[1] Building 1 Contracts—Abandonment of Work—Determination of Jury — Sufficiency of Evidence.—In this action by the owner against the contractor and his surety for damages for breach of a building contract, the determination of the jury upon the issue as to the abandonment of the work by the contractor was supported by ample evidence.In a suit by the owner against the contractor and his surety for damages for breach of a building contract, judgment was entered in favor of the owner and against the contractor, and in favor of the surety against the owner. The plaintiff appealed on the judgment-roll from that part of the judgment in favor of the surety. Prior to the establishment of two divisions thereof, the district court of appeal of the first appellate district affirmed the judgment. On rehearing, the supreme court reversed both the decision of the district court of appeal and the judgment, directing the trial court to enter judgment in favor of the owner and against the surety. (Tremble v. Tuman, 175 Cal. 696 , [ 167 Pac. 142 ].) From the judgment so entered the surety appeals, bringing up a bill of exceptions. The principal contention is that the evidence does not support the judgment.
The building contract was made in May, 1911, for the erection of a building to cost thirty thousand dollars. Coincident with its execution, the appellant surety company executed its 'bond in the sum of seven thousand five hundred dollars to the owner for the faithful performance of the contract. The plaintiff alleged abandonment of the work by the contractor on October 24, 1911, and damages amounting to $7,894.10. She prayed for judgment of seven thousand-five hundred dollars against the contractor and the surety. The suit was commenced „in June, 1913. The issues of fact were submitted to a jury, which returned a general verdict against the defendants jointly for five thousand dollars and against the contractor alone for $850. To four questions submitted to the jury it answered: (1) The owner’s architect did not delay the contractor’s work by failure to furnish plans, specifications or working detail drawings; (2) Either the owner or her architect ordered the contractor to do extra work, but no delay was caused thereby; (3) The contractor did not have men working on the 'building every working day between October 24, 1911, and November 14, 1911; and (4) to the question, “Did Mrs. Tremble or Mr. Reed [her architect] take the job away from the defendant contractor and finish
The surety moved for a judgment according to the special verdicts and not in accordance with the general verdict, on the ground that the two verdicts were inconsistent. The motion was granted and the first judgment entered in favor of the surety. That judgment was reversed 'by the supreme court. The only matter necessarily decided on the first appeal was that under the pleadings the general verdict and the special verdicts were not inconsistent, because the issue of abandonment was presented to the jury and determined by it in the general verdict. This is the law of the case. The determination is conclusive if there was any evidence to sustain the general verdict.
[1] On behalf of the appellant it is contended there was no abandonment merely by reason of the failure of the contractor to act under a notice referring to section 14 of the contract, and, further, that, apart from abandonment based upon the construction of that section of the contract, there was no evidence of abandonment to support the general verdict. Section 14 provided that should the contractor fail or refuse “to supply a sufficiency of materials or workmen to complete the contract within the time limited herein . . . for a period of more than three days after having 'been notified by the owner in writing to furnish the same, the owner shall have power to furnish and provide said materials or workmen to finish the said work; and the reasonable expenses thereof shall be deducted from the amount of the contract price.” The appellant presents a lengthy argument upon the interpretation to be given to this clause and relies on a case where a similar provision was construed. (American-Hawaiian Engineering & Construction Co. v. Butler, 165 Cal. 497 -510, [Ann. Cas. 1916C, 44, 133 Pac. 280 ].) On behalf of the respondent, it is contended the two eases may be distinguished. It is not necessary to determine the question thus presented. The determination of the jury upon the issue of abandonment is supported by ample evidence irrespective of the provisions of section 14 of the contract.
Various witnesses, some testifying for the plaintiff and some for the defendants, made statements of facts which are summarized below. The contractor was sick. He visited the work only two or three times. One Craves assumed charge
As against the evidence summarized above, counsel for the appellant admit Mr. Turnan’s financial difficulties, but argue there is no evidence that "because of such fact Mr. Turnan ever decided to abandon the work, and that the evidence of his financial condition did not show it was impossible for Turnan to complete the work. On the contrary, it is argued, that while Graves, as Turnan’s agent, had difficulty in securing funds and one or two of his attempts to secure them failed before the plaintiff finally took the work out of the hands of Turnan, Graves was- successful in making financial arrangements which would insure the completion of the work, though possibly not pay all laborers or materialmen or subcontractors.
This arrangement was one made by Graves with three others, by which on November 6, 1911, thirteen days after the notice was given, ten thousand dollars was deposited in the Crocker Bank in the name of G.
[2] Counsel for the appellant admit it would be impossible for a contractor to avoid liability for having abandoned the work by merely keeping sufficient workmen on the job to sustain the appearance of continuance of the work, but they argue that abandonment is a question of intention. It may be shown by conduct. In law, the word “abandonment” does not necessarily imply a willful or culpable disregard of the contractor’s obligations. It may, as in this ease, be applied to a condition of affairs where, through misfortune the contractor is unable to finance his contract, or by reason of his mental or physical incapacity be precluded from carrying on his work or attending to the business incident to it. The cases cited by the appellant upon this subject lay down no other rule. Apart from any question of the interpretation of section 14 of the contrast, the most that could be said upon the subject of abandonment is that the jury determined the fact upon conflicting evidence. On appeal this court is bound by such a determination.
It is contended on behalf of the appellant that abandonment cannot take place unless the contractor intends to abandon; in other words, unless he expressly or impliedly
The judgment appealed from is affirmed.
Langdon, P. J., and Haven, J., concurred.
A petition for a rehearing of this cause was denied by the district court of appeal on May 29, 1919, and a petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on June 26, 1919.
Angellotti, C.x J., Shaw, J., Wilbur, J., and Olney, J., being all the justices present, concurred.
Cases cited
- Tremble v. Tuman 175 Cal. 696 p. 9
- American-Hawaiian Engineering & Construction Co. v. Butler 165 Cal. 497 p. 10