Majority
This is an appeal from a money judgment against appellant in the sum of $11,587. The judgment also denied relief sought by appellant by cross-complaint. The action arouse out of a construction contract entered into between appellant district, as owner, and respondent, as contractor. Respondent, Manual Smith, filed action, alleging that the district had breached its contract with him. The subject matter of the contract was the construction of a sanitary sewer in the town of Empire. It was admitted in the pleadings that a contract had been executed; that respondent had commenced the performance thereof in May of 1949 and had continued such performance through May, June and into July. Respondent alleged that he had performed services and supplied labor and furnished material in the sum of $49,281.94; that he had not been paid that portion of the amounts earned as fixed by the terms of the contract and that for such breach he was compelled to and rightfully did cease work. The contract contained the following provision:
“ (a) Not later than the 15th day of each calendar month the Owner will make a partial payment to the Contractor on the basis of a duly certified and approved estimate of the work performed during the preceding calendar month under this Contract, but to insure the proper performance of this Contract, the Owner will retain ten (10) percent of the amount of each estimate until final completion and acceptance of all work covered by this Contract: . . .
“(b) In preparing estimates, the material delivered on the site and preparatory work done may be taken into consideration.”
The controversy revolves around charges by the contractor that the owner through its engineer arbitrarily withheld progress payments due and that this withholding was motivated by bad faith of the district and its engineer, both of whom the respondent claimed embarked at once upon a course of conduct designed to run the contractor off the job.
The court found that while he was on the job the contractor furnished materials and rendered services to the district of the reasonable value of $28,969.55; that he had received payments totaling $17,382.18, and that the balance of $11,587.37 was owing and unpaid; that the district’s engineer prepared estimates of the work performed while it was going forward and was fully cognizant of the reasonable value thereof; that by the 15th of July, 1949, the sum of $23,175.65 was due, owing and payable from the district to the contractor and that this sum amounted to 90 per cent of the labor and materials which had been furnished by respondent on the job during May and June; that the appellant, acting through its engineer, had arbitrarily neglected and refused to certify the proper amounts for payment as provided by the contract and that appellant had knowingly withheld from the respondent greater amounts than authorized by the contract; that these excessive withholdings were made because the appellant had been without adequate funds to pay respondent the sums which were justly due him; that on June 22d respondent was paid $7,998.90 on account of work done during May; that on July 13th respondent was paid $9,883.28 on account of work done during June; that during those two months respondent performed work and furnished materials to the value of $25,493.21 and was entitled to be paid on account thereof $23,175,65, whereas he received in fact only $17,382.18, leaving a deficit of $5,793.47 due him at the end of those two months, after the making of just allowance for rightful withholdings; that on or about July 15th respondent had properly demanded payment of the sums so due and unpaid and that payment thereof had been refused; that by reason of such breach respondent had been prevented from continuing his work or completing the job and was now entitled to all sums withheld from the total earned; that respondent had given notice to appellant that unless the sums justly due were paid he would consider the contract breached and cease work; that he did
Primarily, this appeal presents the question of substantial support for the court’s factual findings above recited. The trial was lengthy, the documentary evidence received was voluminous, the testimony of the witnesses was grossly conflicting and the situation was shown to be one where from the very beginning the parties became antagonistic. In his first certificate, dated June 22d and covering the work of May, the engineer stated that labor and materials had been furnished to the total value of $13,331.50. He authorized payment of $7,998.90, which was 60 per cent of the stated value and his explanation was “Retention of 40% is recommended in lieu of incomplete work and clean-up not being made.” Respondent considered that this retention of 40 per cent was unjustified. He said, however, he considered the estimates of work done to be sufficiently accurate for progress payment purposes and made no formal protest, expecting the matter would be adjusted when the next payment was made. On July 13th the engineer made his second certificate, stating that the value of work and materials furnished during June amounted to $15,638.05 and he recommended payment of 60 per cent thereof amounting to $9,383.28, with the explanation that “Retention of 40% is recommended in lieu of incomplete work and clean-up not being made.” We have said that the engineer stated the values for the work of May and June. Neither certificate specifically states what period is covered, but the court found they did cover the work of May and June, respectively, and the record supports that finding, which is in harmony with the provisions of the contract. This time respondent objected violently to what he claimed were excessive and wholly unjustified withholdings. He stated the necessity
Respondent’s foreman in charge of the work attended a meeting of appellant’s board and protested the 30 per cent withholding. He asked the board if it had the money to pay what was due and the reply was negative. Several members of the board so stated. Said the witness: “The substance of the comments made by the board at that time shows they didn’t have the funds available.” The chairman of the board testified that at that meeting someone had said; “No, we haven’t got no money in the bank. We couldn’t pay you if we wanted to. ’ ’ The foreman testified that on the day following the board meeting he was on the job and talked to the engineer and asked him for the reason why the extra 30 per cent was withheld. The engineer replied: “The way I feel today I don’t give a continental damn if you ever get anything.” The foreman walked away, then came back and heard the engineer say to a subordinate: “They are entitled to more money. We are going to have to get more money. What is the matter, don’t they have the money? The subordinate said, “No, I don’t think they have,” and the engineer said, “Well, we will have to make arrangements to get the money, to get additional financing.” The foreman said that on the 15th of July he delivered the letter, demanding proper payment on pain of declaring a breach if it was not received, and no reply being made, they completed the work that had been started and left the job.
