Majority
Plaintiff instituted this action to recover from defendant a balance of $591.21 alleged to be due for the performance of certain work provided for by the terms of a contract entered into between the parties and for the reasonable value of additional work performed by plaintiff which was not included in the contract. The defendant filed an answer containing a general denial of all allegations of the complaint and a cross-complaint whereby he sought to recover from plaintiff the sum of $315 on account of a promissory note in this amount executed by plaintiff to defendant as payee and an additional sum of $314.77 alleged to be due from plaintiff as an overpayment for work performed pursuant to the contract mentioned in the complaint and under a second contract which provided for the performance of similar work on another building. The plaintiff filed an answer generally and specifically denying the allegations of the cross-complaint.
The trial court before whom the action was pending ordered that it be referred to a designated referee who should try all issues both of law and of fact. In accordance with the order thus made the case was tried before the referee appointed by the court. Following the presentation of evidence the referee reported to the court the findings of fact made by him and his conclusions of law drawn from the findings. The court thereupon adopted the findings and conclusions of the referee and rendered judgment in conformity therewith decreeing that plaintiff have and recover from defendant the sum of $346.21 together with his costs incurred in the action. From the judgment thus rendered the defendant prosecutes this appeal.
During the summer of 1927, appellant entered into a contract with the city board of education of the city of Santa Ana to make certain additions to two school buildings in the city of Santa Ana. Included in the work which was to be performed on said buildings was certain plastering work. Appellant thereupon on August 1, 1927, entered into two verbal contracts with respondent, a plastering contractor, for the performance of the plastering work on the two buildings. . One of the contracts related to plastering to be done on the Edison school building and the other contract provided for similar work to be done on the arcades of the Santa Ana Polytechnic High School. The amount sought to be recovered by respondent was for a balance claimed to be due for work done on the high school building. The contract price stipulated for this work was $1186. The price fixed for the performance of the work on the Edison school building does not definitely appear. Appellant testified that it was $625. Respondent testified that it was $652 and that he performed work thereon in addition to that provided for in his contract, for an agreed price of $20, making a total of $672. The work which was agreed to be performed on the high school building consisted of the application of a brush coat to the arcades of the building and the preparation of the arcades for such brush coat by scouring and rubbing said arcades with carborundum stone. After the contract for the plastering work to be done on the arcades of the high school building had been made, the parties agreed to modify the contract to provide that respondent should apply a sand finish to the arcades in lieu of a brush coat and in addition that he should run molds and form caps and bases on said arcades. This was work which was different from the work provided in the original agreement and obviously entailed the expenditure of more time and the utilization of more material. The performance of this extra or additional work and the reasonable value therefor gave rise to the dispute between the parties which occasioned the bringing of the action.
It is earnestly contended that the referee’s finding that the reasonable value of the extra work performed by respondent on the high school building amounted to $1337.98 is entirely lacking in evidentiary support. The evidence with respect to this feature of the controversy consisted principally of the testimony of the parties to the action. It was irreconcilably conflicting. While it does not appear how the referee arrived at the figure which he adopted as the reasonable value of the work the record shows that respondent testified that the reasonable value of the extra and additional work performed by him exceeded the amount found by the referee by more than $200. There was therefore evidence which would have supported a finding of a larger amount. It cannot be said, therefore, that the finding as to the reasonable value of the extra work on the high school building is entirely lacking in evidentiary support. Under these circumstances a reviewing court is not warranted in interfering with the finding. (Schroder v. Aden Gold Min. Co., 144 Cal. 628 , 630 [ 78 Pac. 20 ] ; Ferro v. Lagomarsino, 45 Cal. App. 741 , 744 [ 188 Pac. 626 ].)
