Majority
Headnote
[1] Contract — Erection of Building — Waiver of Performance Within Contract Time—Negotiations for Purchase of Adjoining Lot.—In this action for damages for an alleged breach ofThe plaintiff commenced an action against the defendant to recover damages for an alleged breach of contract. The defendant was awarded a judgment and the plaintiff has appealed under section 953a of the Code of Civil Procedure.
The defendant is a corporation engaged in buying and selling real estate. It had sold under an executory contract to the York Realty Company a lot 40x80 located at and 'being the northeast corner of Stockton and Green Streets. Later the purchaser was about to sell its contract to the plaintiff in this case. Whether after, before, or as a part of those negotiations is not clear, but we will assume, for the purpose of this decision, as a part of the consideration moving to this plaintiff the defendant executed its contract. The defendant still being the owner of adjacent lands on the north side and wanting to build up the neighborhood, advised the plaintiff to purchase the contract held by the York Realty Company and, as an inducement, executed and delivered to the plaintiff a contract in words and figures as follows, to wit:
“To Julius Levin Company:
“Within one year from date of delivery to you or your nominee of our deed to lot N. E. Corner Stockton and Green Streets, San Francisco, fronting 40 feet on Stockton Street and 80 feet on Green Street, we agree to erect and complete on the lot 40x80 adjoining same to the North, a store, or market building of one or more stories and basement, and if not so completed within said time we will pay to you, or your successor in interest, the sum of $2,500.00, as liquidated damages for the failure so to complete said building within said time, it being impossible to estimate damages in the event of breach of this agreement, it being understood and agreed that delays caused by act of God, or the enemy, strikes, shall not be considered as part of the said period of one year.
“Commercial Centre Realty Co.,
“By A. Ruef, Manager.
“February Twenty-eighth,
“Nineteen Hundred Nineteen.”
According to the terms of that contract, as applied to the other facts above stated, the defendant should have built its building on or 'before February 28, 1920. It did not do so. The plaintiff sued as for a breach. The defendant answered and pleaded (1) a denial, (2) no consideration, (3) a waiver, and (4) a rescission and abandonment. The trial was had before a jury. All of the defenses were supported by at least some evidence, oral or documentary, or both. The jury returned a general verdict in favor of the defendant. No special verdicts were requested or rendered. The third defense was copiously presented. Mr. Ruef, the president of the defendant corporation, testified at length regarding that defense. His testimony was to the effect that in May, two or three months after the date of the contract on which the suit was based, he commenced to have conversations with the officers of the plaintiff corporation of and concerning the nature of the best building which the defendant should build. They discussed a theater instead of a store or market. Estimates indicated that a theater would pay twenty per cent, and tentative leases indicated that a lessee could be found who would advance the most of the money, if not all, needed to construct the theater. When these facts transpired, the plaintiff’s officers
[2] The appellant claims that the trial court committed errors in instructing the jury. This claim is addressed to instructions on the subject of damages and the subjects covered by the first, second, and fourth defenses. If the jury found for the defendant on the third defense (and in support of the judgment we must assume"that it did), then the jury had no occasion to consider damages and the error, if any, was immaterial. The same remark can be made as to instructions addressed to the first, second, and fourth defenses.
Taking in view the whole record, we find no error. But if there was any error committed by the trial court, we
The judgment is affirmed.
Nourse, J., and Langdon, P. J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied hy the supreme court on April 9, 1923, and the following opinion then rendered thereon:
In denying the application for a transfer to this court we do not wish to be understood as approving the opinion to the effect that errors in the instructions upon the first, second, and fourth defenses were cured by the general verdict of the jury in favor of the defendant.
An examination of the record, however, discloses that the instructions complained of were not prejudicially erroneous as to the plaintiff.
The petition for a rehearing in this court after decision by the district court of appeal of the first appellate district, division two, is denied.
Wilbur, C. J., Waste, J., Kerrigan, J., Lennon, J., Myers, J., Lawlor, J., and Seawell, J., concurred.