Majority
Headnote
[1] Municipal Corporations — Construction ox Pipe-line — Extra Work — Noncomfliance With Contract — Liability ox City.— Where a contract with a municipal corporation for the construction of a water-pipe line for the city’s water supply specifies the precise conditions under which alone it will be obliged to pay for extra work, but this method is not followed by the contractor, there can be no recovery for such extra work under the contract.This is an appeal from a judgment for extra work, in favor of plaintiff and against defendant, a municipal corporation.
The plaintiff and the city of Daly City, a municipal corporation, entered into a written contract for the construction of a water-pipe line for the city’s water supply. The pipe-line was required to be laid, by the contract, plans, and
The plaintiff was informed by the city engineers of this new requirement and of changes in the plan necessary to meet this requirement. The plaintiff continued with the work, and then discovered that this change in the plan would bring the pipe trench below the surface soil and into rock, and it protested that this would entail considerable additional expense. The engineers orally directed the plaintiff to proceed with the work and “keep a good record of it and see what it costs, and when we get through we will make a fair settlement with you.”
After the work was finished a claim for the extra work, labor, and materials necessitated by this change in the plan was presented to the board of trustees and was by it rejected. This suit was commenced for the sum of $2,844.80, and resulted in a judgment for $1,432.98. The original contract price was $8,900.
The contract provided that the work should be done in strict accordance with the plans and specifications, and completed to the satisfaction of the engineers of the city, and its board of trustees, for the sum of $8,900; and it further provided that in the event of any deductions or additions being made, certain unit prices established and specified in the contract would be used in determining the amount to be added or deducted. These, however, do not include the
Cl] The municipality had the right to specify in the contract the precise conditions under which alone it would be obliged to pay for extra work. This it did. But this method was not followed by the contractor. There was no prearranged schedule of prices for the extra work agreed to betAveen the engineers and the contractors; neither was the extra Avork or alteration, nor any payment therefor, authorized by resolution of the board of trustees. As this provision of the contract was not complied with there can be no recovery under the express contract. (Gray v. La Societe Francaise, etc., 131 Cal. 566 , [ 63 Pac. 848 ].)
The findings are prepared in such a way as to support the theory of an implied as well as an express contract. We are of the opinion that the evidence is insufficient to support the judgment on the theory of an implied contract. [2] It is well settled that an implied contract does not arise for work done for a municipality under an ultra vires contract. (Reams v. Cooley, 171 Cal. 157 , [ 152 Pac. 293 ]; Zottman v. San Francisco, 20 Cal. 96 , [ 81 Am. Dec. 96 ].) That Avould have the effect of putting the power to contract Avhere none existed, and Avould in effect change the charter of the city. [3] As the engineers here were not permitted to contract on behalf of the city under the terms of the contract defining and limiting their powers, to hold that they could by their conduct give rise to an implied contract would in
The only action of the board of trustees in regard to the matter is the rejection of the claim for payment for the extra work. The whole matter seems to have been handled between the engineers and contractors under the belief that equitable considerations would prevail, and not the strict terms of the written contract. The engineers had no power to obligate the city for this extra work. The judgment is not supported by the evidence, either on the theory of an express or implied contract.
The judgment is therefore reversed.
Waste, P. J., and Richards, J., concurred.
Cases cited
- Gray v. La Societe Francaise de Bienfaisance Mutuelle 131 Cal. 566 p. 624
- Zottman v. City & County of San Francisco 20 Cal. 96 p. 624
- Wallace v. Mayor of San Jose 29 Cal. 180 p. 625
- J. M. Griffith Co. v. City of Los Angeles 6 Cal. Unrep. 119 p. 625