[1] Street Law—Recovery of Assessment—Pleading.—In an action by a railroad company against a city to recover money, which the former was required to pay for street work, upon the theory that the city was obligated under an order of the Railroad Commission to pay for the work done within the block between two designated streets, excepting a described portion where the rails of the plaintiff crossed the block, a specific allegation in theThe plaintiff sought to recover a judgment against the defendant for certain money paid by plaintiff to redeem street improvement bonds secured by a lien upon its property in the city of Madera. A general demurrer to the complaint was interposed by defendant, but was overruled, and by its answer the defendant admitted all of the allegations of the complaint excepting the allegation that the claim of plaintiff was due, owing, and unpaid. The ease coming on for trial was submitted to the court upon the allegations in the complaint, as admitted by defendant in its answer. Judgment was rendered for the defendant, and the plaintiff has appealed.
On the oral argument of the appeal counsel for respondent urged the point that the complaint fails to state a cause of action. It appears from the complaint that in 1913, following the presentation of an application by the city of Madera for permission to extend Sixth Street at
Appellant’s theory of its case may be set forth by quoting the closing paragraph of its opening brief on this appeal: “In conclusion, appellant earnestly contends that respondent is obligated to pay for the maintenance of that portion of Sixth Street between E Street and F Street lying outside of and beyond two feet outside the outer rails of the outer railroad tracks of appellant, and having failed in its obligation to do so, that appellant is entitled to a judgment for the money which it was compelled to expend for that purpose. ...”
[1] In view of the fact that plaintiff’s right to recover is based upon the payment by it of an amount assessed against its property on account of work done within the block between E and F Streets, the specific allegation that the charge was wholly for and on account of work done without the block, which allegation limits and qualifies the previous averment as to the assessment, creates a fatal de
[2] However, if we assume, notwithstanding the existence of this specific averment, that the complaint sufficiently shows, as is contended by appellant, that the assessment did include not only the cost of the improvements of the intersections, but also the cost of the work within the block, we are then confronted with the situation that, while the appellant admits the liability of its property for such portion of the assessment as was chargeable for the improvement of the intersections, it failed to allege or prove either such portion or the portion charged on account of the work done within the block. To recover the full amount paid, it was incumbent upon the plaintiff to prove that the assessment was wholly on account of the improvement within the block, but the contention of plaintiff just referred to excludes any claim that the assessment was thus limited. To recover a lesser sum it was then necessary for plaintiff to prove the specific amount it was compelled to pay because of the inclusion of the expense of that particular part of the improvement in the total cost, but the complaint contains no allegation either specifying such an amount or giving data from which it could be determined, and, on the trial, no attempt was made to make such proof.
A judgment then for the entire amount paid by plaintiff under the assessment would clearly have been erroneous and plaintiff, having failed to prove what lesser sum, if any, it was entitled to, the court, for that reason alone, if none other, was compelled to render judgment against it.
It being necessary to affirm the judgment for the reasons stated, a discussion of other questions raised in the briefs becomes, unnecessary.
The judgment is affirmed.
Hart, J., and Finch, P. J., concurred.
A petition by appellant to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on November 6, 1923, and the following opinion then rendered thereon:
In denying the petition for a transfer to this court after decision by the district court of appeal, we withhold approval from that portion of the opinion holding that the complaint does not state a cause of action. The complaint does not allege and no evidence was introduced to show the amount which the plaintiff was entitled to recover from the city, if it be assumed that the agreement between the city and the appellant, confirmed by the order of the Railroad Commission, was valid and binding upon the parties, and entitled the plaintiff to recover some amount from the city under the circumstances alleged in the complaint, consequently the judgment must be affirmed.