Majority
Headnote
Street Work — Grading Montgomery Avenue — Completion op Work —Extension op Time — Expiration of Contract. — The- action was brought to foreclose a street assessment lien for grading Montgomery Avenue, in the city and county of San Francisco. The contract under which the work was done required its completion within sixty days. The work was not completed within the time, and subsequently the board of supervisors of the city and county extended the time for its completion. Held, that upon the failure to complete the work within the time required the contract expired, and the board of supervisors had no jurisdiction to revive or validate it.— Action to foreclose a street assessment lien for street work alleged to have been done under a contract for grading Montgomery Avenue in the city and county of San Francisco.
The contract required that the work should be completed within sixty days. The work was not completed within the time; and under the law the contract expired. Subsequently, however, the board of supervisors of said city and county extended the time; but it had no jurisdiction to revive and validate a dead contract. The order of extension was, therefore, unauthorized and void. (Beveridge v. Livingstone, 54 Cal. 54 ; Owens v. Heydenfeldt, 6 W. O. R. 149; Torrens v. Townsend, 6 W. C. R. 149.)
But so far as the statute attempts to vitalize a dead contract and validate a void assessment for street work, it is unconstitutional and void. (People v. Lynch, 51 Cal. 15 ; People v. McCune, 57 Cal. 153 ; Brady v. King, 53 Cal. 44 .)
Judgment affirmed.
Boss, J., and McKinstey, J., concurred.
Cases cited
- Brady v. King 53 Cal. 44 p. 429, p. 430
- People v. Goldtree 44 Cal. 323 p. 429
- People v. Lynch 51 Cal. 15 p. 429, p. 430
- Reis v. Graff 51 Cal. 86 p. 429
- People v. O'Neil 51 Cal. 91 p. 429
- People v. McCain 51 Cal. 360 p. 429
- Mahoney v. Braverman 54 Cal. 565 p. 429
- Beveridge v. Livingstone 54 Cal. 54 p. 429