Majority
The parties to this action entered into a contract in writing whereby appellant agreed to construct for respondent at the city of Riverside two bungalows and a
The case was tried before the superior court, without a jury, and the trial court made findings from the evidence, enumerating 24 technical specifications, designated by letter from “a” to “x,” inclusive. Twelve of these it found had not been complied with, and also that the defendant had been damaged thereby in the sum of $1,213; it further found that $140.90 had been paid in addition to the $4,600 admitted by the complaint, and that the amount remaining unpaid was $946.10. Conclusions of law were signed and filed, reciting that the plaintiff was entitled to judgment for this latter amount, and judgment was rendered accordingly.
Finding numbered IV recites: “That said defects were caused by the want of proper care and attention of the plaintiff and the workmanship was not first class, and the material used in the construction of said houses and garage is not first class, and defects, omissions and changes from the plans and specifications pervade the whole of said structures, and the plaintiff has not performed his contract as agreed, and he did not substantially perform same, or attempt honestly and in good faith to perform the same; the defendant did not accept said houses as being constructed in compliance with said contract.”
The plaintiff made a motion for new trial on August 7, 1923, and on August 11th the defendant moved that the judgment be vacated, that judgment for costs be entered in his favor, that the plaintiff be denied any relief, and that the conclusions of law be amended to conform thereto. The latter motion was argued and submitted, and the trial court granted the same, striking out its former conclusions of law, “and substituting in lieu thereof the following: As a conclusion of law from the foregoing facts the court finds that the defendant is entitled to judgment, that the plaintiff
The plaintiff appealed from the first judgment upon the ground, among others, that he should have been awarded the full amount demanded, less $140, and that the judgment was not supported by the evidence. He also appealed from the judgment last entered upon the ground that the trial court was without power to alter its conclusions of law and judgment, or to do more than grant a new trial, which the defendant did not request. It is insisted by appellant that the substituted judgment is void for the reason that conclusions of law may under such circumstances be modified or amended only to conform to the findings of fact, whereas, as amended, the conclusion above quoted is contrary to the findings.
It is the theory of respondent, and was stated by the trial court in granting the motion to vacate the original judgment, that a builder acting in good faith may recover the contract price, notwithstanding slight and trivial defects or deviations from the specifications, and is not held to a strict and literal compliance therewith; but that there is no legal basis for one acting in bad faith to recover either a reasonable value of the services or the contract price less the damages.
The Code of Civil Procedure, in section 663 thereof, provides that a judgment of the superior court may be vacated and another and different judgment entered when the conclusions of law are incorrect or inconsistent with the findings of fact, and that in such event the conclusions of law shall be corrected and amended. It has been held that such a matter is properly reviewable in the trial court under said section, rather than by motion for new trial. (Elizalde v. Murphy, 11 Cal. App. 32 , 39 [ 103 Pac. 904 ].)
Therefore, we proceed to inquire, first, as to whether or not the plaintiff, under the finding that he failed to attempt honestly and in good faith to perform his contract substantially in accordance with agreed plans and specifications, but having received about two-thirds of the contract price, is entitled to judgment for the balance; and, second, as to whether or not under the facts presented such finding is warranted by the evidence.
The court found in the instant case that through want of proper care and attention the plaintiff failed to furnish first-class materials or workmanship; that he did not substantially perform or attempt to perform his contract honestly or in good faith, and that the defects complained of pervaded the whole of said structures. The rule above stated was followed, and a judgment for an alleged balance, after partial payment, was likewise denied in each of the following cases: Laidlaw v. Marye, 133 Cal. 170 [ 65 Pac. 391 ]; Merchant v. Hayes, 117 Cal. 669 [ 49 Pac. 840 ]; Lynip v. Alturas School District, 24 Cal. App. 426 [ 141 Pac. 835 ], It will be observed, however, that in those cases wherein all compensation was denied, the performance was not substantially complete or in compliance with the contract of the parties; there was a wilful and intentional departure, causing defects which were so essential, and so pervaded the whole structure, as substantially to defeat the object which the parties intended to accomplish.
