Majority
Appellant and respondent, acting by and through the department of engineering, entered into a contract whereby the former undertook to construct the embankment for a section of the state highway under construction between Coalinga and Fresno, beginning on said highway at engineer’s station No. 439 and concluding at station No. 1071, a distance of approximately twelve miles. The plan of construction called for a twenty-four foot roadway, consisting of a fifteen-foot center strip of concrete and dirt shoulders four and one-half feet wide on each side of the pavement. The earthen shoulder or embankment was required to slope outward from the concrete pavement, a distance of four and one-half feet, at the ratio of one and one-half feet horizontal to one foot perpendicular, which grade is known to engineers as a one and one-half to one slope. The earthen shoulders were constructed wider than called for in the contract and instead of having a drop of nine and one-half inches at the outer edge, as per contract, they were built at a grade almost level with the pavement, which added a much greater yardage of earth to the embankment than the appellant was required by his contract to supply. Appellant was not allowed any compensation for furnishing and placing this excess material, which, it is claimed, approximated 12,110 cubic yards of earth. The claim was disallowed on the theory that said resident engineer did not authorize the appellant to depart from the plans and specifications in the particular referred to and if
The appellant was to be paid $1.10 per cubic yard for all excavation made by him in the construction of said embankment. This is to say, the holes from which the material was excavated, known as borrow-pits, were to be measured, and the contractor paid for the number of yards, as shown by the capacity of the excavations or borrow-pits. At about the time said embankment was completed, and before any measurements were taken, the easterly half of said highway was submerged by flood waters which carried into said borrow-pits or excavations silt and earth in such quantities that their original areas could not be satisfactorily measured. The entire westerly half did not suffer such damage.
The finding of the trial court on this branch of the case is “that owing to the flood conditions it became impossible to measure the excavations according to the method provided in said contract and the defendant adopted said method of adding 21.1 per cent more material to the quantity found in the embankment; that plaintiff excavated more material than the measurements of the partially filled excavation would indicate, for which the said defendant has paid by the allowance of 21.1 per cent material more than actual measurement of the embankments; that the character of soil from stations 600 to 1071 was similar; that while the general contour, as shown by the maps and profiles, appears to be similar, as a matter of fact the cuts and fills are dissimilar and not comparable; that the embankments between the same
“The Court finds that plaintiff is not entitled to payment for any greater quantity of material than by adding 21.1 per cent of material to the quantity of material actually reposing in said embankment, for which said plaintiff has been paid in full.”
No objection is made to the actual measurements of excavations from station 600 easterly to station 815. The borrow-pits between these points were not affected to any material extent by flood waters. Complaint is made, however, that the actual measurements of said partially filled borrow-pits between stations 815 and 928 were treated as though they had not been affected by flood waters and were included as a factor in calculating the percentage of shrinkage in computing the whole distance from stations 600 to 928, upon which a general average was struck. In other words, appellant claims that upon the court’s finding that the borrow-pits between stations 815 and 928 had been partially filled it should have treated said pits as partially filled
It appears that the unaffected area from station 600 to Station 815 showed a shrinkage factor of 52.9 per cent. From station 815 to station 928 there appeared to be nineteen per cent less excavation than embankment. This variance can be accounted for only on the theory that the borrow-pits in the area were in a partially filled state, rather than in their original state.
The important question in the case is to ascertain as nearly as possible the normal shrinkage factor. In justice to the learned trial court, this was a matter attended with difficulties. It would seem reasonably certain, however, that the whole distance between stations 815 and 928 should not have been included as undisturbed area in an effort to ascertain the original contents of the borrow-pits. It would appear that the borrow-pits within the limits of station 600 to station 815 would furnish a fairer basis for estimate as to capacity than would the inclusion of station 928. It should not be extremely difficult for engineers and others familiar with local conditions to determine upon the ground approximately the point at which the disturbance of said pits or excavations began. The 21.1 shrinkage factor adopted by the learned trial judge would appear also to be 3.15 per cent smaller than the average estimate of the four engineers who testified on the subject, one of whom was called by plaintiff and the other three by defendant. The average
The other point pressed by appellant has to do with approximately 12,000 cubic yards of earth placed in embankment form in excess of the quantity required to be furnished by the provisions of the contract, for which appellant received no compensation. This extra material was rejected by the commission as “unauthorized.” This issue involves a question of fact as to whether the resident engineer, who is alleged to have ordered the extra material furnished, did in fact do so, and, further, if he did order said work done, was he expressly authorized to so act? The solution of this question is dependent upon evidence, the weight of which cannot be passed upon by an appellate court. Other questions of fact presented in the ease are wholly questions for decision by the trial court in the exercise of a sound discretion.
Upon a full consideration of the ease we are of the view that appellant is entitled to a greater amount for his services than was produced by the application of the 21.1 per cent shrinkage factor and that a more satisfactory basis of compensation will be established upon a retrial of the cause.
Judgment reversed.
Curtis, J., and Preston, J., concurred.
. Hearing in Bank denied.