Street Law — Recovery upon Bond — i-Place of Filing Statement of Claim. — In a case of street improvement work done under contract with a municipal corporation in accordance with the Street Work Act of 1885 (Vrooman Act) and amendments thereto, a claimant furnishing material therefor who seeks to recover on the bond given in connection with the contract must file his statement of claim, as directed by section 6% of such act, with the superintendent of streets, and such a statement filed with the board of trustees and not delivered to such superintendent or filed in his office is not a compliance with such section, although the same was addressed to both the superintendent and board of trustees.The plaintiff appeals from the judgment entered in this action in favor of defendant American Surety Company of New York, and also appeals from an order denying plaintiff’s motion for a new trial.
On April 8, 1911, one L. H. McGowan, as contractor, entered into a contract with the street superintendent of the city of Covina for certain street improvement work. The contract was authorized and the work done in accordance with the Street Work Act of 1885, commonly known as the Vrooman Act,-, and the amendments thereto. In connection with the act of entering into this contract, and on the same date, the contractor, as principal, and the defendant American Surety Company of New York, as surety, executed a bond to the city of Covina, payable in the event that said principal should fail to pay for any materials furnished for the work of improvement described in the contract, or for any work or labor done thereon of any kind; and the bond by its terms was made for the benefit of any and all persons, companies, or corporations performing labor on or furnishing material to be used in said work of improvement. The plaintiff having furnished materials for that work and the principal having failed to pay therefor, this action was prosecuted to recover on the bond.
Section 614 of the Vrooman Act was adopted in 1899, and requires the contractor to give a bond such as was given in this case. That section further provides: “Any material-man, person, company, or corporation, furnishing materials to be used in the performance of said work specified in said contract, . . . whose claim has not been paid by the said contractor, company, or corporation, to whom the said contract was awarded, may, within thirty days from the time said improvement is completed, file with the superintendent of streets a verified statement of his or its claim, together with a statement that the same, or some part thereof, has not been paid. At any time within ninety days after the filing of such claim, the person, company, or corporation, filing the
There is another statute, approved March 27, 1897, entitled, “An act to secure the payment of the claims of materialmen, mechanics, or laborers, employed by contractors upon state, municipal, or other public work.” (Stats. 1897, p. 201.) This act provides that “Every contractor, person, company, or corporation, to whom is awarded a contract for the execution or performance of any building, excavating, or other mechanical work, for this state, or by any county, city and county, city, town, or district therein, shall, before entering upon the performance of such work,” file a bond as described in said act. The required provisions of the bond under this act and the purposes of the bond and the requirement as to giving of notice of claim prior to the commencement of any action thereon, are stated in terms almost identical with the language used in section 6% of the Vrooman Act, but with one important difference. The act of 1897 (as in force when the bond sued on herein was made) required that a claimant seeking to recover upon such bond, “shall, within thirty days from the time such work is completed, file with the commissioners, managers, trustees, officers, board of supervisors, board of trustees, common council, or other body by whom such contract was awarded, a verified statement,”
Although the notice of claim in this, case begins with the words, * ‘ To the Superintendent of Streets and Board of Trustees of the City of Covina, State of California,” we cannot agree that the act of the plaintiff in filing it or sending it to be filed with the board of trustees was in any sense a compliance with the requirement of section 6y2 that the claim be filed with the superintendent of streets. If section 6% constitutes the law applicable to this case, it must be concluded that the plaintiff has failed to perform a necessary condition precedent to its right to recover against the surety on the bond.
Although the act of 1897 is quite general in its terms, it is at least doubtful whether it ever was intended to apply to contracts awarded under the terms of the Yrooman Act. Although contracts under the Yrooman Act are awarded by the city authorities and entered into by the superintendent of streets, the funds for payment of the contractor are obtained by special assessments levied against the property fronting upon the street, and are not paid out of the city treasury. French v. Powell, 135 Cal. 636 , [ 68 Pac. 92 ], relied upon by appellant as an instance where a bond given to secure payment of claims arising out of the construction of a tunnel was held to be a bond given under the act of 1897, is not in point. The contract in that case was not made under the Yrooman Act, but was made by the city on its own behalf and the work was paid for out of the general funds of the city. But even if it be conceded that the act of 1897 at the time of its enactment was applicable to the case of street work done under the Yrooman Act, then we are of the opinion that the adoption of said section 6y2 (approved February 21, 1899; Stats. 1899, p. 23) repealed the act of 1897 in so far as that act could be said to be applicable to work which came within the scope of section &y2. If such street work was included in the act of 1897, it was a special class of work distinct in character from work under contracts made and paid for directly by the state or any of its subdivisions. It was competent for the legislature to enact legislation particularly applying to this class of work. In so doing the legislature,
Finally, counsel for appellant insist that it is entitled to recover upon the bond as a common-law bond, in which event it was not required to file notice of claim with any city officer. Upon this matter there was a conflict of authority which had not been settled when appellant’s briefs were filed in this case. Since that time, however, the eases upon which it relies have been overruled. We refer to Miles v. Baley, 170 Cal. 151 , [ 149 Pac. 45 ], decided by the supreme court of California on May 11,1915. The bond in that case was given under the act of 1897 and in connection with a contract for the erection of a high-school building. Referring to Union Sheet Metal Works v. Dodge, 129 Cal. 390 [ 62 Pac. 41 ], and People’s Lumber Co. v. Gillard, 136 Cal. 55 , [ 68 Pac. 576 ], the court conceded that the opinions in those eases do tend to sustain the position that an instrument like the one there under consideration might be upheld as a good common-law bond without regard to the statute requiring the giving of a bond; and then, after discussing certain other decisions and the reasons therefor, definitely concluded that Union Sheet Metal Works v. Dodge, and People’s Lumber Co. v. Gillard should, as to this particular question, be regarded as overruled.
In Miles v. Baley, 170 Cal. 151 , [ 149 Pac. 45 ], it was distinctly stated that “if the instrument is a statutory bond, it was manifestly essential for the plaintiff to show that all the requisites of the statute vital to the support of an action upon the bond by materialmen, etc., had been observed by his assignors, and the silence of plaintiff respecting that vital
The judgment and order are affirmed.
'James, J., and Shaw, J., concurred;