Appeal—Beview of Insufficiency of Evidence—General Specification—Particulars Bequired—Exception — Particular Finding Assailed as Wholly Unsupported.—Upon appeal from a judgment and from an order denying a new trial, where insufficiency of the evidence is relied upon for a reversal, a general specification “that the evidence is wholly insufficient to justify a judgment in favor of the plaintiffs,” is improper, as not in compliance with section 648 of the Code of Civil Procedure, requiring a specification of the particulars wherein the evidence is insufficient to justify the decision. But where a particular finding is assailed as being wholly without evidence to support it, a more particular specification is not required.This is an appeal from a judgment against the defendant and from an order denying his motion for a new trial in an action for services rendered by plaintiffs as architects.
Defendant relies for a reversal of the judgment and order upon the insufficiency of the evidence. The only specification of such insufficiency is “That the evidence is wholly insufficient to justify a judgment in favor of the plaintiffs.” We think, with the plaintiffs, that this is not a compliance with section 648 of the Code of Civil Procedure, requiring a specification of the particulars wherein the evidence is insufficient to justify the decision. (Matter of Baker, 153 Cal. 537 , [ 96 Pac. 12 ]; Meek v. Southern Cal. Ry. Co., 7 Cal. App. 607 , [ 95 Pac. 166 ]; Porter v. Counts, 6 Cal. App. 551 , [ 92 Pac. 655 ].) But as defendant claims that there is an entire absence of evidence to support the finding assailed—in which event he asserts that a specification of particulars is unnecessary (San Luis Water Co. v. Estrada, 117 Cal. 168 -184, [ 48 Pac. 1075 ])—we have examined the evidence, and will therefore rest our decision upon the principal point in the case, without further noticing respondents’ claim that the specification set forth above is entirely insufficient.
Plaintiffs prepared plans and specifications for the construction of a building to be erected in San Francisco; a builder was found who would construct the building for less than fourteen thousand dollars, and who furnished at once a satisfactory bond for the performance of his contract. As all these things were according to the terms of plaintiffs ’ contract with defendant, they were entitled—the defendant having refused to permit them to proceed further—to recover a reasonable compensation for services already rendered, and the damages arising from a prevention of complete performance.
In brief, there is evidence in the record to sustain the view that the defendant, without good reason, refused to permit the plaintiffs to complete their contract, which they were willing and able to do. It follows that the judgment and order of the trial court should be affirmed, and it is so ordered.
Lennon, P. J., and Hall, J., concurred.