Majority
Headnote
[l] Mechanics' Liens—Release of Nonenforceable Lien—Payment by Owner—Recovery from Surety.—Under a building contract providing that the contractor, on or before thirty-five days after the acceptance of the building, shall cancel and release the building and premises from all claims that may have accrued against the building, the owner cannot recover on the bond an amount paid to obtain the release of a lien, where such lien was not an enforceable claim for the reason that the bond and contract were both recorded and the owner had paid to the contractor before the recording of the notice of completion sums of money that aggregated the full amount of the contract price.This is an action by the owner of a building upon a building contractor’s bond. The action is against the contractor and his surety. The Surety Company answered, and, after a trial, obtained a judgment from which plaintiff, the owner, appeals.
The building contract whereby the defendant Myers contracted to construct a building for plaintiff contains a provision to the effect that the contractor, on or before thirty-five days after the acceptance of the building, shall “cancel and release the said building and premises from all claims that may have accrued against the said building by reason of the aforesaid erection.” Contemporaneously with the execution of the contract, the contractor, as principal, and the Surety Company, as surety, executed and delivered to plaintiff a bond in the penal sum of $6,600, conditioned that “should said M. A. Myers (said contractor) faithfully keep and strictly perform all the covenants of said agreement [the building contract], and well and truly pay, or cause to be paid, all just claims against him for such aforementioned labor or materials, or both, so performed or furnished, as the case may be, then this obligation to be null and void, and otherwise to be and remain in full force and effect.” Though the bond is a statutory undertaking, given pursuant to the requirements of section 1183 of the Code of Civil Procedure, it also is a valid, express contract between the owner and the surety, and, as between those two, is a good common-law bond. Both contract and bond were duly filed in the office of the county recorder before the commencement of any work, and, therefore, according to the express declaration of the code, the owner’s liability to lien claimants was limited to the measure of the contract price, and any recovery by such lien claimants under their liens would be restricted “to an aggregate amount equal to the amount found due from the owner to the contractor.” (Sec. 1183, Code Civ. Proc.) But there was no amount due from the owner to the contractor; for, at various times between the execution of the contract and the recording of the notice of completion, the owner had paid to the contractor, under the terms of their contract, sums of money that aggregated the full amount of the contract price. The result is that no lien claimant was entitled to a foreclosure of any lien upon the building, though he might be entitled
[1] There are two conditions in the bond on the due performance of which .that undertaking provides that it shall be void. The first is that if the contractor shall faithfully keep and strictly perform all the covenants contained in his building contract, then his obligation as principal and the obligation of the Surety Company as surety shall be null and void. Plaintiff cannot recover as for a breach of this condition. The contract, as we have pointed out, provides that the contractor, within thirty-five days after the acceptance of the building, shall cancel and release the premises from all claims “that may have accrued against said building.” The claim of the lumber company against
The other condition of the bond is that if the contractor shall well and truly pay, or cause to be paid, all just claims against him for labor or materials, then his obligation as principal and that of the Surety Company as surety shall be null and void. Assuming, for the purpose of this decision, that this condition that all just claims against the contractor for labor or material shall be paid is a provision that inures to the benefit of the owner as well as to the benefit of laborers and materialmen, plaintiff, nevertheless, has no cause of action for its breach. To the contract between the -contractor and the Hammond Lumber Company, the plaintiff here was not privy; no obligation rested upon him in respect thereto. Appellant was under no legal obligation to pay the claim of Hammond Lumber Company; his property could not be made liable therefor; and’ it does not appear that the contractor, whose debt it was, requested him to pay it. In order to entitle appellant to recover against the Surety Company, it must be made to appear that the lumber company had an enforceable lien, or that for some other cause the payment that appellant made to the lumber company was compulsorily made. In the absence of an enforceable lien making plaintiff’s payment compulsory, it must be held that the payment of the lumber company’s claim was voluntary on his part; and he cannot acquire a right of action against the surety which he would not have had in the absence of such payment. In principle, the case is not distinguishable from Brill v. De Turk, 130 Cal. 241 [ 62 Pac. 462 ], and for the reasons there stated the judgment must be affirmed. (See, also, Growall v. Pacific
Judgment affirmed.
Craig, J., and Myers, J., pro tern., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on February 27, 1922.
All the Justices concurred.
Lennon, J., was absent, and Richards, J., pro tern., was acting.
Cases cited
- Brill v. De Turk 130 Cal. 241 p. 40
- Growall v. Pacific Surety Co. 21 Cal. App. 185 p. 41