Majority
This action is brought by plaintiff corporation as assignee of San Luis Obispo County. By such action the assignee seeks to have an allegedly assigned faithful performance bond reformed and to recover on it as reformed. The trial court sustained an amended demurrer to the complaint, without leave to amend, and ordered judgment of dismissal. Plaintiff appeals. We have concluded that defendant is correct in its contention that the bond could not properly be assigned to plaintiff, that no right of plaintiff to recover on the bond appears, and that the dismissal should be upheld.
Besides alleging assignment of the bond to plaintiff the complaint avers that in June, 1953, defendant Westfall, acting as owner and subdivider of the tract, “caused the Board of Supervisors of San Luis Obispo County to accept a final subdivision map” of the tract in consideration of Westfall’s promise that he would, as provided in county subdivision ordinance No. 184,[1] within a reasonable time improve all of the streets and roads in the tract as shown on the subdivision map, and that he would post with the county a sufficient bond to insure his faithful performance of the work.
About 10 days later Westfall, pursuant to his agreement with the county, delivered the bond in question, a copy of which is attached as an exhibit to the complaint. It is in the amount of $28,000 and recites that “Whereas, the Principal [Westfall] has entered into a certain written contract with the Obligee, dated the 29th day of June, 1953 to Complete Roads, Los Osos Highlands, No. 2, Subdivision . . . which contract is hereby referred to and made a part hereof as fully ... as if copied at length herein.
“Now, Therefore, the condition of this obligation is such that, if the Principal shall faithfully perform the contract on his part, and shall fully indemnify and save harmless the Obligee from all cost and damage which the Obligee may suffer by reason of failure so to do and shall fully reimburse and repay the Obligee all outlay and expense which the Obligee may incur in making good any such default, and shall pay all persons who have contracts directly with the Principal for labor or materials, then this obligation shall be null and void, otherwise it shall remain in full force and effect.” (Italics added.)
1 Ordinance No. 184 is pleaded by title and date of passage, as permitted by section 459 of the Code of Civil Procedure.
It is further pleaded that Westfall commenced improving the roads but abandoned all work about the middle of December, 1953; the county road commissioner has estimated that it will cost $22,030 to complete the road work; the obligee county, in March, 1956, made written demand on defendant surety to perform the obligation of the bond, but the surety refused; plaintiff presently owns more than 50 per cent of the land in the tract; in October, 1957, the obligee county assigned its rights in the bond to plaintiff. The purported assignment is in writing and states that “In consideration of the execution, concurrently herewith, of Forbearance to Sue” by plaintiff, the county assigns to plaintiff “all of its right, title and interest, legal or equitable, as obligee, to enforce the provisions ’ ’ of the bond. No document purporting. to constitute a covenant not to sue anyone for anything appears in the record, nor are any terms or conditions of any such agreement alleged.
The complaint, filed October 21, 1957, seeks judgment against both the principal and the surety in the sum of $22,030. It does not appear from the complaint whether West-fall still owns land in the tract or has sold or conveyed to others the portions thereof not owned by plaintiff. Neither does plaintiff allege the means by which it became owner of the “more than fifty per cent” of the land which it claims. It does not appear that plaintiff is the only person (if any) who may or might have a claim against the county because of the principal’s default.
Defendant contends, among other things, that the complaint fails to state a cause of action in that the alleged assignment of the county’s rights in the bond is illegal and ultra vires. This contention is meritorious.
The rule is that rights and liabilities under a surety bond are to be determined from the language of the bond read in the light of applicable statutes. (See County of Placer v. Aetna Cas. etc. Co. (1958), 50 Cal.2d 182 , 186 [1] [ 323 P.2d 753 ] ; Fernelius v. Pierce (1943), 22 Cal.2d 226 , 245 [7] [ 138 P.2d 12 ] ; Milliron v. Dittman (1919), 180 Cal. 443 , 445 [1]
As declared in County of Los Angeles v. Margulis (1935), 6 Cal.App.2d 57 , 59-60 [2] [ 44 P.2d 608 ], where the county sued to recover on a similar bond provided by a sub-divider to secure faithful performance of his agreement to improve certain streets and build a storm drain, “Under the contract the county was entitled to have these highways so improved, and this right was of a value equal to the cost of the work. The contract having been breached by a failure to perform, the county was entitled to a sum equal to the cost of the uncompleted portion of the work . . . Under the contract the county was entitled to receive work of a certain value. This work not having been received, the county was entitled to receive in lieu thereof as damages a sum of money equal in value to the uncompleted work which the contract called for, and appellant as surety was liable under its bond up to the penal sum therein specified.”
