Majority
Headnote
[1] Contract — Performance—Finding—Conflict of Evidence—Appeal.—In an action for damages for breach of a contract to manufacture and deliver goods, a finding on conflicting evidence that the defendant had not failed, neglected, or refused to proceed with the work of manufacture, but that defendant had at all times diligently proceeded with the work, must be upheld on appeal.Plaintiff appeals from a judgment in favor of defendant in an action for damages for breach of contract. The undisputed facts, briefly summarized, are these: The plaintiff corporation and the defendant entered into an agreement, dated March 5, 1918, whereby defendant agreed to manufacture and deliver to plaintiff, at Los Angeles, one thousand self-starters for Ford automobiles, to be known as “Globe Starters,” a device covered by patent of which plaintiff was the owner. Plaintiff agreed to pay defendant eight dollars apiece for said starters, paying one thousand dollars in advance and seven dollars each per starter as and when deliveries of any number of said starters were made. Plaintiff paid the one thousand dollars.
On April 16, 1918, after considerable negotiations between the parties, plaintiff and defendant entered into a second contract, which it was agreed was to take the place of the prior agreement. By the terms of the second contract plaintiff was to pay ten dollars each for one thousand starters in the following manner: The one thousand dollars already paid under the first contract was to be considered as a first payment under the second contract, plaintiff was to make another thousand dollar payment on May 1, 1918, and was to pay eight dollars each for the starters as delivered. Six days after the execution of this second contract, namely, on April 22, 1918, the president and vice-president of the plaintiff corporation, who conducted all the arrangements on behalf of plaintiff, called at defendant’s place of business and had a conversation with defendant in regard to the progress of the work contracted for. During that conversation defendant presented for payment by plaintiff a bill of approximately two hundred dollars. Whether or not defendant unjustifiably refused to perform his part of the contract of April 16, 1918, unless plaintiff paid the bill so presented was the primary point for determination by the trial court in the instant case.
Shortly after the conversation of April 22d, and without further communication with defendant, plaintiff, on April 29, 1918, instituted the present action for damages for alleged failure and refusal of defendant to proceed under the contract. Defendant denied the allegations that he had failed or refused to carry out the contract, and filed a cross-complaint, alleging a breach of contract on the part of plain
It appears that five starters, the only ones which have been manufactured or delivered by defendant, were received by plaintiff from defendant on April 13, 1918, three days prior to the consummation of the second contract. It also appears that, when the first contract was made, plaintiff transferred to defendant certain patterns for use in the manufacture of the starters, that some changes in these patterns were later found to be necessary and were authorized by a Mr. Poole, a mechanic in the employ of plaintiff, who was the inventor of the starter and was placed by plaintiff in defendant’s shop for the purpose of supervising and making suggestions for the proper carrying out of the work and directing changes that he found necessary in the construction of the starters. The said changes in the patterns were ordered and paid for by defendant. The items of the bill presented by defendant, during the conversation of April 22d, for payment by plaintiff consisted of charges for the alterations to the patterns and fifty dollars for the five starters delivered on April 13th.
It was the testimony of the president of the plaintiff corporation, corroborated by that of the vice-president, who is the father-in-law of the president, that, upon their refusal to pay this bill when presented by defendant at his office on April 22d, defendant declined to continue with the work on the starters. On the other hand, defendant himself positively and repeatedly testified that, while he urged the payment of the bill on that occasion, he did not refuse to go ahead with the work under the contract if the bill was not paid, but, on the contrary, that he endeavored to point out to the two officers of the plaintiff corporation that the work was progressing with all possible rapidity. When asked by the court as to whether he said that he would not proceed with the work under the contract unless the bill was paid, defendant answered: “No, sir. I wouldn’t say it even if I wanted to say it.” Plaintiff contends that this voluntary statement of defendant accompanying the denial was so evasive as to destroy the force of the denial. The statement may have been superfluous and not responsive to the question, but it can scarcely be designated as evasive. Moreover,
The testimony in behalf of defendant upon this phase of the case is amplified by inferences naturally and reasonably arising from the proven circumstances. There is little likelihood that, a few days before the second thousand dollar payment became due under the contract, defendant would have made a refusal of performance contingent upon the payment by plaintiff of a bill amounting to less than two hundred dollars. The possibility is rendered more negligible by the steps which had already been taken by defendant in carrying out the contract. Admittedly a large amount of castings for use in making the starters had been delivered to defendant, and defendant had placed an order for springs
[1] From what has been said it is apparent that this appeal, for the most part, presents the oft-recurring and fruitless question of the correctness of a decision of a trial court based on a consideration of conflicting, .competent evidence. In view of the sufficiency of the evidence in support thereof, the trial court must be upheld in its finding that “it is not true that defendant failed, neglected, and refused, or failed or neglected or refused, for a period of forty-two days, or for any period, or at all, to proceed with the work of manufacturing said starters, but, on the contrary, it is true that at all times after the 5th of March, 1918, defendant diligently proceeded with said work.”
