term of three years beginning February 10, 1914, under a contract in writing made on February 12, 1914, and modified on May 12, 1914. The first contract provided that Tiffany should be employed by the defendant as expert glazeman for one year at three thousand dollars a year, with the privilege to defendant of changing the employment to three years at two thousand dollars per year at any time within six months “providing a product satisfactory to the defendant” was obtained within sixty days from the date of the contract. Tiffany began work and continued until May 12, 1914, on which date a modification
“In consideration of the above provisions Mr. Tiffany will not hold the Pacific Sewer Pipe Company liable under said contract, in case for any reason the Pacific Sewer Pipe Company are unable to turn out enameled and glazed brick in quantities equal to the present quality and satisfactory to the Pacific Sewer Pipe Company.
“In the latter case Mr. Tiffany is to have ninety days notice before making a change.”
Tiffany was discharged on May 10, 1915, without notice. The court found that up to that time plaintiff had fully performed his contract with a reasonable degree of skill and that the defendant, after the making of the contract, was at all times able to turn out enameled and glazed brick in quantities, equal to the quality which was being turned out on May 11, 1914, and which was satisfactory to said defendant. It is claimed that this finding is contrary to the evidence.
In the making of brick, the mud or clay is first pressed and molded to the shape desired, the glaze or enamel is then applied, and when a sufficient quantity to fill a kiln is thus prepared, the bricks are placed in the kiln and burned to the required degree. The principal duty of the plaintiff was to prepare and mix the glaze or enamel so that it would, when burned, have the hardness and other qualities necessary to make it durable and the brick salable. The glaze or enamel was a liquid into which the bricks were dipped so as to form a coat of the liquid on their surfaces.
It will be observed that the conditions expressed in the modification above quoted embraced three propositions. First, that the defendant should be able to turn out enameled and glazed brick in quantities. Second, that the brick turned out should be equal to the present quality. This obviously refers to the provision of the first contract that the three years’ employment would be made if “a product ivas obtained within sixty days from its date which was satisfactory to the defendant.” It appears from the evidence that at the time the second contract was made Tiffany was producing a quality of enameled and glazed brick which satisfied the defendant and induced it to enter into the second contract. The third proposition embraced in the added condition was that the
The next section declares: “The rule stated in the preceding section is also applied to cases of operative fitness orf mechanical utility when the contract clearly provides that performance shall be satisfactory to the promisor.” Similar statements will be found in 9 Cyc., at pages 618, 619, and 620.
A different rule applies where the contract provides for the construction of a building or the like, in accordance with plans and specifications fixed by the contract, to the satisfaction of the owner or of an architect employed by him. In these cases it is usually held that if the contract is performed as required by the plans and specifications, the person whose judgment is invoked must accept the performance and his mental condition as to satisfaction is immaterial. In such cases the question whether the work is satisfactorily done or not, arises after the contract has been executed, either in whole or in part, and the satisfaction refers to that which is already done. Elliott states the rule to be that such a contract does not justify the promisor in arbitrarily,, unreasonably, and capriciously claiming that he is not satisfied, in order to
The decisions in this state have not attempted to state the rule with reference to cases like the present. In Coplew v. Durand, 153 Cal. 278 , [ 16 L. R. A. (N. S.) 791 , 95 Pac. 38 ], which involved a building contract, there were elaborate plans and specifications, as is usual in such cases, and the work was “to be done to the entire satisfaction of the owner and the architect.” Before each payment was made a certificate was to be obtained signed by the architect. After the work was done both owner and architect stated that they were satisfied with it, but the architect refused to make a certificate. It appeared that the work was done conformable to the plans and specifications. The court merely held that under the circumstances the refusal of the certificate was unreasonable and that the contractor was entitled to recover as if it had been issued. In Gladding etc. Co. v. Montgomery, 20 Cal. App. 279 , [ 128 Pac. 792 ], the district court of appeal remarked that “the stipulation in a contract to perfrom to
The contract in the present case was an executory one. The question does not involve the acceptance of any work already done by Tiffany under his employment. He was discharged from further employment because the defendant was not satisfied with the quality of his work. There is no sufficient evidence to support the finding that the defendant was satisfied with his work. During the time of his service many kilns of brick were burned which were glazed by him, and there is evidence as to some of these that the defendant’s manager expressed himself satisfied. But there is no evidence, and no declaration or admission by any person authorized to speak for the defendant, that it was satisfied with his work as a whole. The contract authorized the defendant to discharge the plaintiff if his work was not satisfactory as a whole, although at times he might be producing brick of the finest quality. The object of the defendant in employing
The judgment for the amount awarded cannot be supported without the finding in question. None of the other findings supplies its place. The appeal must therefore be sustained.
The judgment is reversed.
Olney, J., and Lawlor, J., concurred.