Majority
found that the defendants own three lots in the plaintiff city; that pursuant to ordinances of the city the defendants were duly notified “to repair and reconstruct” the sidewalk in front of said lots; that they failed and neglected to comply with the notice; that thereafter such proceedings were taken that the superintendent of streets let a contract “for the construction of said sidewalk . . . for the sum of $217.95”; that the contractor constructed the sidewalk in accordance with the contract; and that the plaintiff paid him the agreed price therefor. This action is for the recovery of a personal judgment against the defendants for the amount so paid to the contractor. Judgment was entered in favor of the defendants and the plaintiff has appealed therefrom.
The judgment is affirmed.
Plummer, J., and Thompson (B. L.), J., concurred.
A petition for a rehearing of this cause was denied by the District Court of Appeal on April 10, 1930, and a petition by appellant to have the cause heard in the Supreme Court, after judgment in the District Court of Appeal, was denied by the Supreme Court on May 8, 1930.
Cases cited
- Barber v. Galloway 195 Cal. 1 at 10 p. 457
- City Street Improvement Co. v. Pearson 181 Cal. 640 at 649 p. 457
- Atchison, Topeka & Santa Fe Ry. v. Reclamation Dist. No. 404 173 Cal. 91 at 93 p. 457
- Federal Construction Co. v. Ensign 59 Cal. App. 200 at 209 p. 457
- Flinn v. Zerbe 40 Cal. App. 294 at 295 p. 457