[1] Street Law—Assignment of Bonds—Action to Quiet Title Against Assignor—Notice of Assignee of Pendency of Action —Section 385, Code of Civil Procedure—Judgment Binding on Assignee.—Where an assignee of street bonds had notice, of the pendency of an action to quiet title to property affected by such bonds, brought by property owners against his assignor (a street contracting company), and such notice was obtained long before the answer of the assignor was filed in such action, the assignee, under section 385 of the Code of Civil Procedure, could have been substituted as defendant in place of the assignor, or could have elected, as he did, to have the case continued in the name of the assignor, and in either ease such assignee was bound by the judgment rendered in such action.Action to quiet title to nine separate parcels of land owned by the various plaintiffs herein..
With reference to the corrugated iron culverts which formed part of the work to be performed the resolution provided “that there be constructed thereon eleven corrugated iron part circle pipe culverts, each having a twelve-inch radius, a height of six and one-half inches at the center, and a concrete base four inches thick.” The value of this portion of the work amounted to several hundred dollars.
On March 10, 1913, the mayor and members of the common council met informally with a representative of the Ransome-Crummey Company, discussed the matter of making certain changes or alterations in the work which was then being constructed, and they finally agreed that there should be omitted therefrom the eleven corrugated iron part circle pipe culverts, and that in lieu thereof open concrete drains should be substituted. Thereafter a resolution was adopted to this effect. The time to protest under section 5% of the Vrooman Act (as added by Stats. 1909, p. 31), had expired on February 13th, some twenty-five days
The bonds here involved were previously issued on June 16th by the city treasurer to the contracting company.
In his answer to the supplemental complaint filed herein defendant Berry claimed to have acquired these bonds as trustee for the Standard Portland Cement Corporation, to which company they had been assigned by the Ransome-Crummey Company.
On July 24, 1913, an action was commenced in the superior court of Santa Clara County in which the plaintiffs were substantially the same as the plaintiffs in this action, and Ransome-Crummey Company and the treasurer of San Jose were defendants. That action was also one to quiet title to the same land involved in this action. The record also shows that the Standard Portland Cement Corporation and W. R. Berry had definite notice and knowledge as early as January, 1914, of the pendency of this action. Berry also had notice at this time that the interest coupons on the bonds were not paid on January 2, 1914. Counsel for appellant herein verified an answer and cross-complaint in the Bates v. Ransome-Crummey case ( 42 Cal. App. 699 [ 184 Pac. 39 ]), in which that company claimed to be the absolute owner of the bonds. This was almost a year after their pretended sale to Berry. Judgment was entered in that action on November 24, 1915, quieting the title of plaintiffs against Ransome-Crummey Company and the city treasurer. An appeal was taken and it was dismissed October 14, 1919. The present action was commenced February, 1915.
Upon the trial thereof it was claimed that the bonds were prematurely issued, and that the contract was changed after it was executed by the omission of the iron culverts, for which reason it was asserted that no recovery could be had thereon. It was also contended below, and is here,
The trial court found in substance that neither nor any of the defendants had any right, title, interest, or estate in the parcels of land in question. It further found that in doing the work provided for in the resolution of intention Ransome-Crummey Company wholly failed and omitted to. install the iron culverts, and had not therefore substantially performed its contract; that the owners had appealed from the assessment and that their appeal had been denied. It was further found that on July 24, 1913, an action was commenced in the superior court of Santa Clara County in which the plaintiffs in this action were plaintiffs and Ransome-Crummey Company and the city treasurer of San Jose were defendants; that this action was one to quiet title to the same property described in the action against Ransome-Crummey Company and the city treasurer, and that it arose out of the same improvement of the same street; that on August 2, 1913, said company indorsed and delivered to the defendant herein the bonds referred to in the cross-complaint; that in the month of January, 1914, defendant received notice and knowledge of the pendency of said action, and that plaintiffs herein were contesting the validity of the bonds; that in the month of March, 1915, defendant Berry returned the bonds to Ransome-Crummey Company for the purpose of enabling this company to collect the amounts due thereunder; that judgment was entered in that action against the company in December, 1915, and that a new trial was denied; that an appeal was taken and determined, and that the judgment became final. It was further found in this connection that the attorney in the present suit was the attorney for the defendants in the former action, and that he had been such attorney for defendant Berry since January, 1914.
Judgment was accordingly rendered in favor of plaintiffs herein and defendant Berry appeals.
The findings of the trial court are fully supported by the evidence. With reference to the former suit had between the parties it appears therefrom that the action of Bates v. Ransome-Crummey Co., was prosecuted by plaintiffs herein except that three of the present plaintiffs are sue
Section 1908 of the Code of Civil Procedure provides, in part, that the effect of a judgment or final order in an action or special proceeding is, in respect of the matter directly adjudged, conclusive between the parties and their successors in interest by title acquired subsequent to the commencement of the action, litigating for the same thing, provided they have notice, actual or constructive, of the pendency of the action. The evidence establishes the fact that defendant and appellant herein had notice, and, in fact, it shows that he participated in the litigation by advancing money for its conduct. [2] By participating in the former proceedings defendant is estopped by the judgment (15 R. C. L. 1010-1016; 23 Cyc. 1259). This being so, other questions become unimportant and it is unnecessary to discuss them.
The judgment is affirmed.
St. Sure, J., and Richards, J., concurred.
A petition for a rehearing of this cause was denied by the district court of appeal on September 21, 1923, and a petition by appellant to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on October 22, 1923.
Cases cited
- Bates v. Ransome-Crummey Co. 42 Cal. App. 699 p. 507