Similar objection is voiced to the referee’s finding that the total amount paid by appellant for work on the high school building was $1914.77. The evidence with respect to this feature was also in direct conflict. Respondent testified
Further complaint is made that the referee failed to make any finding with respect to interest and attorney’s fees claimed to be due from respondent on account of the note for $315 executed by respondent on October 14, 1927, which note comprised one of the two items sought to be ■recovered by appellant’s cross-complaint. The referee specifically found that at the time the note was executed the work being done by respondent on the high school building was in progress and the amount which would accrue to respondent on account of the contract and the extra work on said building was undetermined and that in consideration of the execution of the note appellant paid to respondent the sum of $263 and furnished no other or further consideration therefor. This finding was in exact conformity with respondent’s testimony. The record shows that the item of $263 formed part of the total amount of $2,802.77 which the referee found was paid by appellant to respondent on account of both contracts and the additional work performed on the high school building. From the fact that the sum of $263 paid by appellant on the date of the execution of the note was thus allowed as a credit to appellant and from the further fact that the referee after allowing the aforesaid sum as a credit found a balance due to respondent on account of the extra work on the high school building, it is apparent that the referee accepted respondent’s testimony with respect to the execution of the note, the effect of which was that the note was given by respondent purely as an accommodation to appellant. The allowance of the credit of $263, therefore, entirely eliminated any consideration for the execution of the note, and appellant, the payee, was not entitled to recover upon it from the maker, since want of consideration is a good and
One further contention of appellant is entitled to consideration. It is urged that the court before whom the
It is fundamental that every court of record has the inherent power to cause its acts and proceedings to be correctly set forth in its records and that whenever it is brought to the attention of the court that the clerk’s record does not correctly show the order which was in fact made by the court at the time it was given the authority of the court to cause its records to be corrected in accordance with the facts is undoubted. (Kaufman v. Shain, 111 Cal. 16 [ 43 Pac. 393 , 52 Am. St. Rep. 139 ] ; Peoples Ditch Co. v. Foothill Irr. Dist., 123 Cal. App. 257 [ 11 Pac. (2d) 86 ].)
By the provisions of section 638 of the Code of Civil Procedure, reference of an action of the character which is here under consideration may be ordered only “Upon the agreement of the parties filed with the clerk, or entered in the minutes.” The validity of the order of reference depended, therefore, upon the existence of an agreement
Furthermore, objection to a reference which has been ordered without consent is waived by a failure to take exception thereto. (Hendy Machine Works v. Pacific C. C. Co., 99 Cal. 421 [ 33 Pac. 1084 ] ; Shain v. Peterson, 99 Cal. 486 [ 33 Pac. 1085 ]; Estate of Magerl, 201 Cal. 162 [ 256 Pac. 204 ].) Not only does the record herein fail to show that any exception was taken by appellant to the order of reference but it affirmatively appears therefrom that appellant appeared before the referee without objection and submitted evidence in support of the allegations of his answer and cross-complaint. Under these circumstances, appellant must be held to have waived all objections to the reference. (Shain v. Peterson, supra; Bonner v. Lehfeldt, 39 Cal. App. 649 [ 179 Pac. 722 ].)
For the reasons stated the judgment is affirmed.
Barnard, P. J., concurred.
Cases cited
- Schroder v. Hayes 144 Cal. 628 at 630 p. 521
- Ferro v. Lagomarsino 45 Cal. App. 741 at 744 p. 521
- Hunt v. Glassell 47 Cal. App. 774 p. 523
- Aimo v. Mitchell 124 Cal. App. 497 p. 523
- De Jarnatt v. Marquez 127 Cal. 558 p. 523
- Dozier v. Hillman 105 Cal. App. 127 p. 523
- Anglo-California Trust Co. v. Oakland Railways 193 Cal. 451 at 460 p. 523
- Randisi v. Simone 26 Cal. App. 661 at 662 p. 523
- Hulen v. Stuart 191 Cal. 562 at 572 p. 523
- Miller v. Ambassador Park Syndicate 121 Cal. App. 92 p. 523
- Kaufman v. Shain 111 Cal. 16 p. 524
- Peoples Ditch Co. v. Foothill Irrigation District 123 Cal. App. 257 p. 524
- Joshua Hendy Machine Works v. Pacific Cable Construction Co. 99 Cal. 421 p. 525
- Shain v. Peterson 99 Cal. 486 p. 525
- Martin v. Ward 201 Cal. 162 p. 525
- Bonner v. Lehfeldt 39 Cal. App. 649 p. 525