Majority
Headnote
Mechanic’s Lien—Abandonment of Contract—Portion of Contract Price Available for Liens.—Where a building contract providing that seventy-five per cent of the value of the labor performed and materials furnished during each month was t'o be paid on the first day of the succeeding month until final acceptance of the building, and the remaining twenty-five per cent thirty-five days after such acceptance, was abandoned before completion, the proper amount for the court to take as a basis for the calculation of the portion of the contract price available to materialmen and applicable to the satisfaction of their liens, under section 1200 of the Code of Civil Procedure, as it then existed, was the" total value of the work and materials placed on the land before abandonment, and not the amount of money which had been paid to the contractor to the date of abandonment.This is an appeal from an order granting a new trial. The action was one to foreclose a materialman’s lien. The facts of the case were these: On or about January 22, 1909, the defendant, E. W. Hopkins, as the owner of a lot in San Francisco, entered into a written contract with Webster-Mace Construction Company as a contractor for the erection of a building thereon. The contract price was eighty-one thousand two hundred dollars, payable as follows: Seventy-five per cent of the value of the labor performed and materials installed during each month was to be paid on the first day of the succeeding month until final acceptance of the building, and the remaining twenty-five per cent of the contract price was to be paid thirty-five days after such acceptance. The contractor commenced to work upon the building under this contract, but on May 27, 1909, before completion thereof abandoned its contract. Prior to the time of said abandonment the plaintiff herein had furnished the contractor lumber to be used and which was actually used in the building amounting at agreed prices to the sum of $2,515.48, of which amount there was an unpaid balance of $1,590.38 at the time of such abandonment, for which the plaintiff duly filed its claim of lien. Up to the time of the abandonment of the contract the defendant had made progress payments to the contractor pursuant to its terms amounting to $30,643.95, which sum represented seventy-five per cent of the actual value of the labor performed and material installed up to the date of the abandonment of the contract. The amount of the material delivered and on the ground at the time work ceased and the contract was abandoned was of only nominal value. Subsequently the owner proceeded with the completion of the building in accordance with the original plans and specifications, and actually and reasonably expended thereon the sum of $53,565.50.
.Upon the trial of the case the court made a finding based upon the foregoing facts and upon the construction which it then placed upon section 1200 of the Code of Civil Proce
Upon motion for a new trial the court became convinced that' the evidence was insufficient to sustain the foregoing finding, and accordingly granted the motion for a new trial upon that ground, and ordered a retrial as to that single issue. It is the correctness of this latter ruling which is challenged upon this appeal.
We are of the opinion that the trial court acted correctly. in its order granting the motion for a new trial upon the ground stated.
During the trial of the cause the court apparently fell into a twofold error with respect to this particular matter. In the first place, the court in making its estimate as to the value of the actual work and materials on the premises at the time of the abandonment of the contract took as its basis for its valuation the amount of money which had been paid to the contractor on account- of such work and materials up to said date; but the court apparently overlooked the fact that this amount represented but seventy-five per cent of the actual value of such work and materials, the other twenty-five per cent thereof being retained by the owner under the terms of the contract; and hence that the total value of the said work and materials would be $40,858.60, which would be the proper amount which the court should have taken as the basis for the calculation provided for in section 1200 of the Code of Civil Procedure, as it then stood, for the purpose of ascertaining the portion of the contract price available to materialmen and applicable to the satisfaction of their liens in eases of this character.
The second error into which the court fell was in the construction given by it of section 1200 of the Code of Civil Procedure in arriving at its conclusion that there was no amount in the owner’s possession available for the payment of the plaintiff’s claim.
The appellant herein undertakes to argue that the supreme court was in. error in its views expressed in that case as to the proper interpretation to be placed upon section 1200 of the Code of Civil Procedure, and that the rule therein announced should be departed from by this court in the instant case. But it is not for us to make that departure, and it would therefore be a waste of effort to follow counsel for the appellant through an exhaustive analysis of cases in this and other jurisdictions for the purpose of determining whether the construction adopted by the supreme court of the section of the code in question was the proper one. It is the construction which must be applied by the trial court and this court to the case at bar, and having thus adopted '
We find no merit in any other of the points urged upon this appeal.
Order affirmed.
Lennon, P. J., and Kerrigan, J., concurred.