This action was instituted by the plaintiff against the City of Gilroy upon a claim assigned to him by Charles E. Sloan to recover for services as an engineer, alleged to have been performed by Sloan for said city in connection with certain street improvements which the City of Gilroy planned to construct in said city. There is no
It is first contended by the City of Gilroy that the contract whereby it employed Sloan to act as engineer in connection with said street improvement work was invalid and without any legal binding effect for the reason that said city at the date it entered into said contract of employment had a legally appointed and acting city engineer. It is admitted that Sloan’s employment was made under the provisions of .section 41 of the Improvement Act of 1911, under which the said city was acting in making said street improvements. This section provides in part as follows: “In all those cities where there is no city engineer, the city council thereof is hereby authorized and empowered to appoint a suitable person to discharge the duties herein laid down as those of city engineer, and all the provisions hereof applicable to the city engineer shall apply to such person so appointed. Said city council is hereby empowered to fix his compensation for such services.” (Stats. 1911, p. 751.)
The defense that the contract was illegal for the reason that the City of Gilroy had a city engineer at the time it entered into said contract with Sloan was not made in the pleadings, nor did the court make any finding regarding that issue. It does not appear that at the trial of this action this defense was particularly stressed nor was it openly relied upon by the City of Gilroy. This may have been the reason why the court failed to find whether said city had a legally appointed and qualified city engineer at the time it entered into its contract with Sloan. There is some evidence, which was probably incompetent, and which no doubt would have been denied admission had objection been made to its introduction, that on January 9, 1924, when the city council of the City of Gilroy first took official action regarding Sloan’s appointment, the City of Gilroy had an acting city engineer by the name of H. B. Fisher, who some time in the year 1912 had been appointed city engineer of said city, or at least had been employed by said city to perform certain engineering work for said city. We will assume, however, simply for the purpose of this discussion, but not
From the foregoing statement of facts, it is quite evident if the city council was without authority on January 9, 1924, to appoint Sloan to act as city engineer in the construction of said work and improvement by reason of the fact that said city had at that date a duly appointed and qualified city engineer, that on February 11, 1924, after it had declared the office of city engineer vacant, such lack of power to so employ Sloan no longer existed. The record shows that after the city, on February 11, 1924, had declared the office of city engineer vacant, it then proceeded to appoint Sloan to such position. After this appointment of Sloan, he was directed to prepare the plans and specifications for the contemplated street work and his compensation was fixed, and it was under this employment that he performed the services for which his assignee was awarded judgment. It, therefore, appears to us to be entirely immaterial, as far as the legality of Sloan’s employment is involved, whether the City of Gilroy had a city engineer on January 9, 1924, or at any other time prior to February 11, 1924, when Sloan was employed. It is true the trial court found that Sloan was appointed city engineer on January 9, 1924, and based its judgment in plaintiff’s favor on that finding. But in view of the undisputed evidence before us, we do not think the„ actual date of Sloan’s appointment is controlling if the evidence shows, as it does without any contradiction, that, if he was not legally employed on the prior date, he was on the subsequent date, after which he rendered the services here involved.
It is next contended by appellant that the percentage contract between Sloan and the City of Gilroy was illegal for the reason that Sloan was on March 17, 1924, when the resolution was passed by the City of Gilroy fixing Sloan’s compensation at eight per cent of the total cost of said improvement, an officer of said city, to wit, its city engineer, and was, therefore, prohibited by law from being interested in any contract made with the city. Appellant relies upon Kennedy v. City of Gustine, 199 Cal. 251 [ 248 Pac. 910 ], in support of this contention. That case is very similar to
■ Another answer to the contention of appellant that Sloan was the city engineer of the City of Gilroy is to be found, we think, in the phraseology of said section 41 of the Improvement Act of 1911. While under the charter of the City of Gilroy, the common council had authority to appoint a city surveyor (which term we think is synonymous with city engineer) it has been appellant’s contention all through this case that Sloan was appointed under said section 41 of the Improvement Act of 1911. This section of the act gives the council no authority to appoint a city engineer, but simply authorized the council in cities where there is no city engineer, “to appoint a suitable person to discharge the duties herein laid down as those of city engineer”. We think that Sloan’s appointment was clearly for that limited purpose and not to discharge generally the duties of city engineer. The provision of law relied upon by the appellant, therefore, that an officer of a city is prohibited from being interested in any contract with the city would not apply to Sloan in so far as it concerns his contract with said city.
Another defense interposed by the City of Gilroy was “that the indebtedness sued upon is greater than the income and revenue of the City of Gilroy for the year in which the same was incurred and also in which it became due and payable, if at all”. It is conceded that the “indebtedness sued on” was incurred, if at all, on September 11, 1924, the date on which the city council of the City of Gilroy abandoned the proceedings initiated by said council for the construction of said work and improvement. This would bring said indebtedness within the fiscal year 1924-1925. On the trial it was shown that the balance in the city treasury at the beginning of this fiscal year was $7,551.15 and that the taxes for said year became due and delinquent
Finally appellant contends that there can be no recovery by the plaintiff for the reasonable value of the services performed by Sloan. As already stated, the court found the reasonable value of said services to be a certain sum and gave judgment for this amount. Appellant bases its objection to the judgment so rendered on its contention that the contract was void or at least illegal, and, therefore, an action for the reasonable value of the services performed thereunder would not lie in favor of Sloan or his assignee. AVe have held, however, that the contract was legal, which is a sufficient answer to appellant’s present contention. AVe might further add that an action based on the reasonable value of said services was the only proper action which would lie in favor of Sloan, notwithstanding his contract for the payment of his services on a percentage basis. As we have seen, the contract was not fully performed by Sloan for the reason that the city council abandoned the proceedings for the construction of said work and improvement before any part thereof was constructed, and Sloan’s contract provided for the supervision by him of the construction of said work as the same was to be performed by the contractor to whom the contract might be let. This the city council had the legal right to do. But in such case, according to section 17 of the act, “the incidental expenses incurred previous to such abandonment shall be paid out of the city treasury”. By section 79, subdivision third, of said act, “incidental expenses”, as used in said act, “shall include the compensation of the city engineer for work done by him”. It is quite evident from these sections of the act, that the claim of Sloan, after the abandonment of the work by the city council, was limited to the reasonable value of his services done under the contract, or in the language of the statute, “for work done by him”. The same question was before the court in the case of Kennedy v. City of Custine, supra, and in its decision this court said: “A city is not primarily liable for the cost of street improvements made pursuant to the terms of the Act of 1911, but the same becomes a lien on the property to be benefited if the
We have covered all the points raised by the appellant against the judgment in this action. In our opinion none of them is of sufficient merit to justify a reversal of the judgment.
Respondent has a motion before us for leave to introduce further evidence in this case. It is denied, and the judgment is affirmed.
Preston, J., Langdon, J., Shenk, J., Thompson, J., Waste, 0. J., and Seawell, J., concurred.
Rehearing denied.