Majority
Headnote
[1] Mechanics’ Liens—Commencement off Wobk— Findings — Evidence.—The term “commencement of work” means some work and labor on the ground, the effects of which are apparent—easily seen by everybody, such as beginning to dig the foundation, or work of like description, which everyone can readily see and recognize as the commencement of a building; and in these consolidated actions to foreclose mechanics’ liens, the evidence was sufficient to sustain the finding of the trial court that work was commenced upon the building in question prior to the time the mortgage of defendant mortgagee was filed for record.The Harbolt Hotel Corporation was, on the seventeenth day of April, 1917, the owner of a certain lot in the city of Los Angeles, and on said day said company entered into a written contract with one Valentine Hetzel for the erection on said lot of a hotel building. Said contract was not filed for record in the office of the county recorder of said county until the ninth day of June, 1917. On April 30, 1917, said hotel company executed a mortgage upon said real property in favor of appellant, the Western Loan and Building Company, to secure the payment of a promissory note for $42,972.50, and said mortgage was, on the seventh day of June, 1917, duly filed for record in the office of the said county recorder. Thereafter, respondents performed labor and furnished material in the construction of said hotel building, under said contract between said hotel company and the said Hetzel. Failing to receive payment for said labor and materials they filed liens for the respective amounts due them and thereafter instituted their actions for the foreclosure of such liens. The court rendered judgment in favor of said lien claimants, the respondents herein, not only sustaining their liens but decreeing that said liens were prior and superior to the mortgage lien of the Western Loan and Building Company, the appellant herein.
[1] The court found that prior to the execution and recordation of appellant’s said mortgage, and on or about the seventeenth day of May, 1917, but prior to June 1, 1917, said contractor Valentine Hetzel, in pursuaance of the said contract for the construction of said hotel, began the erection and construction of said building and continued work thereon until the early part of November of said year. Appellant contends that the construction of said building was not commenced until after its mortgage had been filed for record in the office of said county recorder, and it attacks the finding of the court that the said contractor began the erection of said building prior to the 7th of June, 1917, as unjusti
As to just what is meant by the term “commencement of work” and as to the amount and character of work necessary to be done upon a building in order to say that work has been begun thereon, we think the true rule is stated in Phillips on Mechanics’ Liens, third edition, page 387, where it is said: “What this law means is some work and labor on the ground, the effects of which are apparent—easily seen by everybody; such as beginning to dig the foundation, or work of like description, which every one can readily see and recognize as the commencement of a building.” Applying this rule to the evidence before the court in this action, we cannot say that such evidence is not sufficient to sustain the finding of the court that work was commenced upon the building prior to the time that appellant’s mortgage was filed for record.
Appellant’s main contention on this appeal, however, is that the lien of its mortgage is superior and prior to the liens of respondents, even conceding that work was commenced upon the building before its mortgage had been recorded. Section 1186 of the Code of Civil Procedure provides as follows:
“Effect of Liens. The liens provided for in this chapter are preferred to any lien, mortgage, or other encumbrance which may have attached subsequent to the time when the building, improvement, or structure was commenced, work done, or materials were commenced to be furnished; also, to any lien, mortgage, or other encumbrance of which the lien-holder had no notice, and which was unrecorded at the time the building, improvement, or structure was commenced, work done, or the materials were commenced to be furnished.”
In the case of McClain v. Hutton, 131 Cal. 132 [ 61 Pac. 273 , 63 Pac. 182 , 622], the supreme court, in construing the above section, held that where the contract between the owner and contractor was invalid, by reason of the failure of the parties thereto to comply with section 1183 of the Code of Civil Procedure, liens for labor performed and materials furnished, related back only to the time the work was done and the materials commenced to be furnished, and the court held that such liens were subsequent and in
[2] The liens of respondents herein, however, rest upon a somewhat different basis. Since the decision of McClain v. Hutton, supra, and in 1911 (Stats. 1911, p. 1313), section 1183 was amended, and as then amended it is still in force. In its amended form it differs materially in its requirements from what it did prior thereto. It now contains no provision that for failure to record the original contract between the owner and contractor, said contract shall be wholly void, or void at all, or invalid. Neither does it contain any provision that when the contract is not filed for record “the labor done and materials furnished shall be deemed to have been done and furnished at the personal instance of the owner,” nor any like provision. Under the section as it now stands, the contract, although not filed as required by the statute, is a valid and subsisting contract between the owner and contractor, and binding upon them and all persons furnishing labor or material for the building, except that when not recorded, the liens provided for by said section, except that of the contractor, shall not be limited by the amount of the contract price. [3] All liens for labor done or materials furnished for the building primarily rest upon this contract and derive their validity therefrom. There is no contract, either express or implied,' between the owner and the subcontractors, or others performing work or furnishing material for the building. Following, therefore, the reasoning of the court in McClain v. Hutton, supra, the liens of such persons, originating under and depending for their validity upon the original contract, would date back to the time of the commencement of work upon the building.
There is nothing in the decision of Roystone v. Darling, 171 Cal. 526 [ 154 Pac. 15 ], which in any way conflicts with this conclusion. In the last-named case the court held that section 1183 described two classes of liens. One where the required bond and contract had been filed, in which case the amount of the liens is limited to the contract price of the building; and the other class, where the bond and contract have not been filed, in which case the liens, other than that
The respondents in this action, having performed labor and furnished materials under a contract between the owner and contractor, are entitled to liens for such labor and materials; and as such contract was a valid contract, their liens relate back to the date of the commencement of the work upon the building. Their liens are, therefore, prior to that of appellant’s mortgage, which was not filed for record until after the commencement of said work.
[6] Appellant makes a further contention that respondents, in order to perfect their liens or to give them any vitality whatever, were required to file their respective claims' of lien for record within thirty days after they had respectively furnished their last work and material. We think this contention is answered by section 1187 of the Code of Civil Procedure, which provides for the time of filing claims of lien. In a recent decision our supreme court has held in a case where the contract between the owner and com tractor had not been filed as required by section 1183, as amended in 1911, that a claim of lien filed within thirty days after the filing of notice of completion is sufficient, provided ninety days have not elapsed from the daite of actual completion. (Bird v. American Surety Co., 175 Cal. 625 , 631 [ 166 Pac. 1009 ].) Respondents, in filing their claims, met the requirements of said section 1187 as construed by this decision of our supreme court.
For the reasons hereinbefore expressed, judgment is affirmed.
Conrey, P. J., and Houser, J., concurred.
Cases cited
- McClain v. Hutton 131 Cal. 132 p. 5
- Roystone Co. v. Darling 171 Cal. 526 p. 7
- Bird v. American Surety Co. of New York 175 Cal. 625 at 631 p. 9