Majority
Headnote
[1] Contracts—Mutuality—Excavating Work—Reservations—Option,-—Although a contract for excavating work bound the contractor to complete the contemplated work, while the other party-reserved the right to terminate it at any time and for any unforeseen reason, the contract was not void for want of mutuality after the contractor completed the work and the stipulated payments therefor had been made, except the last, which was inPlaintiff was given judgment for the sum of $834.90 as the balance due upon a contract for making certain excavations in the construction of a stadium for defendant and has appealed therefrom, contending that a much larger balance is due. Appellant’s principal contention is that the findings are not supported by the evidence in that no “binding contract between the parties” was proved and that, even assuming that there was a binding contract, “yet the plans of construction were so materially deviated from ... on matters not contemplated within the terms of the contract that appellant is entitled to recover upon a quantum meruit.” It is conceded that the judgment is for the correct amount if the contract which the defendant attempted to prove is the measure of plaintiff’s right of recovery. Since the findings of the trial court from
About February 15, 1922, the defendant undertook the construction of a stadium in the shape of a horseshoe with the open end to the south, the surrounding embankment to be raised approximately 50 feet above the finished floor level with earth taken from within the inner line of the embankment, the floor to be about 250 feet wide by 850 feet long. W. A. Taylor was the authorized representative of the defendant and Myron Hunt was the architect of the structure. W. T. Ellington represented the plaintiff in most of the transactions between the parties, he and Herbert Francisco then being copartners, but subsequently forming the plaintiff corporation. He offered, in behalf of the copartnership, to do the contemplated excavating at 30 cents a cubic yard and Taylor agreed to that price, but stated that he “wanted him (Ellington) to make an accurate figure and submit a lump sum bid.” Ellington “said he had not figured it accurately enough,” that “it would require somewhere from two to three weeks for him to do it, and he didn’t have time to do it right then.” No “lump sum bid” was ever submitted, but it was agreed that plaintiff would “move on the job and go to it,” and work was commenced about February 20th with a small force. Plaintiff had a large force at work by March 20th and continuously thereafter until the excavations were completed. After the work was commenced Taylor received such instructions from defendant as to prevent the execution of a “lump sum” contract with plaintiff. It does not appear that either party thereafter expressed a desire to enter into such a contract, and it is a fair inference that the original understanding in that respect was abandoned by mutual consent. April 3, 1922, Taylor presented to Ellington for signature a proposed written contract, binding the plaintiff to “do all the excavation necessary in the construction of said stadium” for 30 cents per cubic yard, the yardage to be computed from the map of the premises provided by the architect “and the
“To W. A. Taylor and Rea P. Taylor: Copy to—M. J. J.
Mitchell, President Tournament of Roses Assn.
“Mr. W. F. Creller, Chairman Building Committee.
“Francisco and Ellington, Architects’ Superintendent.
“Referring to our memorandum A. 4216, Contract B. 3801, dated June 26th, 1922, regarding your settlement of extra items under your contract with Francisco and Ellington.
“After consultations with the Building Committee by both yourself and this office, we, in that memorandum, approved your allowing Francisco and Ellington a total added charge for various items as therein set forth, amounting to $9,000.00.
“The bill which they put in totaled something over $14,000.00. Other items in the bill were not allowed. After a further consultation today they convinced you and con
vinced me that there was a proper charge coming from them as the result of the change back to the original level of the bottom of the Bowl, from a level 2' higher, which latter level was contemplated at the time you made your agreement with them.
“You are authorized to make a settlement with them in full for all items not covered by the flat agreement to move dirt at 30/ per yard, providing they will accept, as they have agreed to accept, an additional $3,000.00, bringing their total bill exclusive of the 30/ figuring, up to $12,000.00.
