Majority
Headnote
[1] Building Contract—Erection of School Building—Failure of Contractor to Complete Work—Bight of District.-—Under a clause in a contract for the erection of a school building providing that should the contractor at any time during the progress of the work refuse or neglect to supply a sufficiency of materials or workmen the owner should have the power to provide the same after three days’ notice in writing given and finish the work and deduct the reasonable expense thereof from the contract price, the school district was not required, where the contractor failed to complete the work and there was no abandonment of the contract, to re-advertise for bids for such completion, but it had the right to complete the work itself in accordance with the terms of the contract.This is an action on the contractor’s bond given to the owner as security for the faithful performance of a contract made with the plaintiff school district by one B. H. Paul for the erection of a school building. The plaintiffs appeal from the judgment entered in favor of defendants.
The findings state “that on or about the sixteenth day of October, 1915, the contractor, B. H. Paul, ceased work on said building, and thereafter continuously and at all times up to about the twelfth day of January, 1916, failed to furnish labor and material to carry out said contract.” In fact, he never did anything further on the contract, unless it be held that work done after the date last mentioned, or some part of it, was done by the school district in his behalf. On November 1, November 4, and November 22, 1915, the school district gave to the contractor and to the Southwestern Insurance Company three-day notices framed in ae
On the fourteenth day of January, 1916, the Southwestern Surety Insurance Company offered in writing to the school district that it would furnish all the necessary material and workmen to complete the contract and would fully and faithfully perform the conditions thereof, and demanded that it be permitted to complete the contract. This offer was refused by the school district, which at that time had taken charge of the work. Between the twelfth day of January and the twenty-first day of June, 1916, the school district expended in carrying on the work for the completion of said building the sum of $20,535, which was the reasonable value of all the material and workmen thus furnished. On June 21, 1916, the school district notified the contractor and said surety company that there had been expended on the school building the sum last mentioned, in addition to the sum previously paid to the contractor and that the building was not completed, and the school district requested and demanded that the contractor and said surety company proceed to complete the work in accordance with the contract. This the contractor and surety company wholly neglected and failed to do. There
The work done between the twelfth day of January, 1916, and the twenty-first day of June, 1916, whereby said sum of $20,535 was expended, was done by the school district without any publications calling for bids or specifying the time and place where bids were opened; in other words, without any attempt to let contracts in the manner described in the section of the Political Code to which we have referred.
Upon the facts found, judgment should have been rendered in favor of the plaintiff, unless the judgment should be affirmed for one of two reasons which on this appeal are relied upon by the respondents. These contentions are that the judgment should be affirmed, (1) for the reason that the school district made expenditures in excess of the statutory amount without advertising for bids as required by law; (2) for the reason that the surety company offered to perform the contract and fulfill all the obligations thereof.
It is contended by respondents that their first proposition is sustained by five decisions of the supreme court of this state. Dougherty v. Foley, 32 Cal. 403 , and Meuser v. Risdon, 36 Cal. 239 , are street assessment cases in which it was held that where a contractor failed to enter upon the contract or had abandoned the work, it was necessary for the municipality to re-advertise for bids. But the statute under which the proceedings in those cases had been conducted in terms provided that there must be a re-advertisement for bids under the circumstances stated. In this respect they are different from the statute in question in this case, inasmuch as said section of the Political Code is silent on the subject of re-advertisement for bids or reletting of contracts. In Reams v. Cooley, 171 Cal. 150 , [Ann. Cas. 1917A, 1260, 152 Pac. 293 ], and Matthews v. Town of Livermore, 156 Cal. 294 , [ 104 Pac. 303 ], the court was dealing with a situation created by the failure of public corporations to comply with the provisions of law governing the letting of original contracts, and not with any question pertaining to the duty or power of the district or corporation to proceed under circumstances like those presented in the
Foxen v. City of Santa Barbara, 166 Cal. 77 , [ 134 Pac. 1142 ], is the one case in which the facts are closely parallel to those in the case now before the court; with a difference, however, which we think is important. The city of Santa Barbara is a municipal corporation operating under a freeholders’ charter in which there are sections which provide an exclusive method for the construction of all public works. Proceeding according to that method, the city entered into a contract for the boring of certain tunnels to develop water for use by the inhabitants of the city. It is stated in the opinion that “subsequently, with the consent of the defendant, the contractor abandoned the work and the water commissioners of the city thereafter prosecuted the construction of the tunnels.” This work was done by employing engineers, foremen, bosses, and men to do the work without attempting to let a contract “to the lowest responsible bidder,” as required by the charter. On examining the record in that case we learn that, as set forth in the findings, the contractor “did by and with the consent of said city, relinquish and abandon the said contract or contracts so far as they obligated him to construct the then uncompleted portion” of the described work. Therefore, in passing, we express the opinion that when the court said in the decision that the contractor “abandoned the work,” those words were used in the sense of the findings; that is to say, that the contract was abandoned. It was held that under those circumstances the water commissioners did not have power to perform the work on the tunnels by day’s labor, and that any contract which they made with the plaintiff in that connection was void.
[1] In the present action the contract was not abandoned by the contractor, nor was it abandoned by the school district. The contractor had failed to complete the work. The school district insisted upon its completion in accordance with its terms. In proceeding to do the work on and after the twelfth day of January, 1916, the school district was proceeding in accordance with the terms of a contract still in existence, which had been let according to law, and which by its terms provided for the then existing emergency. The provision thus made was a part of the contract of
We have not deemed it necessary to discuss the numerous decisions from other states which are referred to in the briefs, most of which sustain the position of appellants on this question. It is conceded that a few decisions run the other way, notably the case of Chicago v. Hanreddy, 211 Ill. 24 , [ 71 N. E. 834 ], which is cited in the Foxen ease, supra. We are satisfied that the rule contended for by respondents and indicated in the Foxen case, even if admitted as the true rule, should not be held to apply, unless the contract has been abandoned and thereby is at an end.
In Bacigalupi v. Phoenix Building etc. Co., 14 Cal. App. 632 , 639, [ 112 Pac. 892 , 894], the first district court of appeal describes in apt words the purpose and effect of contract terms similar to those contained in section 6 of the present contract which we have quoted. The court said: “This paragraph has no application to the case where the contractor entirely abandons the contract, but only applies where he is proceeding under the contract, but fails to supply a sufficiency of materials or workmen to complete the contract within the time limited by the contract. It was intended to give the owner the right, under such circumstances and after giving the notice, to take the completion of the contract into his own hands and to deduct the cost thereof from the contract price. This we think to be the meaning of the paragraph as between the owner and the contractor, and by which the surety was bound.” In legal effect, the work is being done under the contract and in its performance the owner is acting for the contractor, as it was agreed that he might do under those circumstances.
[2] . The offer of the surety company to perform the contract, when considered with relation to the expiration
The judgment is reversed.
Shaw, J., and James, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on January 17, 1921.
All the Justices, concurred, except Lennon, J., who was absent.
Cases cited
- Meuser v. Risdon 36 Cal. 239 p. 78
- Reams v. Cooley 171 Cal. 150 p. 78
- Matthews v. Town of Livermore 156 Cal. 294 p. 78
- Foxen v. City of Santa Barbara 166 Cal. 77 p. 79
- Bacigalupi v. Phoenix Building & Construction Co. 14 Cal. App. 632 at 639 p. 80