Majority
Headnote
[1] Contracts—Acceptance of Plans and Specifications—Failure to Proceed With Construction — Liability for Architect’s Compensation Promised—Evidence—Findings.—In this action to recover the compensation the board of trustees of the defendant high school district stated in their published notice they would pay to the architect whose plans and specifications in detail for a proposed addition and extension to the high school of the district were adopted, the evidence was sufficient to support the finding of the trial court that on a given date, the said board of trustees, after duly considering all of the plans and specifications submitted under said notice, by resolution and order spread upon the minutes of the said board, adopted the plans and specifications submitted by plaintiff, subject to a condition subsequent, to wit, that the plaintiff should modify and change the plans to the satisfaction of the board; and said board, having thereafter failed and refused to proceed further with the construction of said building, and not having requested plaintiff to make any modifications or changes in said plans and specifications, but having failed and refused to pay plaintiff the agreed compensation, the latter, having stood ready to comply with all the conditions of his contract, became entitled to the compensation agreed to be paid.On or about the twelfth day of February, 1915, the board of trustees of the defendant published a notice to architects, calling for plans and specifications in detail for a proposed addition and extension to the- high school building of the district. It was stated in the notice that “the said trustees will award to the architect whose plans and specifications in detail are adopted” a specified premium and compensation. At a meeting of the board held on the fourteenth day of March, 1915, the board, having considered several plans and specifications submitted under said notice, including those of the plaintiff, took action which was shown by the minutes of the meeting that it was “Moved by Hamilton, seconded by Clark, that the plans and specifications of F. T. Harris be accepted. Motion carried.” At .a meeting of the board held on the sixteenth day of April, 1915, said minute entry was read and, on direction of the members of the board, but without formal motion and order of the board, the secretary amended the minute entry by inserting after the word “accepted,” the words “when modified and changed to the satisfaction of the board.” After the amendment had been interlined by the secretary, a motion was made and carried “that the board rescind the action of March 14, 1915, with reference to accepting the plans and specifications of architects.”
[1] Upon the issue as to whether or not the plans and specifications were accepted as alleged in the complaint, the court found: “That on the fifteenth day of March, 1915, the said board of trustees of the defendant, after duly considering all of the plans and specifications submitted under the said notice by resolution and order spread upon the minutes of said board, adopted the said plans and specifications as submitted by plaintiff, subject to a condition subsequent, to wit: that the plaintiff should modify and change
Appellant contends that said findings are not sustained by the evidence in this, that there was no absolute acceptance of plaintiff’s offer with a condition subsequent, but that there was only a conditional acceptance and that therefore no contract resulted and would not result until there had been a compliance with the conditions of the acceptance by the plaintiff in making modifications and changes in his plans and specifications which would meet the approval of the board. By the use of the phra'se, “subject to a condition subsequent,” as we interpret the finding, the court decided that the board did in fact accept the “plans and specifications in detail,” as presented by plaintiff, but with the condition or understanding that such modifications therein as should be directed by the board would be made by the plaintiff. Upon this finding, if sustained by the evidence, it must be held that the contract was complete; and since the board did not thereafter indicate its desire to have any modification or change made in the plans or specifications and the plaintiff did not fail to comply with any such indicated desire or instructions, and since it was shown that the plaintiff filed the necessary bond and stood ready to comply with all the conditions of his contract, he became entitled to the compensation agreed to be paid.
The judgment is affirmed.
Shaw, J., and James, J., concurred.