“Our contract A 4210, dated June 22, 1922, authorized you to pay Francisco and Ellington the sum of $6,000.00 on account of extra charges as definitely set forth in this memorandum. You are hereby authorized to pay Francisco and Ellington the further sum of . . . $8,000.00 which, together with the $8,000.00 payment referred to above, brings the total payments on account of extra charges to $12,000.00 as set forth above.
“As stated to you in our Order of July 6th, being Memorandum A 4233, Contract B 3801, it is left to you to determine the rapidity with which you can afford to pay out these moneys and still protect yourself in the matter of the cash bond which you have put up with the Owner.
“It should be definitely understood and agreed between you and Francisco and Ellington, that the acceptance of this additional $12,000.00 binds Francisco and Ellington to the completion of all excavating as required or directed in connection with the Stadium, under their unit price of 30/ per cubic yard, plus only the additional, $12,000.00 authorized by this memorandum.
“Myron Hunt, Architect,
“By Myron Hunt.
“K. & O. B. July 6, 1922.
“Approved:
“Pasadena Tournament of Roses Building Committee,
“By W. F. Creller,
“Approved and accepted:
“Francisco and Ellington,
“By H. Francisco.”
[1] Appellant contends that the agreement of April 3d was void for want of mutuality in that it purported to bind the plaintiff to complete the contemplated work “but that respondent still reserved the right to terminate the work at any time and for any unforeseen reason.” If the question had arisen prior to performance there would be much force in appellant’s argument, but the contract has been executed by both parties. The plaintiff has completed the work and the defendant has made all stipulated payments therefor, except the last, which is in dispute because the plaintiff demanded a larger sum than provided by the contract, and the defendant has made no attempt to exercise its option to terminate the agreement. “Even contracts uni
Appellant contends that if it be held that the agreement of April 3d is valid, “even then the plaintiff is entitled to recover upon quantum meruit because of the changes made in the plans and specifications after the contract was entered into.” The contract of April 3d was supplemented by the agreement of July 5th, and appellant does not contend that any changes made prior to the latter date are material to the question under discussion. In appellant’s reply brief it is said: “Appellant contends the evidence shows that two changes were made about August 1st. (1) The south end of the field was shortened fourteen feet and widened thirty feet. (2) The south ends of the embankment were shortened approximately three hundred feet.” The evidence hereinbefore quoted shows that the first change mentioned was to the advantage of the plaintiff. In addition to the testimony already set forth, Rea P. Taylor, testified that at the July conference “it was stated that this increase in length of the tunnels had caused the increase in the yardage of the fill and that would necessitate putting more of the dirt in the wide part of the fill, leaving the toes of the fill to be filled in at a later date, from material excavated from the river channel that was then contemplated. . . . There was not enough fill called for in the original plan opposite the south end to take the dirt that was excavated from it; that was just a very small section of fill in there. Q. I know, but there was some bank to be filled there according to the plans? A. Comparatively small. Q. As it was finished, the lower ends of the horseshoe were practically not filled at all? A. Quite right. And at the meeting that this settlement was made, Mr. Hunt then had said that if we did not have sufficient earth to complete absolutely all that was shown in the drawings in the way of a fill, that the earth would be available to place on the south ends of the horseshoe . . . where there was no seats to go, that earth would be available from the wash they were to cut in there with their steam shovel. Q. That was to be filled in from the river channel which is outside of the stadium ? A. What it lacked was to be filled in from the river channel.
[2] The complaint consists of a general allegation of indebtedness for services performed. The answer and the findings are equally general. The foregoing evidence is amply sufficient to support the implied finding that there was no change in the plans and specifications after July 5th to the prejudice of the plaintiff or which released it from its agreement of that date binding it “to the completion of all excavating as required or directed in connection with the
The judgment is affirmed.
Thompson, J., pro tem., and Plummer, J., concurred.
Cases cited
- Marin Water & Power Co. v. Town of Sausalito 168 Cal. 587 at 600 p. 457
- North Confidence Mining & Development Co. v. Morrice 56 Cal. App. 145 at 149 p. 457