Majority
Headnote
[1] Mechanics’ Liens — Materialmen — Eight oe Lien — Waiver — Eight to Recover on Bond.—A materialman may waive, by agreement or otherwise, his right to a lien against the building for the construction of which he has furnished material, without in any way impairing his right to proceed against the sureties upon the undertaking given in compliance with section 1183 of the Code of Civil Procedure.This action was instituted for the purpose of foreclosing certain materialmen and mechanics’ liens. The only cause of action with which we are concerned on this appeal is that on behalf of Praters Glass and Paint Company, a corporation, the appellant herein. This company sought a judgment against the sureties on the bond given by the contractor to the owner in compliance with the provisions of section 1183 of the Code of Civil Procedure. E. B. Rivers, as the owner of the real property on which the building was constructed, entered into a contract with the Southwestern Construction Company, a corporation, for the construction of said building at an agreed price of $91,000. The contractor gave a bond as required by section 1183 of the Code of Civil Procedure, with the defendants Henry S. Patten and P. W. Patten as sureties, in the sum of $45,500, being fifty per cent of the contract price of said building. There is no claim but that this bond met all the requirements of said section 1183. Under the contract for the construction of said building the appellant, Praters Glass and Paint Company, furnished glass which was actually used in the construction 'of said building, the reasonable market value of which was the sum of $5,135.34, no part of which has been paid. Appellant’s complaint herein set forth the foregoing facts and asked for judgment against respondents, the said sureties, for the sum of $5,135.34. The respondents in their answer make no denial of the allegations of the complaint, but as a special defense alleged that as a part of the consideration for executing said undertaking and as an inducement to them to execute the same, the appellant prior to the signing of said bond by the sureties executed and delivered to the sureties the following writing: “April 26, 1921. Mr. Henry Patten, Patten & Davies Lumber Co., Los Angeles, California. Dear Sir: In
Respondents further allege in their answer that it was the intent and purpose of said plaintiff, the appellant herein, by the execution of said writing to relieve said respondents of the burden of said undertaking to the extent of $4,000, and that had it not been for the execution of said writing by the appellant, respondents would not have become sureties upon said undertaking. The trial court found the allegations of respondents’ special defense to be true, and rendered judgment accordingly.
On this appeal the appellant attacks these findings as unsupported by any evidence. Appellant contends that by this writing it did nothing more than waive its right to a lien against the building for which it furnished said material, and that this waiver did not extend to nor include its right to proceed against said sureties on said bond for the amount unpaid on its claim. In this connection appellant contends that as a materialman furnishing materials to be used and which were actually used in the construction of said building, it was given under the statute the right to a lien against said building and the land upon which it was constructed, together with a convenient space about the same, and also a right in case of the nonpayment of its claim to proceed against the sureties on said bond for the amount unpaid on its claim; that these two rights are separate, distinct, and independent of each other, and that by waiving its right to a lien against the real property it in no manner impaired its right of action against the sureties on the bond to recover the amount remaining unpaid upon its claim. In support of this contention, appellant relies upon the case of General Elec. Co. v. American Bonding Co., 180 Cal. 675 [ 182 Pac. 444 ]. That action was instituted by the plaintiff therein
“Section 1197 of the same chapter clearly contemplates suits which may be maintained without the previous filing of liens, for it provides that: ‘Nothing contained in this chapter shall be construed to impair or affect the right of any person to whom any debt may be due for work done or materials furnished to maintain a personal action to recover said debt against the person liable therefor; . . . but the judgment, if any, obtained by the plaintiff in such personal action shall not be construed to impair or merge any lien held by said plaintiff under this chapter; provided, only, that any money collected on said judgment shall be credited on the amount of such lien in any action brought to enforce the same, in accordance with the provisions of this chapter.’ The bond by its terms creates a direct obligation on the part of the surety to pay for materials used in the construction of the building and the right of action on such bond is preserved by said section 1197 as well as by section 1183.
“It can no doubt be persuasively argued that the bond which must ‘be also conditioned for the payment in full of the claims of all persons performing labor upon or furnishing materials to be used in the work’ relates to claims of lien filed within time. But it seems to us that this is a strained interpretation. The mere use of the word ‘claim,’ which is as apt a description of the demand of the individual who has filed no claim of lien as it is of one who has filed such claim, is not persuasive.
“It is to be noted also that the portion of the section (and of the bond which follows its terms), by which the rights of materialmen are safeguarded, does not use the word ‘claims’ but the bond is made to ‘inure to the benefit of any and all persons who . . . furnish materials to be used in the work described’ in the contract.
