This is an action in which plaintiff secured a judgment for $7,822.02 and costs and a decree of foreclosure of a mechanic’s lien for work and labor done and performed and for materials furnished in the construction of an office building in San Diego. On June 25, 1954, plaintiff submitted a bid to the defendants (owner-builders) to furnish all labor and materials for the installation of suspended ceilings and acoustic tile work on the first and
On July 21, 1954, plaintiff and defendants entered into a subcontract agreement in writing wherein plaintiff agreed to do the acoustical tile work, including suspended ceilings, in all areas shown on the plans, and to furnish and install United States Gypsum perforated Auditone, mill finished with fire resistant paint, for the sum of $7,845. The use of sheetrock was not mentioned in the contract or in the second bid submitted by plaintiff and he had no knowledge of plans containing a specification that such sheetrock was required in the construction of the suspended ceilings when he started work on the contract on or about August 10, 1954.
On or about September 10,1954, after plaintiff had installed about 2,500 square feet of acoustical tile without the use of sheetrock, he was notified by the city that no further work was to be performed until the city had released the stop order. Berry then had a conversation with Sapp in which Berry informed Sapp of the stop order and Sapp said “Get down
Berry purchased sheetrock for the job and installed it throughout under the acoustical tile, pursuant to the building department’s orders, and when he again asked Sapp for a purchase order for the installation of the sheetrock, Sapp stated that he would talk to his brother about it and would then give him the order. When the work was completed on September 28, 1954, Berry presented his bills to Sapp covering $1,881.60 for %-inch sheetrock, $56 for sheetrock on a partition, $110 for 40 hours overtime, and $84.50 for sheet-rock on an equipment room ceiling, a total of $2,132.10. The defendants refused to pay for these items, claiming that it was not their responsibility to have the sheetrock installed. Defendants paid $2,000 on the original contract and refused to pay the balance or the extra items covering the sheetrock installation. Plaintiff then filed a notice of mechanic’s lien on November 10, 1954, and his amended complaint for foreclosure of this lien was filed February 3, 1955.
The trial court found, among other things, that the installation of sheetrock was not called for in the agreement of July
Appellants’ first contention is that the plaintiff has not proved performance, excuse for nonperformance or substantial performance and therefore may not recover the balance of the contract price. They state that the contract calls for the installation of “U. S. Gypsum, perforated Auditone, mill treated, with U. S. G. flame resistant paint”; that plaintiff failed to comply with this requirement in that, admittedly, the tile was not treated with flame resistant paint. However, the evidence shows that with the installation of sheetrock between the acoustical tile and the ceiling it became unnecessary to paint the tile with flame resistant paint to comply with the building regulations. The sheetrock was sufficient
In Thomas Haverty Co. v. Jones, 185 Cal. 285 , 289 [ 197 P. 105 ], it is held that in the case of building contracts, when the owner has taken possession of the building and is enjoying the fruits of the contractor’s work in the performance of the contract, if there has been a substantial performance thereof by the contractor in good faith, where the failure to make full performance can be compensated in damages to be deducted from the price or allowed as a counterclaim, and the omissions and deviations were not wilful or fraudulent and do not substantially affect the usefulness of the building for the purpose for which it was intended, the contractor may, in an action on the contract, recover the amount unpaid on his contract price, less the amount allowed as damages for the failure in strict performance.
In the instant case defendants filed no counterclaim and there is nothing in the record to indicate that plaintiff would not have painted the tile if the defendants had requested it or if it had been necessary. Under the circumstances shown, the trial court’s finding that plaintiff had fully performed his contract is supported by substantial evidence.
Appellants’ principal contention is that the trial court erroneously allowed plaintiff to recover for the installation of the sheetrock as an “extra.” This argument is untenable. The evidence shows that plaintiff’s bid of July 21, 1954, was submitted on the basis of the elimination of sheetrock installation. The contract signed on the same day made no reference to sheetrock and plaintiff had been informed by the building department that flame resistant tile installation would be sufficient. This fact was communicated to the defendants.
The amount and value of the extra work was sufficiently established by the introduction in evidence of the bills and invoices covering such work and material and the trial court’s finding that such labor and materials were furnished with the consent of defendants and at the reasonable market value at the current market prices for such labor and materials prevailing at the time in the city of San Diego is supported by the record. A trial judge possesses a sound discretion in fixing the reasonable value of services performed. (Collier v. Landram, 67 Cal.App.2d 752 , 759 [ 155 P.2d 652 ].) As is said in Nylund v. Madsen, 94 Cal.App. 441 , 445 [271 P.374]:
“ ‘In an action for services rendered the questions whether they were rendered, and if so, what is their value, are for the jury; and in the absence of evidence of the value of such services, or where the evidence leaves uncertain the amount plaintiff is entitled to recover, the jury may estimate their
value from their own judgment and knowledge on the subject,’ ”
Since there is substantial evidence in the record to support the findings of the trial court they cannot be here disturbed. (Berniker v. Berniker, 30 Cal.2d 439 , 444 [ 182 P.2d 557 ].) The judgment is affirmed.
Barnard, P. J., and Burch, J. pro tem.,[1] concurred.
* Assigned by Chairman of Judicial Council.
Cases cited
- Thomas Haverty Co. v. Jones 185 Cal. 285 at 289 p. 700
- Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council 128 Cal.App.2d 676 at 683 p. 701
- Wyman v. Hooker 2 Cal.App. 36 at 41 p. 701
- Nuttman v. Chais 101 Cal.App.2d 476 at 478 p. 701
- Collier v. Landram 67 Cal.App.2d 752 at 759 p. 701
- Nylund v. Madsen 94 Cal.App. 441 at 445 p. 701
- Berniker v. Berniker 30 Cal.2d 439 at 444 p. 702