[2] Plaintiff complains of alleged errors in regard to the admission of evidence bearing upon the question of damages' The first alleged error is the admission in evidence of the bill for alterations to the patterns and for the five starters delivered on April 13th, and including the amount thereof in the damages awarded defendant. It is claimed that plaintiff did not agree to pay for the changes to the patterns and did not owe more than thirty-five dollars for the five starters, for the reason that they were delivered under the terms of the first contract. Inasmuch as the written contract of April 16th was in the form of a quotation of defendant accepted by plaintiff, it does not purport to set forth that part of the agreement which adjusted the rights of the parties in regard to the steps which had previously been taken under the contract of March 5th. Therefore, evidence of these arrangements was admissible, provided they were not inconsistent with the terms of the written agreement of April 16th. (Guidery v. Green, 95 Cal. 630 , [ 30 Pac. 786 ], Sivers v. Sivers, 97 Cal. 518 , [ 32 Pac. 571 ]; Germain Fruit Co. v. J. K. Armsby Co., 153 Cal. 585 , 594, [ 96 Pac. 319 ].) In view of the total absence of any agreement making a special exception of the five starters delivered,- -and in view of the fact that the whole of the one thousand dollars paid under the contract of March 5th was to
[3] An itemized summary of the expenditures of defendant under the contract was admitted in evidence under the issue of damages. Plaintiff assigns this as error, for the reason that the person who kept defendant’s books did not testify to their correctness. The statement, or summary, was admitted under subdivision 5 of section 1855 of the Code of Civil Procedure, because the original consisted of “numerous accounts or other documents, which cannot be examined in court without great loss of time.” Defendant maintains a card system of bookkeeping and testified that he personally made up the statement in question by going over the cards and checking up the entries thereon with the original bills which he retained and which he knew had been paid. Therefore, the statement was, in fact, made from the original bills, of the payment of which defendant had personal knowledge, and defendant was competent to testify to the correctness of the items thereof upon his own knowledge, which he did. For this reason, testimony by the bookkeeper as to the correctness of the books of defendant was unnecessary and the statement was properly received in evidence.
It is contended that there is no evidence to support the finding that “immediately after making said agreement [referring to the agreement of March 5th] defendant ordered certain castings to be used in said starters.” This finding is immaterial and unnecessary to support the judgment for, even if there is no evidence of this particular fact, there is ample evidence, as previously stated, to support the general finding that defendant proceeded diligently with the work at all times after March 5th. Plaintiff complains of
It is true, as pointed out by defendant, that plaintiff might have been more impartial in setting forth extracts from the evidence in the supplement to his brief. However, we do not deem the omissions so flagrant as to call for an order requiring plaintiff to reimburse defendant for costs and attorney’s fees incurred in printing a supplement to defendant’s brief containing testimony in defendant’s favor.
The judgment is affirmed.
Sloane, J., and Wilbur, J., concurred.
Cases cited
- Guidery v. Green 95 Cal. 630 p. 260
- Sivers v. Sivers 97 Cal. 518 p. 260
- Germain Fruit Co. v. J. K. Armsby Co. 153 Cal. 585 at 594 p. 260