“But there is another and a very strong reason for rejecting the theory that section 1187 of the Code of Civil Procedure restricts the terms of section 1183 of the Code of Civil Procedure and makes thorn applicable only to those persons who have filed liens, and that reason is found in the history of the two sections and in the decisions of this court relating thereto. ’ ’ '
The court then proceeds to review the history of the legislation affecting these two code sections as well as the decisions of this court relating to such legislation, and concludes by reasserting its conclusion that: “The phrase ‘claiming the benefits of this chapter’ (found in said section 1187) was thus given a meaning which confined its operation to the benefits of asserting a lien upon the property and did not extend it to include the benefits of any other remedy afforded by the chapter against the owner.” This court accordingly held in that case that the waiver of the plaintiff therein of its lien by its failure to file its claim of lien as required by section 1187 of the Code of Civil Procedure did not deprive it of its right of action against the surety on the bond given under the provisions of section 1183 of the Code of Civil Procedure. There can be little, if any, difference between a waiver of lien by a failure to file the claim of lien as required by section 1187 and a waiver by express agreement in so far as such waiver may affect the claimant’s right to proceed against the sureties on the bond given under section 1183 of the Code of Civil Procedure. In either case the materialmen or laborers, as the case may be, simply forfeit their right to a lien against the property of the owner without in any way impairing their further and additional right given them under section 1183 to proceed against the sureties upon the bond. This conclusion is in perfect accord with the terms of said section 1183 and with the provisions of the bond in the present proceeding. In said section it is expressly provided that said bond “shall also by its terms be made to inure to the benefit of any
[2] Referring now to the writing signed by the appellant, and which it is claimed by respondents is a waiver of appellant’s right to recover in this action on said bond, we find that by its terms it is confined to an agreement to wait thirty-five days after the completion of the building for the payment of its claim and to a waiver of “our lien rights.” No reference is made therein as to any waiver of the rights of appellant under said bond. It must be apparent, therefore, of the two rights which the statute gives appellant that by this writing it waived only its right to a lien against the property, leaving its right of action upon the bond in full force and effect and capable of being enforced in a proper proceeding.
[3] It is further insisted, however, that even if it be conceded as true all that has been said herein, yet under the record before us the judgment must be affirmed. This record
[4] It is true, under section 1860 of the Code of Civil Procedure and section 1647 of the Civil Code, for the purpose of construing an instrument, the circumstances under which it is made may be shown, but these sections apply only in aid of construction in the real sense. They have no application where it is sought, as here, to add to the language an additional term which is not contained therein. This court in the case of Payne v. Commercial Nat. Bank, 177 Cal. 68 -72 [L. R. A. 19180, 328, 169 Pac. 1007 , 1008], has expressed the rule in apt and convincing language as follows:
“The principal claim of appellant bank is that the trial court erred in refusing to receive parol evidence of the transaction- between the plaintiff and the payee named in the check, culminating in the giving of the check, for the purpose of showing the intention of plaintiff to give a check for five hundred dollars to the payee. It seems to be the theory of learned counsel for defendant that under various sections of our Civil Code (1635, 1636, 1637, 1640, 1641," 1643, 1647, 1654), which simply lay down well-settled rules for the construction of the language used in the contract, the ambiguity may be removed and the cheek treated as one for five hundred dollars. This theory is without any support in the authorities. Rules provided for the construction of contracts are simply for the purpose of ascertaining the true intent and meaning of the language used therein. Under these rules parol evidence is admissible where it tends to show the correct interpretation of the language used, the purpose being to enable the court or jury to understand, in the light of the circumstances shown, what the words employed really mean, and to interpret those words, in so far as this can reasonably be done, in accord with the intention of the parties as the same may be shown by such circumstances. But no authority sustains the proposition that under the guise of construction or explanation a meaning can be given to the instrument which is not to be found in the instrument itself, but is based entirely
upon direct evidence of intention independent of the instrument. It has been well said that in the admission of extrinsic evidence the line which separates evidence which aids the interpretation of what is in the instrument from direct evidence of intention independent of the instrument must be kept steadily in view, the duty of the court being to declare the meaning of what is written in the instrument, and not what was intended to be written.”
From the foregoing we conclude that the writing executed by appellant and given to the respondents was no more than a waiver by appellant of its right to file a lien; that it was not a waiver of its right of action upon the bond given by. the contractor to the owner, on which respondents were sureties; that appellant’s right to proceed against said sureties was not waived nor in any manner affected by its waiver of a lien; that said writing, in so far as it expresses the intention of the appellant in executing and delivering it to respondents, is clear and unambiguous, and any testimony offered or admitted for the purpose of showing that appellant’s intention was different from that expressed in the writing would be inadmissible and incompetent as an attempt to vary the plain and explicit terms of a writing by parol evidence. It follows, therefore, that the finding of the court that appellant intended by said writing to relieve respondents from any of the burdens of said undertaking is unsupported by the evidence. For this reason the judgment must be reversed, and it is so ordered.
Waste, C. J., Richards, J., Shenk, J., Seawell, J., Preston, J., and Langdon, J., concurred.
Rehearing denied.
Cases cited
- General Electric Co. v. American Bonding Co. of Baltimore 180 Cal. 675 p. 690
- Payne v. Commercial National Bank 177 Cal. 68 p. 695