Majority
Headnote
Mechanics’ Liens—Notice to Owner to Withhold Payments—Abandonment of Work by Contractor.—Where one who has furnished materials to the contractor for the construction of a school building serves notice on the school district, after the contractor has abandoned work on the uncompleted building and at a time when he has received all payments to which he is entitled, to withhold sufficient money to pay the claim of the materialman, the school district is not thereby in any way made liable to the materialman, under section 1184 of the Code of Civil Procedure.The action was to recover the value of certain materials furnished by plaintiff to the contractor to be
The findings of the court inviting attention are as follows: “That pursuant to said contract said A. B. Pearson commenced the construction of said school building, and continued to supply work and materials for the same up to about January 1st, 1912, at which time he reached the end of his resources, ceased work upon the building and abandoned his
By other findings it appears that, during the months of September, October, November, and December, 1911, while Pearson was in charge of the work, respondent furnished certain quantities of brick to Pearson and to subcontractors under Pearson, all of which were used in the construction of said building. On the third day of January, 1912, and after the abandonment of the contract by Pearson, respondent served notice upon the trustees of the district that there was a balance of $686.40 due him on account of brick furnished to Pearson and his subcontractors for use in said building and required them to pay said sum out of any money due or to become due said Pearson.
It is thus made entirely plain that the service of said notice constitutes the only possible ground for any liability on the part of said district. This notice was given in pursuance of section 1184 of the Code of Civil Procedure [Stats. 1911, p. 1315] and its legal effect is exposed in the following quotation from said section: “Upon such notice being given, it shall be lawful for the owner to withhold and in the case of property, which, for reasons of public policy or otherwise, is not subject to the liens in this chapter provided for, the owner or person who contracted with the contractor shall withhold from his contractor sufficient money due or that may become due to such contractor, to answer to such claim.”
The said notice had the effect of a garnishment of any money coming to the contractor which was in the hands of the owner, the school district, and the extent of the latter’s liability to plaintiff is measured by its liability to the contractor. That is to say, there was and is no liability at all.
Of course, if respondent had served his notice before the district paid Pearson all that he earned under the contract, a different situation would be presented. The governing principle of the case is covered by the decision in Bates v. Santa Barbara Co., 90 Cal. 546 , [ 27 Pac. 438 ] ; Denison v. Burrell, 119 Cal. 180 , [ 51 Pac. 1 ]; Bianchi v. Hughes, 124 Cal. 27 , [ 56 Pac. 610 ] ; Butler v. Ng Chung, 160 Cal. 438 , [Ann. Cas. 1913A, 940, 117 Pac. 512 ] ; Suisun L. Co. v. Fairfield School Dist., 19 Cal. App. 595 , [ 127 Pac. 349 ], and we can see no good reason for offering any additional suggestions upon the subject.
Apparently the only pretense of justification for holding the defendant liable is found in the language of section 1200 of the Code of Civil Procedure, as it formerly existed, as follows: “In case the contractor shall fail to perform his contract in full, or shall abandon the same before completion, the portion of the contract price applicable to the liens of other persons than the contractor shall be fixed as follows,” etc. We need not enquire, however, whether this could be given effect to control the said contract of the parties, as this section was repealed May 1, 1911 (Stats 1911, p. 1319), and hence was not in force when plaintiff furnished said material.
It is to be deplored if plaintiff must lose his claim but we see no legal ground upon which he can enforce it against appellant. His contract was not with the latter, and he failed
The judgment is reversed.
Chipman, P, J., and Hart, J., concurred.