Majority
Headnote
[1] Mechanics’ Liens—Time fob Filing—Cessation of Work.—A claim of lien by a subcontractor not filed until more than nine months after the constructive completion of the contract, there having been a complete cessation and abandonment of the work by the contractor, is not filed in time.The plaintiff brought this action to foreclose a mechanic’s lien. The only question on the appeal from judgment in favor of defendants is as to whether or not plaintiff’s claim of lien was filed within the time allowed by law. The appeal is taken on the judgment-roll alone, and the findings must be presumed to be in accordance with proof presented on the trial.
According to the findings, the defendant Juliet N. Martin, owner of the real property involved, entered into a contract with W. W. Paden, whereby Paden agreed to erect an apartment house on the land of defendant Martin for the agreed price of forty-three thousand five hundred dollars, and accepted from said defendant certain mortgages and securities on the premises in question, and on other property of said defendant, for the contract price. From the negotiation and sale of these securities he was to raise the money to build the house and receive his profits. The contract was not recorded. The plaintiff Pence entered into an agreement with Paden whereby, as subcontractor, he undertook to furnish the materials and labor for the carpenter work.
[1] The work of construction was begun, and claims on behalf of the plaintiff accrued to the amount of $425. Thereafter Paden, being unable to find a market for his securities, discontinued work under his contract for want of funds, and there was a complete cessation of all work on the building from on or about the 30th of January, 1915. Work was never resumed upon the building by the contractor Paden, or under this contract. About the middle of
Under section 1187 of the Code of Civil Procedure, the plaintiff had thirty days after he had ceased to labor or furnish materials, or thirty days after the completion of the original contract under which he was employed, in which to file Ms notice of lien. Under the provisions of the same section, cessation from labor for thirty days is deemed equivalent to a completion, for all purposes of the mechanic’s lien law. Under the further provision of this section, by reason of the owner not having filed a notice of completion
[2] There is no foundation in the record for appellant’s contention that the plaintiff was misled or “tolled” into a false sense of security by the defendants, or that there was any collusion between Paden and the other defendants to deceive him. Neither the allegations of the complaint nor the findings of the court justify such a conclusion. There was no privity of contract between him and the owner of the property, or any of the defendants, other than Paden. The contract created no liability against the owner of the premises, other than such as might arise under a valid assertion of the lien. Defendants owed appellant no duty to protect his rights. His only claim against the property was his right to a lien, as incident to his employment under the Paden contract, and that was dependent upon his strict compliance with the requirements of the mechanic’s lien law. If the defendants had by act or representation willfully and fraudulently led him to forego his rights of lien, they would doubtless be estopped from setting up as a defense his failure to file the notice within the statutory time; but by merely standing by and permitting him to sleep on his rights, they are not estopped. It does not, however, appear by the record here that the defendants, or either of them, were even aware of the fact that Paden had not settled in full with his subcontractor.
The judgment is affirmed.
Finlayson, P. J., and Thomas J., concurred.
Cases cited
- Kerckhoff-Cuzner Mill & Lumber Co. v. Olmstead 85 Cal. 80 p. 629
- Johnson v. La Grave 102 Cal. 324 p. 629
- Robison v. Mitchel 159 Cal. 581 p. 629