Headnote
Contracts—Nonperformance Within Provided Time—Rescission— Due Performance Under Second Contract—Nonliability Under First Contract.—Where the assignee of a contract for the doing of certain work fails to perform the same within the time specified and notice of rescission is given, the rescinding party is not answerable to such assignee for any compensation agreed to be made for such work under a second contract made with the assignor of the first contract which has been duly performed.Appeal from a judgment entered in favor of the defendant. On the sixth day of February, 1912, respondent made a written contract with one C. H. Lovell, which provided for the printing of fifty thousand baseball schedules upon cards, at the net price of ten dollars per thousand, delivery to be made not later than March 30th of the same year. A few days later a printing firm, doing business under the name of Provident Printshop, notified respondent that its order had been assigned to them by Lovell and that they would complete the same, and instructing respondent to make payment to appellant to whom, so the Printshop informed respondent, had been “assigned the collection of this bill.” Respondent accepted and “0. K.’d” this notification, but the printing not having been done within the time specified, respondent gave written notice to the printers rescinding the contract. It later made a second agreement, based upon different terms, with Lovell, and upon his having furnished the merchandise required under this second contract, they paid him the price agreed upon. Thereafter the appellant made demand upon respondent for the payment to him of the
The judgment is affirmed.
Conrey, P. J., and Shaw, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on March 29, 1915.