Majority
Headnote
[1] Public Works—Highway Construction—Abandonment—Competition by County — Bight to Moneys Due. — Where the contract for the construction and improvement of a section of a county highway not only gives the county the right to withhold twenty-five per cent of the stipulated amount to be paid as compensation for the proposed improvement, but also gives the county the right, in the event of abandonment by the contractor, to use any moneys due or to become due on the contract to complete the work left undone, the contractor cannot make any assignment of the funds due to him at the time of the abandonment of the contract that will affect the right of the county to use that fund in the payment of the expenses in completing the work; and the right of the county, in such event, is not limited to the retained percentage of twenty-five per cent.On the thirteenth day of June, 1916, an agreement was entered into between the county of Kern, acting through its board of supervisors, as the party of the first part, and the Coast Construction Company, a partnership consisting of Stephen V. R. Malcolm and others, as party of the second part, for the construction and improvement of 7.56 miles of that certain highway in the county of Kern known as and called the McKittrick-Marieopa road, for the estimated sum of $44,766.15, to which was thereafter added, as extras, the sum of $1,017.42. At the same time, and as a part of the same transaction, there was delivered to the board of supervisors of said county, of Kern and made a part of said agreement two certain bonds, executed by the American Surety Company of New York, the cross-complainant and respondent
The agreement was conditioned in the usual form and provided for progress payments in the sum of seventy-five per cent of the estimated value of the work and the retention by the county of Kern of the sum of twenty-five per cent until thirty-five days after the final completion of the work agreed to be performed. The bonds were conditioned as is usual in such cases.
Thereafter, and on or about the thirtieth day of June, 1916, the Coast Construction Company, the contractor in the agreement above mentioned, entered into an agreement with the Empire Securities Company, the appellant in this action, whereby the execution of the contract for the work above provided to be done by the Coast Construction Company was set forth, also the execution of the two bonds given by the American Surety Company of New York. The amount of the contract and other matters were set forth. It was mentioned that the contractor desired to borrow money for the purpose of enabling the contractor to carryout the aforesaid contract and the Securities Company was willing to lend money for that purpose. It was agreed that the Securities Company would advance to the contractor in installments, as requested from time to time, money not in excess of seventy-five per cent of the work done and materials furnished under the aforesaid contract, etc.; it was further provided that an agent of the Securities Company might be at all times upon the work with authority limited to the keeping of the time of employees, the paying of bills for labor and material and seeing that all labor and material previously furnished had been paid for, etc. As security for such advances, the agreement assigned to the Securities Company all the right, title and interest of the contractor in and to the moneys that might become due and payable under the agreement for the improvement of the road above mentioned.
Under this agreement with the contractor the Securities Company loaned the sum of $32,284.65, all of which was
The contractor entered upon the performance of the work early in July, 1916, and proceeded with the same until on or about the eleventh day of December, 1916, when it abandoned the same and discontinued work thereunder. At the time of the abandonment of the work, five units, upon which seventy-five per cent estimates, had been made, were completed. Of these, four estimates in the aggregate of $20,304.94 had been paid. The fifth estimate, approved by the highway commission, but not by the board of supervisors, in the sum of $3,867.25, remained unpaid. It is this sum that is in controversy in this action. The trial court awarded this sum to the American Surety Company, and it is from this part of the judgment or decree of the trial court that the Securities Company appeals.
