Majority
Headnote
[1] Contracts—Construction of County Highway—Elimination of Uncompleted Portion — Mutual Agreement —■ Evidence — Findings.—In this action to recover damages for the alleged breach of a contract for the construction of a county highway, arising out of the elimination from the contract of a portion of the highway which was at the time uncompleted, the evidence was ample to support the finding of the trial court that the elimination of the uncompleted portion of the highway from the contract was made pursuant to a mutual agreement of the parties to that end.This is an action to recover damages for the breach of a contract entered into between plaintiffs and defendant whereby plaintiffs engaged to construct a certain highway for defendant. Judgment went for the latter and plaintiffs appeal.
The contract between the parties provided for the building of nearly eleven miles of road. Appellants had entered upon the performance of the work, had fully completed more than four miles of the road and had done the preliminary work of clearing the land throughout the remainder of the distance, when the uncompleted portion of the highway was “eliminated” from the contract. Notice of this elimination was given orally to appellant, according to some of the testimony, by the engineer and certain members of the highway commission of respondent and appellants were by the engineer, according to his own testimony, ordered to “shut down” the work under the
[1] It was alleged in the answer and found by the trial court that the elimination of the uncompleted portion of the highway from the contract was made pursuant to a mutual agreement of the parties to that end. Appellant contends that the court’s finding on this subject is not supported by the evidence, and, as we view the case, the determination of the appeal depends upon the solution of this question alone. One of the members of the board of supervisors of respondent testified, in part: “I had a conversation with the plaintiffs in this case concerning the contract now before the court. I do not remember the exact date, but it was some time during the fall of 1917. The conversation was with Mr. Paul Benson. ... I cannot give the exact words. ... As I understand, Mr. Benson’s position was that if they were compelled by the county to complete the entire contract, there was a doubt whether there would be funds enough to pay them. ... I cannot give the exact language, but Mr. Benson was attempting to ascertain from me what the disposition of the board of supervisors of the county would be toward settling the contract in full, and they got me to admit in my judgment there wouldn’t be
On December 5, 1917, and after the time of the various conversations referred to by these two witnesses, appellants addressed to the highway commission of respondent a letter, the body of which was as follows: “As you have eliminated that portion of our contract on the Wasco-McParland road from station 0.30 to station 351.00 (except such portion as has already been completed), we ask for release on same in order that we may have our bond canceled. Hoping you may see fit to grant the same, we are, Respectfully, . . . ” There is apparently one feature of this communication which accords with the claim of appellants that the “elimination” was made unilaterally by respondent and that appellants were “ordered” to cease work under the contract by the engineer of the highway commission. That feature is exhibited in the opening words of the letter: “As you have eliminated that portion of our contract,” etc. These words of the missive, however, may have been used because of the fact that in a sense respondent was primarily chargeable with the elimination through its failure to keep intact the fund referred to in the testimony of the two witnesses; but whatever the reason for their use, other deductions may be drawn from the letter—deductions entirely consistent with the claim of respondent that the contract, as to the uncompleted work, was abandoned through the mutual consent of the parties. Why, for instance, was the letter written before any formal action in the matter of “elimination” had been taken either by the highway commission or by the board of supervisors? Prior to December 5, 1917, nothing had developed on the subject except by way of oral communication between the parties. If appellants were opposed to the “elimination” why did they not say so in their letter ? The communication is devoid of the slightest assertion that they were not agreeable to a cessation of the work under the contract. If
On the receipt of the letter from appellants, on December 6, 1917, the highway commission transmitted it to the board of supervisors with the recommendation “that the request be granted by your board.” On the same day the latter body adopted the resolution referred to in the letter of its secretary, already mentioned, which in terms, it will be remembered, eliminated the uncompleted work from the contract. The resolution recited, by way of preamble, the receipt of appellants’ letter by the highway commission, and also the fact that the commission had recommended that appellants’ request be granted.
We cannot but conclude that the record discloses ample evidence to support the finding to which objection is made.
Judgment affirmed.
Finlayson, P. J., and Craig, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on August 14, 1922.
All the Justices present concurred.
Richards, J., pro tem,, and Myers, J., pro tem., were acting.