Majority
Headnote
[l] Mechanics’ Liens — Completion op Contracts — Finding — Evidence.—Where a sublessee, purposing changes in the leased premises, employs eertain persons to perforin the plumbing, electrical wiring and painting, and no definite price is agreed upon nor plan adopted for the contemplated changes, but the work is laid out from day t'o day as it progresses, and such persons employed to do the work follow the instructions given to them from time to time by the sublessee, or his superintending contractor, as to the manner of its performance, in an action to foreclose their liens for such work, testimony of the plaintiffs that all the work which the sub-lessee had requested had been performed prior to Ms death, isJ.—The appeal is from a decree of foreclosure of three contractors’ liens against the leasehold interest of appellants in certain premises in San Francisco. The claims of lien sued upon are based upon work performed in the making of alterations and repairs to a portion of the building on said premises, occupied by one J. 0. Long as a sublessee of
[5] It is further claimed that the record does not disclose when the appellants acquired knowledge of the making of the improvements from which the lien claims arose, and that they never obtained any knowledge of the scope and extent of such improvements. No evidence was introduced upon this matter. Its determination rests, therefore, upon the pleadings. The answer of appellants contains the following allegations: “Answering paragraph 11 of said first cause of action these defendants admit that the defendants S, J. Pringle and E. C. Pringle had knowledge that certain alterations and repairs were to be made in said building, but deny that said S. J. Pringle and E. C. Pringle had full knowledge of the alterations and repairs in said complaint set forth, and in this particular said defendants S. J. Pringle and E. C. Pringle allege that said J. 0. Long informed them that he desired to malee certain alterations and repairs and that these defendants then requested that a full plan of the repairs be submitted to them for their approval, and that said J. 0. Long failed to submit said plan showing said alterations and repairs, and these defendants allege that while they knew that said J. 0. Long had commenced work in said building, that they did not know just what the scope of the said work was.” The knowledge admitted by the foregoing allegations was sufficient, in our
The judgment is reversed in so far as it decrees a lien in favor of the plaintiffs Henry P. Castagnino and Emanuel Castagnino, as copartners doing business under the firm name and style of Castagnino Bros. In all other respects the judgment is affirmed.
Langdon, P. J., and Brittain, 3., concurred.
A petition for a rehearing of this cause was denied by the district court of appeal on May 9, 19191, and the following opinion then rendered thereon:
The appellants in this action have filed a petition for rehearing, claiming that the court has misinterpreted the contracts of the lien claimants Perazzi and Decker Electrical Construction Company, as set forth in their respective claims of lien; and, further, that, under the interpretation of the contracts adopted by the court, the lien claimants were not original contractors and, therefore, their liens, not having been filed within thirty days, were invalid'. Appellants also request a modification of the former opinion as to the prorating of the costs on appeal. In this latter request the respondents have joined in a separate petition, urging, however, a different basis of division of costs.
It appears from the notices of lien filed by said Perazzi and Decker Electrical Construction Company that each of said claimants alleged a contract consisting of two items; first, the performance of certain work in changing the location of the barber-shop, for which in each case a definite contract price was agreed upon; and, secondly, for the performance of certain other work, with regard to which no definite
In the former opinion it is held that two of the liens involved in these consolidated eases were valid and one was invalid. It is, urged by both parties to the appeal that under such circumstances the costs of the appeal should be prorated between them. This contention is well founded and is supported by precedent in similar cases.
. It is, therefore, ordered that appellants’ petition for a rehearing be, and the same is hereby, denied; that the opinion heretofore filed herein be, and the same is hereby, modified by adding at the close thereof the following: “And it is further ordered that appellants recover such proportion of their costs on appeal as the amount of the lien of Henry F. Castagnino and Emanuel Castagnino, as copartners doing business under the name of Castagnino Bros., bears to the total amount of the three liens involved in the appeal; and that the respondents recover such proportion of their costs on appeal as the total amount of the two liens of H.
Langdon, P. J., and Brittain, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme'court on June 9, 1919.
All the Justices concurred.