From the whole record before us, it is apparent that the evidence does not support such a finding. The contract merely provided that Gale should “furnish all labor and materials for the erection and completion of two bungalows and garage house at 163 So. Monroe St., Riverside, Cal., according to plans and specifications as agreed for the sum of sixty-nine hundred dollars ($6900.00). Payments to be made in the following order, $2,300.00 when the buildings are roughed in, $2,300.00 when the plumbing and wiring is in and the buildings are plastered, $2,300.00 when completed.” It appears that the plans and specifications were crude, requiring in some instances technical measurements which, owing to other considerations, were impossible; patented
As was said in Connell v. Higgins, supra, and other cases cited, a literal compliance as to all the details is not requisite to recovery. The object which the parties intended to accomplish was not defeated, or materially affected, by the deviations or omissions of which complaint is made. The trial court specifically detailed and found upon the evidence before it about twelve items upon which the parties seriously differed, and that an expenditure of $5 to $218 in various instances, aggregating $1,213, would compensate the defendant for his damage. We are not at this point concerned with the accuracy of the individual findings as to damages. It is sufficient to say that the plaintiff did not abandon the contract, nor did he display a lack of honesty or of good faith, such as is contemplated by the decisions, holding that in such cases the contractor is entitled to nothing. The buildings were fully completed, and the results of plaintiff’s efforts, though not entirely satisfactory to the defendant, were accomplished by diligence, experience and the exercise of plaintiff’s best judgment under the circumstances.
Appellant next contends that the evidence was not sufficient to support the findings as to certain deductions for damages alleged by the defendant, that he should have been awarded the full amount prayed, less $140, and that the judgment first rendered should be reversed.
Upon final submission of the case, the trial court announced from the bench in the form of an opinion certain deductions for defects or omissions for which it decided that respondent should be allowed damages, stating that judgment would be given in favor of the plaintiff for $1,006.10, but directed that the defendant prepare findings and judgment. The findings submitted by respondent’s counsel varied in some respects, as to certain items, from those announced by the court, and as finally signed and filed the findings, conclusions and judgment awarded to the plaintiff the sum of $946.10. To these findings the plaintiff excepted, tendering other proposed findings, and thereafter moved for a new trial, which motion was not formally acted upon, but was denied by operation of law. The defendant, as already observed, moved the court that said judgment be vacated, and that judgment in his favor, for costs, be entered, which motion was granted.
It is but justice to the appellant to state that from the record before us it is obvious that he was confronted with a most complicated and difficult problem. There were various conferences between himself and respondent at which many of the details of the buildings were verbally agreed upon; no written specifications, other than mere typewritten notations of an admitted novice, were furnished; blue-prints, not drawn to scale, and drawings which simply approximated the measurements which he was required to follow, constituted all that he had before him as a guide, except a catalogue of ready-built houses containing pictures from which he was expected to gather ideas as to general design. Appellant testified that with these crude “specifications,” rough drawings, the catalogue, and remembering to the best of his ability previous oral agreements, he constructed the bungalows and garage. There is a sharp conflict in the testimony, however, as to what was actually agreed upon, as to
After the trial court announced judgment for the plaintiff and directed that findings be prepared accordingly, on the fifth day of July, 1923, plaintiff filed his memorandum of costs and disbursements. The findings and judgment were not signed and filed, however, until August 1, 1923. The defendant moved that the cost bill be stricken from the files, upon the ground that no judgment had been entered at the time the same was filed, which motion was granted. Section 1033 of the Code of Civil Procedure provides that the successful party must deliver to the clerk and serve upon the adverse party his memorandum of costs and disbursements within five days after notice of decision of the court. It has been held that the “decision” referred to by said section consists of the findings of fact and conclusions of law, signed by the court, and filed with the clerk. (Porter v. Hopkins, 63 Cal. 53 , 55; Mullally v. Irish-Ameriean B. Soc., 69 Cal, 559 , 561 [ 11 Pac. 215 ].) And that a
The findings are amended by striking out the language of Finding IY herein quoted. The judgment entered October 10, 1923, is reversed. The superior court is directed to enter a judgment in accordance with the views herein expressed, being in effect a re-entry of the judgment of August 1, 1923, and the order striking out plaintiff’s cost hill is affirmed.
Works, P. J., and Thompson J. concurred.
A petition for a rehearing of this cause was denied by the district court of appeal on June 1, 1928, and a petition by appellant to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on June 28, 1928.
All the Justices present concurred.
Cases cited
- Elizalde v. Murphy 11 Cal. App. 32 at 39 p. 532
- Connell v. Higgins 170 Cal. 541 at 556 p. 533
- Laidlaw v. Marye 133 Cal. 170 p. 533
- Marchant v. Hayes 117 Cal. 669 p. 533
- Lynip v. Alturas School District 24 Cal. App. 426 p. 533
- Porter v. Hopkins 63 Cal. 53 at 55 p. 537
- Sellick v. De Carlow 95 Cal. 644 p. 538