At the conclusion of the trial it was adjudged that laborers and materialmen had enforceable claims against the Surety Company in the total sum of $15,703.38. It was also found by the trial court that, at the time of the abandonment of the contract the status of the contract and the amount of money still in the county treasury in the county of Kern was as follows:
“Contract price ............................$44,766.15
Extras ..................................... 1,017.42
Total .....................................$45,783.57
Payments to contractor....................... 20,304.94
Balance available for completion............$25,478.63
The amount last stated was made up as follows:
Retained percentages ...............$ 8,057.39
Fifth estimate, approved by Highway Commission but not by Supervisors, exclusive of retained percentage of 25 per cent ...................... 3,867.25
Unearned balance of contract price... 13,553.99
Unexpended balance .........................$25,478.63
It was further established that the county of Kern had forfeited such
contract and had elected to and did complete the work therein provided for, expending in connection therewith, after allowance of certain credits, the sum of.........................$18,660.26
[Tr. 615]
Leaving in the hands of the county for such disposition as the court might direct, the sum of..........................$ 6,818.37”
As to the payment made by the contractor for labor and material, the trial court found as follows: “Approximately the sunn of $20,000 was proven by said contractors to have been expended in connection with, said contract, but a substantial part of said last-named amount was expended for purposes other than material and labor. Whether such sum was paid from the fund so furnished by said Empire Securities Company, or from moneys borrowed by said contractors from other sources, because of the mingling of said funds, to the knowledge, and with the consent of said, Empire Securities Company, it is impossible to determine.”
The trial court also found that the Securities Company, at the time of the assignment of $3,867.25 was made to it by the Coast Construction Company, advanced nothing of value and did not pay out any money represented or covered by said assignment towards the discharge of the claims of the materialmen for the payment of labor on account of the improvement of said highway; that the only promise made by the Empire Securities Company was that, if a representative of the Coast Construction Company would go to Bakersfield and there assign to the Empire Securities Company said claim or estimate in the sum of $3,867.25, the Empire Securities Company would then consider the making of a further advance. This advance was desired to meet a pay-roll of the Construction Company then due. This advance was never made. The court further found that the Securities Company desired the assignment for the intent and purpose of appropriating to its own use the amount of money represented thereby and not for the purpose of applying the sum towards the payment of labor performed upon or materials used in construction
It is by virtue of this assignment of the fifth estimate that the Securities Company claims to be entitled to the sum of $3,867.25, as hereinbefore stated. To support its contention the appellant relies upon the eases of Los Angeles Rock and Gravel Co. v. Coast Construction Co., 185 Cal. 586 [ 197 Pac. 941 ]; Slayden v. O’Dea, 182 Cal. 500 [ 189 Pac. 1066 ]; Adamson v. Paonessa, 180 Cal. 157 [ 179 Pac. 880 ]; Hunt v. Empire Securities Co., 50 Cal. App. 43 [ 194 Pac. 744 ]. These eases, however, have no application to the issues presented to this court for decision. In those cases the contracts were awarded under the provisions of the Vrooman Act (Stats. 1885, p. 147), or the Improvement Act of 1911 (Stats. 1911, p. 730), contain no provisions as to the retention of any portion of the contract price, and also were instances in which the contracting parties had no rights in any portion of the amount agreed to be paid to which a surety upon performance could be subrogated. [1] In the case at bar the county of Kern had control and in its treasury the entire sum agreed to be paid to the contractor and the provisions of the contract not only gave the county the right to withhold twenty-five per cent of the stipulated amount to be paid as compensation for the proposed improvement, but also had the right in the event of the abandonment of the contract by the contractor, to use any moneys due or to become due on the contract to complete the work that might be left undone by the contractor. Section 106 of the agreement between the Coast Construction Company, the contractor, and the county of Kern provided for such eon- • tingency and gave the county the power above stated. After specifying what the county might do towards completing the work should it be left undone by the contractor, that section contains this language: “All expenses charged under this paragraph shall be deducted and paid by the county out of any moneys then due or to become
[3] In so far as the assigned warrant is concerned which is involved in this case, the Securities Company stands in the position of a general creditor. No money was advanced on account thereof, as heretofore stated, and as also shown all moneys advanced by the Securities Company went into the general banking account of the Coast Construction Company upon which checks were drawn in prosecution of at least four distinct and separate contracts for that many different specified improvements. In this particular the language of the court in Title Guaranty & Surety Co. v. Dutcher, 203 Fed. 167 , quoting from page 169, is directly applicable: “All the money borrowed by the contractor went into his general bank account with other of his money. During the time involved he had four separate contracts with the city. No account was kept of the' particular work upon which disbursements were made, and it is not shown how much, if any, of the money borrowed, or other money of his, was paid upon the contract in question.” Under such circumstances it was held that the rights of the surety were paramount. A large number of cases were also cited by the court in the above-mentioned decision. To the same effect is the case of First Nat. Bank of Seattle v. City Trust etc., 114 Fed. 529 [ 52 C. C. A. 313 ], In that case the rights of the surety on account of moneys advanced by it to discharge claims for unpaid labor and material were held paramount to that of the bank which founded its claims upon money loaned to the contractor, which likewise went into the contractor’s general banking account.
