Majority
Headnote
Contract to Purchase Land—Provision for Improvements not Completed in Time—Waiver of Third Payment—Construction-Validity—Effect.—A contract to purchase land which contains a provision for improvements to be made within a specified time, and if not so completed, the third payment should not be required, is a reasonable provision for a fair apportionment of the purchase price; and it is not invalid and unenforceable either as an attempt to liquidate the damages, in violation of section 1670 of the Civil Code, nor as a penalty, which would prevent specific performance of the contract under section 3369 of the Civil Code. It is in effect an agreement to sell property in an incomplete condition for a fixed price, with an option to make improvements within a specified time, which, if done by the seller, an additional price was to be paid therefor, which makes the payment of the purchase price in full.The action was one brought by plaintiff against defendant for the specific performance of a contract for the purchase of real estate. The contract, made a part of the complaint, was entered into by defendant as party of the first part and W. B. Redburn & Son and plaintiff of the second part, the same being an agreement to sell and convey to the parties of the second part certain described premises consisting of a large number of lots in a tract called the “Back Bay Tract No. 1,” being a subdivision of certain lands in the city of Long Beach. The consideration price named for the lots was $31,850, $12,740 being paid at the date of the signing of the agreement, $9,555 being payable on or before the fifteenth day of July, 1906, and the balance of $9,555 on or before the fifteenth day of January, 1907, with six per cent interest upon deferred payments, payable semi-annually. The agreement contained the usual clause providing that if default be made in any of the payments, or in any of the covenants and conditions of the contract, the whole should become due and payable and the first party given the right to cancel the contract, re-enter and take possession of the premises and retain all moneys paid as rent for the use and occupation of such premises. It was further agreed that when all of the payments were made a deed should be given conveying a good and sufficient title to the property, free and clear of all encumbrances. It was further
A general demurrer to the complaint was interposed and overruled, and defendant answered, admitting the execution of the contract,, but denying performance upon plaintiff’s part; and alleging further that in June, 1906, plaintiff and Redburn & Son partitioned the premises between themselves, evidenced by a new and independent contr'aet which was entered into between defendant and the respective parties to the partition; said second contract is set out in the answer, and contains no provision with reference to the price which should be received for the premises in the event the improvements were not made; admits the conveyance to Redburn & Son of their share of the property so allotted by the mutual partition and the receipt by defendant of the full consideration price therefor. Defendant denies that all of the improvements were not made within eighteen months, but .alleges that they were all made before the suit was commenced, except as to the matter of sidewalks and curbs; that defendant was unable to make such sidewalks ■ and curbs because of the absence of certain ordinances requisite therefor. Defendant further alleges that at. the time of the filing of the complaint herein it had filled the said lots, but there is no issue as to default having been made in the filling of such lots within the eighteen months prescribed in the original agreement. The answer, however, seeks to excuse this nonperformance of the contract because of its impracticability, in view of the fact that the Back Bay Tract comprised a large body of land which, to be filled in a proper manner, required dredging and filling of the entire tract, which could not be done within the eighteen months. Defendant denies generally those allegations of the complaint as to the reasonableness and fairness of the contract with reference to the purchase price. Plaintiff in due time filed his affidavit denying the due execution and delivery of the second contract attached to defendant’s answer.
The action was tried by the court, which found the allegations of the complaint to be true, found that the contract
It is very clear from the record that the second contract, being the one set out and attached to defendant’s answer, was never executed; that while the signatures were thereto attached, the same was not delivered by defendant or accepted by plaintiff, and that the only contract between the parties duly executed and delivered was the contract set out and attached to plaintiff’s complaint. The answer admits the partition, alleging only that it was evidenced in a particular
The principal point presented by appellant is that this waiver of the third payment in default of the making of the improvements was a contract either for a penalty or for liquidated damages ; that, regarding the same as one for liquidated damages, under section 1670 of the Civil Code, the same is void because from the nature of the case it was neither impracticable nor extremely difficult to fix the actual damages in the event of failure to perform the conditions, and that there is no evidence in the record tending to show the amount of actual damages, if any existed; and further, that if treated as a penalty, under section 3369 of the Civil Code, specific relief cannot be granted to enforce a penalty or forfeiture in any case. The learned trial judge in construing the agreement determined the case evidently upon the theory that the so-called waiver of the third payment was neither an attempt to liquidate damages, nor in the nature of a penalty, but was, in effect, an agreement to sell property in an incomplete condition for a fixed price, which was the cash price plus the first deferred payment, with an option to make certain improvements thereon within eighteen months, which, if made, then the price agreed upon should be the total amount specified, which included the third payment. In other words, that the specified third payment was nothing more than a stipulation as to the enhancement in value which would attach to the property in the event that the contemplated improvements were made within the specified time, and if so made that the plaintiff should pay therefor a stipulated sum; a condition somewhat analogous to a contract involving a sale of vacant property at a fixed price, with an option to construct a house thereon of certain character within a stipulated time, which, 'if done by the seller, an additional price should be paid therefor. We are of opinion that this is a fair construction of this contract, and so construed it is not open to the criticism offered, and does not come within the provisions of the sections of the Civil Code above cited, and that the allegations of the complaint were sufficient to warrant the relief granted.
Appellant further contends that, the action being one for the specific performance of a contract to which Bedburn & Son were parties, the same could not be decreed unless Bed-
Appellant further contends that it was error for the court to grant a decree requiring specific performance of the contract by a conveyance of all of the lots, for the reason that it was alleged in the answer and found by the court that one of the lots ,had been conyeyed by defendant to one Patterson, thereby as to such lot waiving the benefit of the contract, and which lot was included in the decree. While the finding of the court that this particular lot was subject to an agreement of sale entered into between plaintiff and Patterson is inaccurate, the record disclosing the conveyance by defendant to Patterson with plaintiff's consent, nevertheless, no prejudice could result to defendant on account of such unwarranted finding. The lot was included in the original contract of sale and the decree could only have the effect to perfect Patterson’s record title. The mere sale of one or more of the lots would not have the effect to destroy plaintiff’s right to have specific performance to the end that the title by him agreed to be conveyed to the purchasers might be perfected. We quite agree with appellant that under the construction of the contract as determined by the court no claim for damages could be considered. The purchasers took only the uncompleted property, and the making of the improvements was optional with the. seller, who failed to avail himself of such option, and the same could not be the basis for damages. The finding of the court with reference to the value of the improvements and the damages incurred by reason of the delay may be ignored. There is no evidence in the record from which damages may be estimated, even if allowable; nor were there any allegations in the answer that would permit a finding as to the value of the improvements made after the time had expired under the contract
Judgment affirmed.
James, J., and Shaw, J., concurred.
A petition for a rehearing of this cause was denied by the district court of appeal on January 29, 1913.