We have referred to enough to show that the evidence supports the court’s finding the appellant “acting through its Engineer unreasonably and arbitrarily neglected and refused to certify or approve the proper amount for payments as provided by said contract and that said Defendant knowingly withheld from the Plaintiff greater amounts than was provided for by said contract because at the time that said payments were due it was without adequate funds to pay the
Appellant contends that the engineer’s estimates actually favored respondent and that its proof of the amount of work done “not contradicted by the contractor” was binding on the trial court. As we have said, the evidence in this case is grossly conflicting throughout. Eespondent here is referring to errors of one sort and another appearing on the face of the various certificates and testified to by appellant’s witnesses. But there was testimony by respondent that as to the amount of work done the first two certificates were approximately correct. The trial court in its memorandum opinion referred to many of these conflicts and it is apparent that it both accepted and rejected parts of the testimony in support of both sides to the controversy. It is not for this court on appeal to say the trial court should have believed one witness over another.
Appellant contends that even if it paid less than it should have paid during the progress of the work, it would have been guilty of no breach since the respondent made no specific demand for payment. This contention cannot be sustained. The engineer’s estimates of the value of work done and materials furnished set the gross amount earned and there was no quarrel between the respondent and appellant upon that point while respondent was on the job. The controversy was over the fact that the engineer arbitrarily and falsely, as found by the court upon substantial evidence, withheld money due under the contract’s terms as to progress payments. It was not necessary for the contractor to make any specific demand that he be paid the gross amount shown to have been earned by the engineer’s estimate, less proper and honest withholdings. Furthermore, he did give notice that these withholdings were excessive, that the proper amount of money would have to be paid to him or he would cease work and that demand was refused. Under the circumstances the claim of appellant that it did not breach the contract cannot be supported for want of any specific demand.
Appellant asserts that an engineer’s estimate certifying
Appellant contends that it had a right to withhold all the amounts which it did withhold because of a provision in the contract reading as follows:
“The Contractor shall pay . . . (b) for all materials, tools, and other expendable equipment to the extent of ninety per cent (90%) of the cost thereof, not later than the 20th day of the calendar month following that in which such materials, tools, and equipment are delivered at the site of the project, . . . and (c) to each of his Subcontractors, not later than the 5th day following each payment to the Contractor, the respective amounts allowed the Contractor on account of the work performed by the respective Subcontractor, to the extent of such Subcontractor’s interest therein.
“In addition to the amount which the Owner may otherwise retain under the Contract, the Owner may withhold a sufficient amount or amounts of any payment or payments otherwise due to the Contractor, as in its judgment may be necessary to cover:
“(a) Payments which may be past due and payable for just claims against the Contractor . . . for labor or materials furnished for the performance of this Contract.
“(b) For defective work not remedied.
“(c) For failure of the Contractor to make proper payments to his Subcontractors. ’ ’
Appellant contends that the trial court erred in computing the amount withheld from the contractor which was in fact justly due, that in fact only a much smaller amount was due and that for that reason the breach of the contract of which
“ (a) The extent to which the injured party will obtain the substantial benefit which he could have reasonably anticipated;
“(b) The extent to which the injured party may be adequately compensated in damages for lack of complete performance ;
“(e) The extent to which the party failing to perform has already partly performed or made preparations for performance ;
“(d) The greater or less hardship on the party failing to perform in terminating the contract;
“(e) The wilful, negligent or innocent behavior of the party failing to perform;
“(f) The greater or less uncertainty that the party failing to perform will perform the remainder of the contract.”
We need not follow appellant through its discussion of this contention. The materiality of a breach is in the main a matter for the trial court to determine from all the facts and circumstances shown in evidence. (Gold Min. & Water Co. v. Swinerton, 23 Cal.2d 19 , 28 [ 142 P.2d 22 ]; Campbell v. Hauser Lbr. Co., 147 Wash. 140 [ 265 P. 468 , 470]; Williston on Contracts, rev.ed., § 841 n. 4.) We may refer to the circumstance, which the court undoubtedly considered, that is, the one having to do with the wilful, negligent or innocent behavior of the party failing to perform. As to this, the appellant says: ‘ ‘ There can be no question but that the District was innocent of any intention to inconvenience Manuel Smith, not to mention the entire absence of any intention to defraud Manual Smith.” Appellant’s quoted statement ignores completely the force and effect of the court’s findings as to its conduct in the matter. Its conduct was justifiably found to have been anything but innocent. We hold that the court was justified in determining that the appellant’s breach of its contract was material and justified the cessation of work by the respondent.
The judgment appealed from is affirmed.
Peek, J., and Sehottky, J., concurred.
A petition for a rehearing was denied August 31, 1954, and appellant’s petition for a hearing by the Supreme Court was denied September 30, 1954.
Cases cited
- Gold Mining & Water Co. v. Swinerton 23 Cal.2d 19 at 28 p. 73