Majority
Headnote
Contract to Remove Sand, Deposit Clay and Grade Lot—Breach— Liquidated Damages—Burden of Proof—Actual Damages.—In an action for breach of a contract by defendants to remove all surplus sand from plaintiff’s block and pay an agreed price for the sand per cubic yard, and to deposit two inches of clay on the land and one-half the street fronting thereon and grade the lot to the official grade, free of expense to plaintiff, with a provision therein for liquidated damages in case of breach, the burden of proof is upon the defendants, to sustain such provision by showing that “it would be impracticable or extremely difficult to fix the damage,” and in default of such showing, the court properly disregarded the stipulation as void and rendered judgment, upon due proof, for the actual damages sustained by plaintiff for breach of the contract in excess of such stipulation.This is an action for damages for breach of contract. Plaintiff owned a piece of land in San Francisco known as Block 39, bounded by Van Ness avenue, Polk street, North Point and Bay street, and on February 21, 1901, entered into a contract with defendants, by the terms of which the defendants were to remove 7000 cubic yards of surplus sand from said block and to pay therefor six and one-quarter cents per cubic yard; they were also to level and grade said block and streets to the official grade, and to cover the entire surface of said block and one-half the streets fronting thereon with clay to the depth of two inches; all of which
It appears from the findings (which are supported by the evidence) that the defendants removed from the said block 11,388 cubic yards of sand, being 4,388 cubic yards in excess of the quantity specified in the contract; that they did not grade or level to the official grade the said block and streets, nor cover said block and one-half of said streets with clay to the depth of two inches or at all. The court further found that plaintiff, in order to bring her said land to the official grade and level, will be obliged to place thereon 4,388 cubic yards of earth, which will cost her the sum of $1090.17; that the defendants have paid the plaintiff only $144.52 on account of the amount due to her for the sand removed from her said block, leaving a balance due thereon of $567.23.
In accordance with these findings a judgment was entered for the plaintiff for the sum of $1657.47. The appeal is from that judgment and from an order denying defendants’ motion for a new trial.
The contract contained the following provision: “For any violation of or default in the stipulation or covenants of either of the parties to this agreement, the defaulting party shall pay to the aggrieved party the sum of $1,000 as liquidated damages.” The court below held this clause of the contract void under section 1670, Civil Code, and awarded the plaintiff the actual damages.
That section reads: “Every contract by which the amount of damages to be paid, or other compensation to be made, for a breach of an obligation, is determined in anticipation thereof, is to that extent void, except as expressly provided in the next section.” The next section (section 1671) is as follows: “The parties to a contract may agree therein upon an amount which shall be presumed to be the amount of damage sustained by a breach thereof, when, from the nature of the case, it would be impracticable or extremely difficult to fix the actual damage.”
Defendants assert that there is no evidence whatever upon the question whether it was practicable or not' to fix the actual damages suffered by the plaintiff, and that therefore the finding of the court that this provision of the contract is void cannot be sustained.
This point was considered in Patent Brick Co. v. Moore, 75 Cal. 205 , 209, [ 16 Pac. 890 ], where there was a stipulation in a building contract to pay the owner a specified amount as liquidated damages for each day’s delay in completing the building. The court held that this provision in the contract was not of itself, in the absence of all other evidence on the subject, sufficient to sustain the clause. The court further said that while there might be contracts which from their very nature would warrant parties in anticipating and fixing damages to be recovered on a breach, yet, said the court, “it -must always, it seems to us, be demonstrated by satisfactory evidence that the case is one where such liquidated damages may, under the statute, be contracted for and recovered.”
In Long Beach etc. Dist. v. Dodge, 135 Cal. 401 , 405, [ 67 Pac. 499 , 501], it is said: “It is clearly incumbent upon the party seeking to recover upon such agreement (liquidated damage clause) to show by averment and proof that his case is within the exception.”