Here as in the Margulis ease, the county presumptively is entitled to receive the road work which Westfall agreed to complete. And here the right to recover under the bond appears clearly to be a right of the county rather than of the owner of a portion of the property which might be affected by the default. (See Evola v. Wendt Construction Co. (1959), 170 Cal.App.2d 21 , 25-26 [ 338 P.2d 498 ].) It is the county which is indemnified by the express terms of the bond against loss from “all cost and damage which
We recognize that in Christie v. Commercial Casualty Ins. Co. (1935), 6 Cal.App.2d 710 , 714 [1] [ 45 P.2d 263 ], it was held that a laborer (the foreman of the construction work) could recover unpaid wages on a public works performance bond. But there the bond was conditioned “to secure the payment of all work and labor ‘of any kind’ performed in the course of the construction of the roadway” and the court held that “The language of the bond leaves no doubt it was furnished for the direct benefit and protection of those who" perform work or supply materials for the roadway in accordance with the contract, although they may not be parties to that instrument.” The bond in issue here is conditioned for the benefit of the obligee county and by no possible view of its language can it be held to have been “furnished for the direct benefit and protection” of the principal (the sub-divider) or other-landowners in the tract. Furthermore, the Christie case does not hold, nor does any authority which has been cited or discovered suggest, that the public body .may assign its rights under such a bond to another, as plaintiff alleges has been done .in the present case. And insofar as concerns any suggestion that the county’s assignee might prosecute the action for the partial or ultimate benefit of the county, section 25203 of the Government Code specifies that the board of supervisors “shall direct and control the prosecution and defense of all suits to which the county is a party . . .” (See also County of Contra Costa v. Soto (1902), 138 Cal. 57 , 60, 62 [ 70 P. 1019 ].)
Plaintiff claims, however, that in any event it, as the present owner of the land in the subdivided tract, is a third-party beneficiary under the bond; i.e., one for whose benefit the
For the reasons stated it follows that the complaint does not, and that plaintiff would be unable to amend to, state a cause of action on the allegedly assigned bond. The trial court was correct in sustaining the amended demurrer without leave to amend and in ordering dismissal of the action.
The judgment is affirmed.
Gibson, C. J., Shenk, J., Traynor, J., Spence, J., McComb, J., and Peters, J., concurred.
2 Of course neither plaintiff nor any other lot purchaser comes within the provisions of section 1559 of the Civil Code: “A contract, made expressly for the benefit of a third person may be enforced by him at any time before the parties thereto rescind it.” (Italics added.)
Cases cited
- County of Placer v. Aetna Casualty & Surety Co. 50 Cal.2d 182 at 186 p. 400
- Fernelius v. Pierce 22 Cal.2d 226 at 245 p. 400
- Milliron v. Dittman 180 Cal. 443 at 445 p. 400
- Hub Hardware Co. v. Aetna Accident & Liab. Co. 178 Cal. 264 at 267 p. 401
- County of Los Angeles v. Margulis 6 Cal.App.2d 57 at 59-60 p. 401
- Evola v. Wendt Construction Co. 170 Cal.App.2d 21 at 25-26 p. 401
- Christie v. Commercial Casualty Insurance 6 Cal.App.2d 710 at 714 p. 402
- County of Contra Costa v. Soto 138 Cal. 57 at 60, 62 p. 402
- County of San Diego v. California Water & Telephone Co. 30 Cal.2d 817 at 823 p. 403