Majority
Headnote
Liens of Mechanics and Matsbial Men.—There is no constitutional objection to a statute securing a lien to material men, who, at the instance of a contractor, furnish him with materials which are used in the construction of the building, provided the aggregate liens do not exceed the contract price, as fixed by the owner and contractor.We can see no constitutional or other objection to a statute securing a lien to a material man for the value of the materials which have gone into a building; provided, the aggregate liens do not exceed the contract price as fixed by the owner and original contractor.
And in such cases the contractor and owner cannot de
In case of judgment on behalf of the material man against the owner and his property, the latter is entitled to deduct from any sum due the contractor, the amount of such judgment. (Stats. 1867-8, p. 592.)
On the present appeal it does not appear that the asserted liens amount to the contract price, or that such price was paid when this action was commenced, or the liens were filed.
Judgment reversed and new trial ordered.
Mr. Justice Rhodes did not express an opinion.
Cases cited
- Shaver v. Murdock 36 Cal. 293 p. 177
- Blythe v. Poultney 31 Cal. 233 p. 177