In Montana the law on this subject is in the same language as ours, and there, in Deuninck v. West G. I. Co., 28 Mont. 255 , [ 72 Pac. 618 ], the court said: “If a suit be brought on a contract for the actual, and not the liquidated, damages, it is for the defendant to show the court by proper answer and competent proof that the contract for stated damages is valid. "
But we think the findings complained of are supported by the evidence. An expert civil engineer, called on behalf of plaintiff, testified that it would take 4,388 cubic yards of earth to bring the block to the official grade established at the time the contract was made. Two other witnesses were called by the plaintiff, who for forty-one and twenty-five years respectively had been engaged as contractors in grading and leveling blocks and streets, and they testified that it would cost a certain fixed sum per cubic yard to fill and grade the block, and another certain sum per cubic yard to
This ease in one respect is like Pacific Factor Co. v. Adler, 90 Cal. 110 , 120, [ 25 Am. St. Rep. 102 , 27 Pac. 36 , 38], for “when the plaintiff rested, the ‘nature of the case,’ . . . was such that the court could decide as a fact that it was neither extremely difficult nor impracticable to fix the actual damage sustained by the plaintiff by reason of defendant’s breach of the contract.”
Defendants suggest that “even if the provision as to liquidated damages be void as to the fixing of the amount of damages, it may still be of effect as setting the limit of damages.” To sustain this position People v. Central Pacific Ry. Co., 76 Cal. 38 , 39, [ 18 Pac. 90 , 95],is cited, where the court said: ‘ ‘ The statement of a penalty in a contract is of very little importance, its only consequence being to limit a recovery of actual damages, so .that no more perhaps can be recovered than the sum named in the penalty.” But in that case the question was not before the court whether the amount stated in the contract was the limit of the recovery, and what the court said in that regard was purely by way of dictum. Treating, however, the provision as a penalty, still the amount named would not be the limit of plaintiff’s recovery. In Noyes v. Phillips, 60 N. Y. 408 , there was an agreement for an exchange of land with this clause, “and the parties to these presents each agree to give a good and sufficient deed for their respective pieces of property on or about the 1st day of April, 1873, or forfeit the sum of $500,” and defendant’s counsel asked the court to charge that the jury could not under any circumstances go beyond the sum of $500, or that sum and interest from April 1, 1873. The court declined so to charge, and defendant’s counsel excepted. The jury found a verdict for $1,000. Appellant contended that “the recovery could not exceed $500.” The appellate court (Chief Justice Church) said as follows: “The second point is not tenable. It being a penalty and contained in an agreement inter partes, the plaintiff has his election to sue for the penalty or for a breach of the contract. In the latter event
This ruling was followed in Matter of Carter, 21 App. Div. 118 , 123, [ 47 N. Y. Supp. 383 ].
So, also, the supreme court of Florida, in Smith v. Newell, 37 Fla. 147 , [ 20 South. 249 ], after discussing the question whether the sum was liquidated damages or penalty, says that if the sum mentioned in the contract is construed to be merely a penalty the plaintiff “must prove the actual damage that he has sustained, and he cannot in such a case recover any greater sum as damages than his proof shows him to have actually sustained in consequence of the breach of the contract. In such eases plaintiff is entitled to recover all such damages as he proves himself to have exactly sustained in consequence of the breach, whether they exceed the amount of the penalty mentioned in the contract or not. The amount of the penalty does not, in such cases, limit the amount of the recovery. ’ ’
The court in its judgment required the defendants to pay the plaintiff six and one-quarter cents per cubic yard for the 4,388 cubic yards of sand removed, and at the same time compels them to pay what it will cost to restore to the lot this amount of sand, thus for the one item of injury giving to the plaintiff double damages. The judgment is therefore hereby modified by deducting therefrom the sum of $274.25, the amount allowed for the 4,388 cubic yards of sand at six and one-quarter cents per cubic yard, and thus modified the judgment and order appealed from are affirmed, appellants to recover costs of this appeal.
Hall, J., and Cooper, P. J., concurred.
A petition for a rehearing of this cause was denied by the district court of appeal on October 18, 1909, and a petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on November 15, 1909.
Cases cited
- Patent Brick Co. v. Moore 75 Cal. 205 at 209 p. 351
- Long Beach City School District v. Dodge 135 Cal. 401 at 405 p. 351
- Pacific Factor Co. v. Adler 90 Cal. 110 at 120 p. 352
- Noyes v. Phillips 60 N. Y. 408 p. 352
- In re Carter 21 App. Div. 118 at 123 p. 353