Majority
Headnote
Mechanics’ Liens—Action of Foreclosure—Order of Payment to One Filing Insufficient Claim.—In a proceeding to enforce mechanics’ liens, one who has not filed a claim of lien, or who has filed an insufiieient claim, but who has served notice on the owner that he has furnished materials, stating the amount thereof and directing that the amount of his claim be withheld by the owner, is entitled, if a party to the proceedings in foreclosure, to have an order of court directing the payment to him by the owner of such sum, jonder the notice provided by section 1184 of the Code of Civil Procedure, as it may appear to the court he is entitled.In prohibition. The facts presented by the affidavit and petition are these: Frey, the petitioner, as owner, contracted with one Campbell for the construction of a building. The same was completed and thereafter an action was begun to foreclose mechanics’ liens, to which Frey, the contractor and lien claimants, other than the plaintiffs, were made parties. Among the lien claimants was a corporation known as The Universal Lumber & Mill Company. This company, in addition to its answer, filed a cross-complaint seeking to establish its claim of lien for lumber and materials furnished and used in the construction of said building. The court proceeded to a trial of the issues, and found that the claim of lien of the mill company was invalid in that it was defective, not specifying to whom it had furnished the materials' and" did not truthfully contain a statement of the terms, time given, and conditions of its ‘contract. The claim of lien stated that the amount of the contract price for such materials furnished was $3,739.38. This the court finds is untrue; that there was an express contract between the contractor and said mill company to furnish materials for $3,219.00 and an implied contract to pay quantum, meruit for the balance of the materials furnished, which the court finds to be the sum of $520.38. The court found that there was the sum $2,831 in the hands of defendant Frey, the owner, being the balance due on said original contract price, and that the plaintiffs and the other lien claimants, other than the mill company, were entitled to liens for the respective amounts claimed by them; that the mill company was entitled to a judgment against the contractor for $3,739.38, and that the balance of all moneys in the hands of the owner after payment of the liens found be applied to the judgment of said mill company, and that it recover judgment against the contractor for the balance of said account. Judgment was accordingly rendered in favor of plaintiffs and the other lien claimants for the aggregate amount due them, and the balance remaining in the hands of the owner after such payments, amounting to $1,716.83, was by the court directed to be paid by the owner to the mill company, and a judgment for the remainder of $1,022.55 was rendered in favor of the mill company and against the contractor. This judgment became final; no execution was ever issued out of the same. The owner paid all of the lien claimants, but made default in
Respondents invoke the long-established and recognized rule that the judgment of a court having jurisdiction of the subject-matter and the parties is, as to the thing adjudged, conclusive upon all the parties regardless of the question whether the thing was correctly adjudged or not, and cannot thereafter be reviewed except in the manner and within the time prescribed by law. This application, therefore, presents the question of the jurisdiction of the court to direct the payment of the balance of the fund in the hands of the owner to one who had not established a lien, and to punish as for contempt for the disobedience of such order. There can be no question under the decisions of the supreme court of this state, (Weldon v. Superior Court, 138 Cal. 428 , [ 71 Pac. 502 ], and other cases), that in a proceeding to enforce mechanics’ liens, one who has not filed a claim of lien, or who has filed an insufficient claim, but who has served notice on the owner that he has furnished materials, stating the amount thereof, and directing that the amount of his claim be withheld by the owner, is entitled, if a party to the proceedings in foreclosure,
The writ is, therefore, denied.
James, J., and Shaw, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on August 30, 1913.
Cases cited
- Frink v. Heirs of Hedrick 127 Cal. 184 p. 424
- In re Hovey 80 Pac. 234 p. 425