Majority
Headnote
Mechanic’s Lien—Foreclosure — Pleading—Time tor Performance of Work—General Demurrer—Cause of Action.—A complaint in an action to foreclose a mechanic's lien, which alleges the performance of ten days and seven hours’ work upon the building between the first day of June and the twenty-first day of July, 1909, and that the building was completed on the sixth day of July, 1909, shows that sufficient time elapsed for the completion of such work before the completion of the building, and is not subject to a general demurrer on the ground that it does not state a cause of action.Plaintiff brought this action to enforce by foreclosure an alleged lien accruing to him as a mechanic who performed labor upon a building being constructed for defendant. It is alleged in the complaint that defendant entered into a contract with one Morgan for the construction of a five-room brick cottage and that the contract was in writing and duly recorded; that plaintiff was employed by Morgan, the contractor, to perform labor as a painter upon the cottage, for which Morgan agreed to pay him the reasonable value of his services; that pursuant to such employment plaintiff did, “between the first day of June, 1909, and the twenty-first day of July, 1909, ’ ’ perform ten days and seven hours ’ labor in painting said cottage, which labor was of the reasonable value of $54.37. It was further alleged that the cottage was completed on the sixth day of July, 1909, but that no notice of completion was filed with the county recorder, and that on the twenty-first day of July, 1909, plaintiff filed and recorded his claim of lien. The complaint contained other appropriate allegations as to the description of the real property upon which the cottage was constructed, and set forth that the land described was necessary for the convenient use of the building. To this complaint a general demurrer was interposed, which was overruled by the court and defendant having failed to answer the complaint within the ten days allowed him so to do, decree was thereupon entered in accordance with the prayer of the complaint. From that judgment the appeal is taken.
It is insisted on the part of appellant that the complaint of plaintiff failed to state a cause of action for the reason that it does not appear therefrom that the labor performed by the plaintiff was performed prior to the date of the completion of the building, which plaintiff alleged to be the sixth day of July, 1909. To give force to this contention plaintiff’s alie
The judgment is affirmed.
Allen, P. J., and Shaw, J., concurred.
Cases cited
- San Joaquin Lumber Co. v. Welton 115 Cal. 1 p. 774