Majority
The above-entitled actions, though separate in record, as far as pleadings, findings and judgments appear, were consolidated for trial in the court below. On the appeal both actions are heard on one set of briefs and both involve identical points. There was, as indicated, but one trial and the issues involved in both cases are to be determined from the. same evidence. The first action was instituted to foreclose a lien upon certain real estate owned by the defendants therein. These same defendants subsequently brought the second action to quiet the title to their property and the issue in this latter suit was the effect of the claimed lien upon the title. So, it is readily observed, in both eases the controversy concerns the lien, its validity and effect. There were, at the outset, other parties involved, but the rights and claims of these have been determined or settled and do not enter into the present appeal.
Merely historical, it may be noted that the suit of the lien claimant to foreclose his lien was commenced at a time long prior to the institution of the suit to quiet title. Judgment was obtained foreclosing the lien as against all parties, including the owners of the property. On subsequent proceedings the judgment as against the owners was set aside and the issues as between the lien claimant and the owners remained undecided at the time the owners commenced their action to quiet their title. In this last action the lien claimant, answering, set up his lien and asked that his validity be declared. Thereafter, and very properly, came the order consolidating the actions for trial. Though tried as one, separate judgments resulted. In the lien suit the judgment of the court below was against the plaintiff, lien claimant, the court’s findings being that claim of lien did not meet the requirements of the statute governing and further that the right of lien had been lost. In the quiet-title action the judgment and decree, in the court below, found the title of the plaintiffs, the owners, free from any claim of the defendant lien claimant, and enjoined a further assertion of said lien.
To avoid confusion of parties, hereinafter, the issues will be discussed as between the lien claimant and property owners and the parties will be referred to in such capacities.
The findings of the court below, which support both judgments, are epitomized as follows: That plaintiff filed his lien against the property on account of labor done and materials furnished. That said form of lien contained a description of the property sought to be charged with said lien as follows: Beginning at a point 82[^ feet east of the northeast corner of the west one-half of the east one-half of lot 13, section 29, of subdivision of Rancho Azusa de Duarte, as per map recorded in book 6, page 80, Miscellaneous Records of Los Angeles County, the boundaries of said property, aside from said point, not being given in said lien so filed or in the complaint of plaintiff on file herein. The allegations showing construction, reasonable cost, nonpayment, and sufficiency of filing in point of time are found to be true. It is further found that the plaintiff, lien claimant, entered into an agreement with the Fish-mans, whereby it was agreed that the former should be paid, on account of the materials and labor to be furnished by him in the premises, the sum of $50 on the day following the filing of the notice of completion ánd further sums thereafter, some of which were payable more than one year following the filing of said notice of completion; and that said lien claimant further agreed to and did accept a trust deed securing said payments. Here we might note that the finding does not set forth from whom the trust deed was taken. But the admitted fact is that the trust deed was taken from the Fishmans and all parties here agree that
Appellant makes the contention that the question of the sufficiency of the description was without the issues. It might be conceded, however, that the answer of the defendant sufficiently denied the allegations of the complaint on the entire subject of the lien and its contents as to make this question an issue. However, appellant goes further and urges that whatever might have been an issue in the pleadings, at the trial this issue was waived and the case tried in the court below on the theory that the lien was sufficient. In this contention the appellant is supported by the record. The record discloses that in the court below all parties were ready and anxious to have the cause submitted on the real issues without delay or loss of time in the discussion or trial of issues on which there was no real disagreement. Counsel for respondents at the opening of the trial thus stated the case to the court: “The issue is that Mr. Leibowitz, the plaintiff, took a note secured by a trust deed upon that property.” Thereafter, the only testimony put in was when the trial judge was soliciting a stipulation from counsel as to the amount admittedly unpaid under the building contract. At that time counsel for respondent called appellant to the stand and in doing so stated: “This is so informal I don’t know hardly whose witness he is but I will call him our witness for the purpose of cross-examination.” The sole subject of this examination was as to the amount expended and the reasonable value of the work done; everyone seemed to concede the location of the premises beyond question. After evidence was presented on the cost of the building and improvements the following colloquy ensued: "The Court: Now, what other facts are there that are still in dispute? Mr. Shelton (at
