Majority
Headnote
Mechanics’ Liens—Lien of Materialman—Time fob Filing—Construction of Code.—A person furnishing materials for the construction of a building may, under the amendment of 1911 to section 1187 of the Code of Civil Procedure (Stats. 1911, p. 1316), file his claim of lien within thirty days after he has “ceased to furnish materials” therefor.This is an action to enforce a material-man’s lien. The record is here on the judgment-roll alone. The court made findings from which as conclusions of law it found: That plaintiffs are entitled to judgment against defendants Barrick & Murphy, a copartnership composed of W. C. Barrick and H. B. Murphy, for the sum of $146.13, but without costs; that plaintiffs are not entitled to a lien against the property of defendants Roux and wife and that these latter defendants are entitled to judgment against plaintiff for their costs. Judgment passed accordingly, from which plaintiffs appeal.
The contention of appellant is that the trial court drew erroneous conclusions from the findings and should have directed judgment enforcing the lien claimed as prayed for by plaintiffs.
It appears from the findings of fact that defendants Roux and wife were the owners of the lots, situated in the town of Mill Valley, on which the building in question was being erected; defendants Barrick and Murphy were the contractors employed by the owners to erect the building; plaintiffs were materialmen who furnished Barrick & Murphy materials for the building; that, about October 16, 1911, defendants Barrick & Murphy, having charge of the construction of said building, contracted with plaintiffs to furnish the lumber and other materials necessary for said purpose.
“6. That acting under and in pursuance of said contract, and as ordered by said defendants Barrick & Murphy, plaintiffs herein doing business under the firm name and style of Mill Valley Lumber Co., as aforesaid, furnished to said de
•Of this amount, $1,530.38 was paid to plaintiffs, leaving due $146.13. It is then found that, on May 25, 1912, “and within thirty days after plaintiffs had ceased to furnish materials as aforesaid,” plaintiffs filed their claim of lien in due form.
“10. That the contract between defendants George F. Roux and May A. Roux, his wife, as owners, and defendants Bar-rick & Murphy, as contractors, under which the building described in the complaint was constructed, was completed on the 4th day of April, 1912, except as to trivial imperfections and modifications to correct them, which modifications were as follows: adding about three feet to the height of the brick chimney, putting in cement steps entering into the basement, and making changes, in window screens; and that on the 4th day of April, 1912, said defendants George P. Roux and May A. Roux, his wife, as owners, went into the open, complete, exclusive and actual use and occupation of said building.”
Finding 13, mentioned in finding 6, and referred to in finding 10, is as follows:
“13. That the only materials furnished by plaintiffs to defendants Barrick & Murphy, as contractors as aforesaid, from and after the 4th day of April, 1912, to and including the 27th day of April, 1912, were materials to be used, and were actually used, in making said modifications to correct said trivial imperfections in said buildings, and amounted in value to the sum of $10.34.”
Finding 11 is that, on April 9, 1912, “and within ten days after the completion of the contract last mentioned as aforesaid” (i. e., the contract between the owners and the contractors Barrick & Murphy), the owners filed and caused to be recorded a notice setting forth that “said contract last men
“12. That plaintiffs failed to file any claim of lien in the office of the county recorder of Marin County within thirty days after the completion of said last mentioned contract as aforesaid, or within thirty days after the completion of said building save for said modifications, or within thirty days after the filing for record of the notice of completion as above set forth.”
The rights of the parties are to be derived from section 1187 of the Code of Civil Procedure, as amended in 1911 (Stats. 1911, p. 1316.) The section reads: “Every original contractor, claiming the benefit of this chapter, within sixty days after the completion of his contract, and every person save the original contractor claiming the benefit of this chapter, within thirty days after he has ceased to labor or has ceased to furnish materials, or both; or at his option, within thirty days after the completion of the original contract, if any, under which he was employed, must file for record . . . a claim of lien containing,” etc. (These requirements were complied with.) . . . “Any trivial imperfection in the said work, or in the completion of any contract by any lien claimant, or in the construction of any building, improvement or structure or of the alteration, addition to, or repair thereof, shall not be deemed such a lack of completion as to prevent the filing of any lien.” Then follows what shall be deemed 1 ‘ equivalent to a completion for all the purposes of this chapter. ’ ’ The section then provides: ‘1 The owner may within ten days after completion of any contract, or within forty days after cessation from labor thereon, file for record . . ..a notice setting forth the date when the same was completed, or on which cessation from labor occurred, together with his name and the nature of his title, and a' description of the property sufficient for identification, which notice shall be verified by himself or some other person on his behalf.” It is then provided that if such notice be not so filed the owner “shall be estopped in any proceeding for the foreclosure of any lien . . . based on the ground that said lien was not filed within the time provided in this chapter. ’ ’
Briefly stated, the court found that plaintiffs continued to furnish materials as ordered and which were used in the building up to April 27, 1912, and they filed their lien within
It seems clear to us that plaintiffs had thirty days after they had “ceased to furnish materials” within which to file their claim of lien, and, in fact, filed it in time, unless they lost this right because the owner took possession of the building and accepted it as completed. The court found that the building was completed except as to certain modifications which required materials of the value of $10.34 and which the court found were “trivial imperfections.” Still, these materials were used in the building and it was not complete in fact, though so treated by the owners, until those materials were so used. Whether trivial or not, the fact remained and was found by the court that plaintiffs did not cease to deliver
Inasmuch as the error complained of lies in the conclusions of law drawn from the findings and inasmuch as the findings are sufficient to support a judgment in accordance with the complaint, we see no reason for a new trial to be had. It is, therefore, ordered that the judgment be reversed and the trial court directed to enter judgment for plaintiffs as prayed for.
Burnett, J., and Hart, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on June 28, 1915.