Plaintiff, D. Fieri, hired the defendant, Guy L. Rosebrook, a licensed architect, to design a home, to supervise its construction, and to segregate the subcontracts of
The evidence is highly conflicting in many rfespects. There can be little doubt but that plaintiff originally retained defendant to design a house that was not to cost over $30,000, and that defendant represented that the type of house then desired could be built for that sum. The evidence shows that the plaintiff originally ordered a house substantially similar to one constructed by a neighbor, and which had been designed by defendant, and that defendant started to design such a house. The agreed fee for the plans was $800. The evidence also shows that while defendant was working on the preliminary sketches, the plaintiff and his wife ordered various changes. These involved substantial changes in design, larger and additional rooms, and more garage space. Defendant testified that he warned plaintiff on numerous occasions that, if the house were made bigger than originally intended, it would cost more money. The plans were drawn and the $800 fee
It is plaintiff’s contention, and he so testified, that construction started before complete plans had been prepared, that defendant awarded many subcontracts before such plans had been completed, and, as a result, made many changes in construction without informing plaintiff that they would substantially increase the cost of construction. Plaintiff testified that the house was half constructed before he discovered the cost was going to exceed $30,000. Defendant testified that
There were undoubtedly many major changes made in the house during the course of construction. An additional bedroom and an additional bathroom were added, as was a tile roof. A change in the floor level of the house made after construction had started added an additional $15,000. Defendant testified that these changes and many others were all made at plaintiff’s request, and the trial court so found.
When the house was completed it had cost $62,192. In addition to being very unhappy about this cost, plaintiff charged in his complaint that there were defects in the construction caused by negligent supervision of the work. The principal defect was rain leakage caused by an overload of concrete on a sun deck. This overload caused the deck to sag and caused the sliding door frames to bind, and also resulted in the flashings between the wall and the deck becoming ineffective in stopping leakage. It was because of these defects that the trial court allowed plaintiff a $2,500 setoff.
Appeal of Plainiiff
One of plaintiff’s major contentions is that the trial court committed prejudicial error in allowing defendant 4 per cent of the total construction cost for segregation of the contracts. Plaintiff points out that defendant at one time pleaded,[1] and certainly testified, that he had an express oral agreement for 5 per cent, but the trial court fixed the percentage at 4 per cent, which, he contends, must have been based on the reasonable value of such services. Plaintiff then points out that he was precluded from proving generally the reasonable value of such services, and contends that under such circumstances defendant had to recover 5 per cent or nothing at all.
. If it were true that the 4 per cent finding were predicated on the theory that such was the reasonable value of the services involved, then it would have been error to have prevented plaintiff from proving such reasonable value, but the court did not so base its finding. It found an express oral agreement to pay 4 per cent. If there was an express oral agreement fixing the percentage then, of course, the question of the reasonable value of such services was not in issue.
The finding that there was an express oral agreement fixing
* In his original answer and cross-complaint the defendant did plead an express oral contract of 5 per cent for these services. But a demurrer was sustained to the pleading, and the amended answer and cross-complaint omitted any reference to this percentage.
Plaintiff also contends that defendant testified that he was to receive 5 per cent (fixed by the court at 4 per cent) of the total of the segregated contracts, and contends that no evidence was introduced as to the total of such contracts. The trial court based the fee for these services on 4 per cent of the total cost of $62,192. The evidence shows that prior to trial defendant had submitted a bill for these services for $2,800, which is obviously somewhat less than 5 per cent but more than 4 per cent of the total cost of $62,192. This indicates to plaintiff that defendant calculated the segregated contracts on something less than the total construction cost. But the fallacy in this reasoning is that the only evidence in the record is that the entire job was done by segregated contracts. The records showed this was $62,192. Thus, the trial court properly relied on the total construction price as being the equivalent of the total of the segregated subcontracts.
The next major contention of plaintiff is that the 6 per cent figure should have been computed on $30,000 and not on $62,192. It is argued that the evidence shows that defendant was hired to draw plans and supervise the construction of a $30,000 house, and that the additional costs were incurred because of defendant’s claimed negligent failure to have complete and detailed plans at the time construction started. There is no merit to these contentions.