Respondent contends that, irrespective of the theory of the ease, there is always reserved the question of the insufficiency of the complaint to state a cause of action. Pursuing this argument it is contended that the complaint was absolutely barren of any cause of action and that any stipulation of fact could not aid it in this respect. The complaint cannot be so considered. There is the direct allegation of the description of the property, which description was as hereinbefore set forth. In the absence, as here, of a special demurrer and particularly at this stage of the proceedings, there must be applied the ancient maxim holding that certain which can be made certain. For aught that appears on the face of the complaint the premises involved were capable of no better description; likewise, the description given might have been the one usually and generally employed in designating the premises referred to. In the case of Planing Mill Co. v. Roman Catholic Bishop, 179 Cal. 229 , 231 [ 176 Pac. 166 ], the rule is announced as follows : “ ‘ The best rule to be adopted is, that if there appear enough in the description to enable a party familiar with the locality to identify the premises intended to be described with reasonable certainty, to the exclusion of others, it will be sufficient. There is great reluctance to set aside a mechanic’s claim merely for loose description, as the acts generally contemplate that the claimants should prepare their own papers; and it is not necessary that the description should be either full or precise. ’ ” Likewise in this case the court adopts the suggestion in the ease of Union Lumber Co. v. Simon, 150 Cal. 751 [ 89 Pac. 1077 , 1081], to the effect that in action for the enforcement of the lien the plaintiff might enlarge the description in his
The second finding of the court is- that the lien claimant entered into an agreement with the Fishmans whereby it was agreed that the plaintiff should be paid, on account of the materials and labor to be furnished by him in the premises, the sum of $50 on the day following the notice of completion and further sums thereafter, some of which were payable more than one year following the filing of said notice of completion; and said lien claimant further agreed to and did accept a trust deed securing the said payments. As a conclusion of law following this finding it was held that the plaintiff had thereby waived his lien. Here again we meet the claim of appellant that the finding as to the deferred date of payment is without the issues. The answer set up no such defense, but simply alleges that the claim of plaintiff was paid and satisfied by the acceptance of a trust deed. We will not discuss this •phase of the case, though it is readily seen that there is much merit in appellant’s argument. At the trial"the deed of trust referred to was before the court and we prefer to conclude, for the purposes hereof, that it was considered and could be- considered in its entirety and we reach this conclusion in part from the informal nature of the presentation of fact wherein this issue was loosely presented. A brief outline of fact is here necessary. The owners of the premises had entered into an agreement for the sale thereof to certain parties referred to as Fishman. Under this agreement Fishman entered into possession and there
The remaining question concerns the effect of the deferred payments agreed upon in the building contract. We have been cited to no authority holding that where a materialman or contractor agrees to accept deferred payments and default occurs therein that the right of lien is thereby waived or lost. The fact that the amount claimed may not be due would be a defense available to the owner. It is always essential to the foreclosure of a lien that the claimant prove that money remains unpaid and is due. And where a lien claimant fails to make this proof it does not follow that the lien itself was void from its inception, but merely that there is nothing due to him under his claim. Respondent relies throughout on the provisions of section 1190 of the Code of Civil Procedure. We find nothing in this section to support the contentions made. The lien before us was filed within thirty days from the date of completion. Section 1190 of the Code of Civil Procedure provides as follows: “No lien provided in this chapter binds any property for a longer period than ninety days after the same has been filed unless proceedings be commenced in a proper court within that time to enforce the same; or, if a credit be given and notice of the fact and terms of such credit be filed in the office of the county recorder subsequent to the filing of such lien and prior to the expiration of the ninety-day period, then ninety days after the expiration of such credit; but no lien continues in force for a longer time than one year from the time the work is completed, by any agreement to give credit.” It is obvious that the section has reference to the time within
Lastly, respondent seeks to uphold the judgment on the theory that inasmuch as the action was not brought to trial within two years from its commencement the trial court had the discretion to dismiss the same. (Code Civ. Proc., sec. 1190.) It is sufficient answer to note that the trial court did not dismiss the action, though we do not hold that the action was not brought to trial within two years from the date of its commencement. We might add, in conclusion, that we are not passing upon the question of the owner’s liability in cases where the building contract is entered into and the improvements placed upon his property by one in possession under a contract or agreement of sale. In the court below it was assumed that the owner was liable if the lien was valid and not waived. It was conceded that no notice of nonresponsibility had been given, posted or filed as may have been necessary under the facts existing. Therefore, upon a retrial this question is open.
The judgment is reversed and cause remanded for further proceedings. This will be the order in each of the cases.
Spence, Acting P. J., and Sturtevant, J., concurred.
Cases cited
- Planing Mill Co. v. Roman Cath. Bishop 179 Cal. 229 at 231 p. 11
- Union Lumber Co. v. Simon 150 Cal. 751 p. 11
- D. I. Nofziger Lumber Co. v. Waters 10 Cal. App. 89 at 91 p. 12
- Best v. Wohlford 144 Cal. 733 p. 13
- Martin v. Becker 169 Cal. 301 p. 14
- Bank of Italy v. MacGill 93 Cal. App. 228 p. 15
- Otto v. Long 127 Cal. 471 p. 15
- Hughes Bros. v. Hoover 3 Cal. App. 145 at 150 p. 16