Majority
Headnote
[1] Principal and Surety—Bond of Subcontractor—Default—Premature Payments by Contractor—Effect of.—The surety on the bond of a subcontractor is not released from the entire obligation, by reason of premature payments made by the contractor on the subcontractor’s default, but the effect is to leave the contractor without a .cause of action on the bond to recover the amount of the premature payments.The Southwestern Surety Insurance Company appeals from a judgment against it in favor of plaintiff upon a bond executed by it as surety for G. A. Hechler for the performance of a subcontract between Hechler and the plaintiff for the doing of a part of the work upon a building under erection by Siegel.
The Marlborough school for girls, a corporation engaged in the business of conducting a girls’ school, made a contract with Siegel for the erection of a school building on its premises
The -complaint alleges that while Hechler was engaged in the work Siegel paid him, in accordance with the terms of the contract, $4,537.87; that after Hechler abandoned the work Siegel paid for labor performed upon, and materials and supplies used in, the subcontract work by Hechler and left unpaid by him, sums amounting to $3,925.33, and that in completing the building after the abandonment by Hechler plaintiff- expended $2,139.43, which was the reasonable cost of such completion. He asked judgment for the difference between the aggregate of these sums and seven thousand dollars, the subcontract price.
The denials and affirmative allegations of the answer set up the defense that the sums amounting to $4,537.85 alleged to have been paid to Hechler while the work was going on, were not paid “in accordance with the terms of said contract,” and that Siegel violated his agreement with Hechler, for the performance of which the bond was given, by paying money to Hechler in excess of the amount due on the subcontract at the time of such payment, whereby, it is claimed, the surety was released.
The court found that while Hechler was engaged in the work Siegel paid him, “in accordance with the terms of said subcontract,” $4,526.90; that after the abandonment Siegel paid $3,925.33 on bills due from Hechler for materials and labor used in the subcontract work, and that Siegel completed the work on the subcontract at the reasonable expense of $2,139.43. This made an excess of $3,591.66 paid out by Siegel over the subcontract price, for which excess judgment was" given in favor of the plaintiff.
“Second: That the said General Contractor will in consideration of the said covenants and' agreements being strictly performed and kept by the said Sub-contractor, as herein-above mentioned, well and truly pay, or cause to be paid, unto the said Sub-contractor the said sum of money above mentioned as the Sub-contract price.
“In the manner following: Such amounts as Heehler may need for pay roll on or before twelve o’clock noon of each and every Saturday following beginning of work and balance thirty-five days after completion of this contract, but in the event that the General Contractor should deem himself insecure by reason of a possibility that the laborers or the materialmen of the Sub-contractor may file claims of liens upon said property, or may give to the Owner notices to withhold money from the General Contractor, then the General Contractor may at his option withhold further payments until furnished with receipts or releases from all such materialmen and laborers.”
It is the contention of the plaintiff that the phrase “such amounts as Heehler may need for pay-roll on or before twelve o’clock noon of each and every Saturday following beginning of work” covers only payments of the weekly wages of the men employed by Heehler, or other regular weekly sums contracted to be paid by him for the doing of work on the subcontract. It appears from the evidence that in the course of the work Hechler incurred bills in the performance thereof upon which Siegel paid the sums following, to wit: On September 28, 1915, to Butterfield & Scaer $350, for steam shovel work; October 1, 1915, to E. E. Scott, for hauling and excavating, $450; and on October ”21, 1915, to L. A. Rock and Gravel Company $759, for materials used in the work, a total of $1,559. The point made by the appellant is that these sums could not have been included in any pay-roll, within the meaning of the subcontract, and that tmder its terms they did not become due to Heehler, or payable on his account, until thirty-five days after the completion of his subcontract. The argument is that by this departure ’ from the terms of the contract the surety was prejudiced and thereby it was released from its obligation. If the word “pay-roll” has the
[1] It is not an accurate statement of the law to say that the surety would be released from the entire obligation by reason of premature payments. They would not be an alteration of the contract for the performance of which the defendant had become surety. They would be a departure therefrom or a violation thereof, effected by the parties during its performance, without the consent of the surety. The legal result of such departure would not be to release the surety from the entire obligation. The effect would be that Siegel would have no cause of action on (the bond1 to recover from the surety that part of Hechler’s defalcation that was made up of these premature payments. The authorities cited by appellant concerning the effect of a material alteration in the contract after the surety has become bound thereon and without its consent are not strictly applicable.
There are persuasive reasons, growing out of the nature of the subcontract and the work to be done thereunder, in connection with the law as to the liens of mechanics, for giving the above-quoted word “pay-rolls” a broader meaning. But we take a view of the case which renders it unndcessary to determine whether the narrower or broader interpretation is correct and we therefore leave the question undetermined. There are other terms of the subcontract and there were other circumstances, both of law and fact, which must be taken into consideration and which show that Siegel had the right to pay these bills at the time they were paid.
The subcontract provides that Hechler shall save Siegel “free and harmless” from any and all liability which might accrue against or upon Siegel as the result of any default of Hechler in the performance of the subcontract. By the bond executed by the surety company it became bound to the effect that Hechler should perform all the covenants and agreements on his part in said subcontract, including, of course, the one just mentioned, and should indemnify and save harmless the said Siegel against all loss which he might sustain by reason of any claim or claims of lien filed with the county recorder or any notice given to the owner to withhold money from Siegel for any labor performed or material furnished in the work, “or by reason of any demands or
For these reasons we are of the opinion that the finding of the court, of which appellant complains, to the effect that all sums of money paid by plaintiff to defendant Hechler were paid in accordance with said subcontract and for payrolls, was immaterial and not prejudicial to the appellant, even if it were based on an erroneous construction of the contract. The evidence shows that these payments were not made to Hechler personally, but were paid to the respective claimants by Siegel at Hechler’s request. As Siegel had a right to pay them, it is immaterial whether they were technically to be included in the pay-rolls or not.
There is a general finding that while Hechler was engaged in the work Siegel paid to him, in accordance with the terms of the subcontract, the sum of $4,526.90. This sum includes the above-mentioned payments claimed to be premature. We have shown that these payments were paid in accordance with the terms of the subcontract. This finding is supported by the evidence and it is sufficient to support the judgment.
The judgment is affirmed.
Lawlor, J., and Olney, J., concurred.