Contbact—Pleadings—Evidence—Findings — Yabiance—Law of the Case.— The action was brought on an alleged contract in writing by which the plaintiff and his associates agreed to do certain work for the defendant in the construction of a railroad, and to furnish the materials therefor. The complaint purported to state the contract according to its substance and effect, but the answer denied the contract thus stated, and averred that the contract between the parties was embodied in two instruments therein set forth, one being supplemental to and explanatory of the other. The facts on the subject were proved and found in accordance with the answer. By the terms of the contract payments were to be made from time to time as the work progressed, but these payments were to bo based on estimates made by the engineer of the road and reported to the parties. There was no allegation in the complaint, nor any proof in relation to such estimates. After stating, however, that the work had not been completed, the complaint alleged that the completion was prevented by the defendant. In support of this allegation, evidence was given on the part of the plaintiff to the effect that the payments were not made as provided for by the contract, that the failure in the payments rendered it impossible for the plaintiff and his associates to complete the work for want of means necessary to enable them to do so, and that their pecuniary condition and reliance upon the payments were known to the defendant when the contract was made. The facts were found in accordance with this evidence, and it was also found that the work had not been voluntarily abandoned by the contractors, but was wholly and entirely suspended by the defendant. The contract provided in substance that the defendant should have the right, subject to certain conditions as to notice, to cause an increase or diminution of the force of laborers or other means necessary to carry on the work, or to suspend the work entirely, provision being made for delays arising from the exercise of this right, and in regard to the terms of payment in case the work should be entirely suspended. It was proved that the defendant had at different times required the force of laborers employed upon the work to be reduced, and had directed portions of the work to be suspended. On former appeals in the case, the court had decided that the action could not be maintained unless the completion of the work was prevented by the defendant, and that neither a failure in the payments nor the exercise of a right secured to theFor many reasons the judgment of the court below is erroneous. The action is one at law, on a special contract, the plaintiff alleging part performance of the contract on his part, and that of his predecessors in interest, and the preventing of the completion of it by the defendant. The case has been here repeatedly, the complaint on which the last trial was had being the seventh complaint filed in the action. Naturally enough, therefore, certain propositions have become the law of'
For the purpose of overcoming the first of these last-mentioned obstacles, the plaintiff was permitted on the last trial in the court below, against the defendant’s objections, to introduce testimony to the effect that both parties knew at the time of making the contract that the contractors relied, and were compelled by their pecuniary resources to rely, upon the payment by the defendant of the instalments as they became due; and the court below so found. In rightly holding such testimony erroneously admitted, Me. Justice Myeick, speaking for the court, when the case was last under consideration, said: “ Parol evidence of surrounding circumstances may be given to aid in the proper interpretation of an instrument; but where the parties have themselves used words which require no interpretation, where the words are understood, there is no occasion for aid to their proper interpretation or meaning. In this case the parties had, by their contract, clearly expressed two ideas or agreements: First, that the contractors were to perform certain work; second, that the defendant Avas to make payments therefor in instalments. The words as to these agreements are of very plain signification. This court had decided non-payment of instalments was not prevention; therefore, by the terms of the contract payment Avas not a condition precedent. In order to make payment a condition precedent a clause would have to be inserted, injected into the contract, Avhich the parties themselves did not see fit to place there. It is not in evidence that the parties agreed by paroi that the payments should be conditions precedent; but even if they had so agreed, the well-lmoAvn rule Avould apply, that their final conclusions Avere as they have expressed them in writing.” (10 Pac. C. L. J. 263.)
Of course this testimony Avas introduced, and the finding
Moreover, there is in this case neither averment nor proof that the estimates of the engineer, on which alone, according to the terms of the contract between the parties as proved and found, the defendant was to pay, were made, nor is there any legal cause shown, or attempted to be shown, why such esti
But further and beyond all this, the contract declared on by the plaintiff is essentially different from the contract set up by the defendant and proved and found by the court to have been made between the parties; and the respective rights and obligations of the parties under the one are essentially different from what they are under the other.
By the contract stated in the complaint, the obligation of Cox, Meyers & Co. was limited “to the extent of doing, and furnishing materials for, all the gradation, masonry, and bridging, and all other things necessary and proper to place said roadbed (of the railroad referred to) ready for the cross-ties and iron equipment, and no more.” By the contract proved and found their obligation went far beyond this. By that, the work to be done by them was to include all bridges, viaducts, embankments, excavations, road-crossings, culverts, drains, and all other things necessary, usual, and proper to place the part of the railroad described complete for the cross-ties and iron equipment to be placed thereon, and according to certain plans and specifications annexed to the contract and made part of it. The work to be done by them was to be done in the best and most thorough manner, and all that portion of the railroad undertaken to be built by them was to be equal to the best constructed railroad in the State, and was to be in full compliance with the contract then existing between McLaughlin and The Western Pacific Railroad Company, and in full compliance with the requirements of the board of directors of that company. It is manifest that performance of the obligations imposed on Cox, Meyers & Co. by the contract alleged in the complaint would by no means be a compliance with the obligations imposed on them by the contract proved and found.
Furthermore, the defendants obligations, as well as his rights,
Judgment and order reversed and cause remanded for a new trial.
Morrison, C. J., Myrick, J., McKinstry, J., and Thornton, J., concurred.
Petition for a rehearing denied.
Cases cited
- Cox v. Western Pacific Railroad 44 Cal. 18 p. 197, p. 205
- Cox v. Western Pacific Railroad 47 Cal. 87 p. 197, p. 205
- Cox v. McLaughlin 52 Cal. 590 p. 197, p. 199, p. 205
- Cox v. McLaughlin 54 Cal. 605 p. 197, p. 199, p. 205, p. 206
- Mitchell v. Davis 20 Cal. 45 p. 198
- Davidson v. Dallas 15 Cal. 75 p. 198
- Donner v. Palmer 51 Cal. 629 p. 198
- Wittenbrock v. Bellmer 62 Cal. 558 p. 198
- Young America Engine Co. No. 6 v. City of Sacramento 47 Cal. 594 p. 201
- Smith v. Greer 31 Cal. 476 p. 201
- Lennard v. Vischer 2 Cal. 37 p. 201
- Adler v. Friedman 16 Cal. 138 p. 201
- Thomas v. Armstrong 7 Cal. 286 p. 201
- Cunningham v. Hopkins 8 Cal. 33 p. 201
- Holmes v. Richet 56 Cal. 307 p. 202, p. 207
- McMahon v. New York & Erie Railroad 20 N. Y. 463 p. 202
- Washington, Alexandria, & Georgetown Steam Packet Co. v. Sickles 10 How. 419 p. 202
- Rogers v. Cody 8 Cal. 324 p. 202
- Smith v. Mayor & Common Council of Sacramento City 13 Cal. 531 p. 202
- Phelan v. City & County of San Franciso 20 Cal. 39 p. 203
- Loup v. California Southern Railroad 63 Cal. 97 p. 207