Defendant testified, and the trial court found, that the agreement was to pay 6 per cent of the total construction price. That finding is supported. The real question is, what caused the added costs ? Plaintiff testified that it was because detailed plans were not available. The trial court found that plaintiff “authorized and made substantial changes in the design of the premises and in the construction of the home
Plaintiff next objects to the claimed failure of the trial court to give plaintiff a $416.98 credit for having paid that sum to defendant for miscellaneous travel expenses. Defendant admits that he was paid this sum, but claims that this sum was included in the $2,800 found to have been paid by plaintiff and allowed as a setoff. That lump sum was not itemized in the findings, the court merely finding that $2,800 had been paid to defendant by plaintiff, and that such sum should be deducted from the total sum due defendant. Defendant had claimed $648.70 for expenses for his" automobile, telephone, etc., and the court refused to allow these to him. Thus, so far as the findings are concerned, no error appears. (See, generally, Swafford v. Goodman, 115 Cal.App.2d 105 [ 251 P.2d 680 ].) The record does not show that plaintiff objected to this finding or sought clarification. It is his duty to show error on the face of the record. This he has not done.
Plaintiff next points out that the fees totaling 10 per cent
Moreover, the trial court found it would cost plaintiff $2,500 to repair the defects in the sun deck. Presumably, that sum included some sum to pay for the proper supervision of the work. Therefore, plaintiff is not entitled to a further deduction of $250, because that would result in reimbursing him twice. There is no merit to this point.
Appeal of Defendant
The defendant attacks that portion of the judgment allowing the plaintiff a $2,500 setoff, that being the amount that the court found would have to be expended by plaintiff because of defendant’s faulty and negligent supervision of the construction of the sun deck. The precise finding is-. “That it is true that defendant and cross-complainant failed to exercise the standard of care of other architects in the community in the supervision of the construction of the sun deck and supports therefor resulting in certain defects in the construction thereof”; and that the reasonable cost of repairing such defects is $2,500. This sum was deducted from defendant’s fees. Defendant contends that no architect testified that, measured by the general standard of the care of architects, he was negligent. Without such evidence, so he claims, the award cannot stand. It is also claimed that the defects were caused by negligent performance by the
There is much evidence in the record in reference to the sun deck. An architect, an engineer, and various subcontractors testified that the sun deck had been constructed in a faulty manner. As a result it placed too much weight on the underpinnings, it sagged, the window and door frames were bent, and this caused a condition making the flashings ineffective to prevent leaks. The architect called by plaintiff as a witness testified that he had examined the sun deck and its supports; that there was an overload; that the deck was supported by a laminated beam held together with 16-penny nails; that “I don’t believe that nails are the proper connections for laminated beams. Therefore, I haven’t ever specified [them] ”; that “I believe the laminated beam should be held together, the lamination should be held together . . . with bolts.” He recommended that the wood beam, which had sagged under the weight of the concrete floor, should be replaced with a steel beam, and that such was “necessary.” He also testified that, according to his computations and in his opinion, stronger supports than the á" x 4" posts used should have been employed.
A licensed engineer experienced in construction was also called by plaintiff. He testified to water leakage caused by improper flashings between the deck and the house, and to the excessive weight of the slab.
The evidence need not be further explored. Certainly there was ample evidence to show faulty construction of the sun de.ck. Whether that was solely caused by the subcontractor’s negligence or was also caused by faulty supervision of the architect were fact questions. While the standard of care of an architect was not spelled out in so many words, the evidence shows how the deck should have been constructed, and that defendant, as supervising architect, did not require it to'be constructed in that fashion. The trial judge did not need an architect or other expert to tell him that proper architectural supervision and design had not been employed when the sun deck sagged and leaked. In such circumstances, at least a reasonable inference sufficient to support the finding arises that these results were attributable to the negligence of defendant. (See, generally, Goldberg v. Underhill, 95 Cal.App.2d 700 [ 213 P.2d 516 ].)
This case is primarily a fact case. Although the evidence was conflicting, the findings are supported by substantial
On both appeals the judgment is affirmed; each party to bear his own costs on these appeals, except that each party shall bear half of the costs of the transcripts on appeal.
Bray, J., and Wood (Fred B.), J., concurred.
A petition for a rehearing was denied November 19, 1954.