In In re McGarry & Son, 240 Fed. 400 [ 153 C. C. A. 326 ], it is held: “That the surety, on payment of labor and material claims, was subrogated and that its equity attached as of the date of the bond, and that a mere volunteer’s rights would be subject to those of the surety who pays the labor and material bills.” (Citing Prairie State Bank v. United States, 164 U. S. 227 [ 41 L. Ed. 412 , 17 Sup. Ct. Rep. 142 , see, also, Rose’s U. S. Notes].) In that case it was held that the rights of the surety on account
In the case of Wasco County v. New England Equitable Ins. Co., 88 Or. 465 [Ann. Cas. 1918E, 656, L. R. A. 1918D, 732, 172 Pac. 126 ], the supreme court of Oregon speaks of the rights of the respective parties as follows: “When the bank loaned its money it knew that before Cromer entered upon the performance of his contract he had given a bond signed by a surety, and that the law required the county to reserve twenty-five per cent of each monthly estimate. Prom the date of the contract of suretyship the bank was bound to know that the insurance company had an equity in the funds to be reserved; and when the bank loaned its money it did something that it was not obligated to do, and it must be deemed to have acted with a full knowledge of the right of the surety. The contractor and the bank could not create a lien in favor of the bank upon the reserved fund and make it paramount to a prior and then existing lien of the surety,” citing a number of authorities to the same effect.
The federal cases, heretofore cited, are supported by the decision in the case of Prairie State Bank v. United States, supra. Whether the law required the retention of twenty-five per cent is wholly immaterial as the contract of which all parties had notice so specified. An almost identical question was before this court in the case of Maryland Casualty Company v. Shafer, 57 Cal. App. 580 [ 208 Pac. 192 ], In that ease, this court, speaking through the presiding justice, said: “The further provision for retention by the county of sufficient funds to pay claimants who filed verified claims was equally a part of plaintiff’s contract and was for the protection of the surety as much as for that of claimants. To the extent that such provision was observed, the liability of the surety was lessened. The fund retained was beyond the control of Shafer and no assignment by him could prejudice o the rights of the parties for whose benefit the fund was created. To hold otherwise would be to nullify the stipulation of the contract for the retention of the fund and to destroy the security intended for the
To summarize this case, we have these facts: The contractor was carrying, on four contracts; all its money was placed into and withdrawn from a general banking account; the money was not traced; the appellant claims the thirty-eight hundred odd dollars on account of an assignment indorsed upon the fifth estimate upon which no money was advanced by the assignee but which it was understood, as shown by the testimony which we have quoted, the matter of advancing money would be taken up and further considered; the contractor defaulted in his work; at the time of the default the county had in its possession something over $8,000 in retained percentages, as well as other sums of money due and to become due the contractor; the surety advanced over $15,000 to pay the claims of material-men and laborers on account of the contract.
In view of this summary and of all that we have herein-before stated, we think that the judgment of the trial court should be affirmed, and it is so ordered.
Hart, J., and Finch, P. J., concurred.
A petition by appellant to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on June 16, 1924.
All the Justices concurred.
Cases cited
- L.A. Rock & Gravel Co. v. Coast Constr. Co. 185 Cal. 586 p. 641
- Slayden v. O'Dea 182 Cal. 500 p. 641
- Adamson v. Paonessa 180 Cal. 157 p. 641
- Hunt v. Empire Securities Co. 50 Cal. App. 43 p. 641
- Prairie State Bank v. United States 164 U. S. 227 p. 643
- Maryland Casualty Co.v. Shafer 57 Cal. App. 580 p. 644